The project team used its creativity to overcome floods and other obstacles to construction.


By John Caulfield, Senior Editor | November 14, 2019
The museum's west entrance

The west entrance of the museum is laid onto the landscape and inserted into the topography. All photos: Paul Colletti Photography/©IMEG Corp

Located at the base of the Gateway Arch, this underground museum explores seminal events in American history, such as the Louisiana Purchase and the Lewis and Clark expedition. The 46,000-sf addition and 100,000-sf renovation represented the facility’s first reconstruction work since the Museum of Westward Expansion opened in 1976.

The project team had to work mostly below ground and within the National Register–listed landscape. The Mississippi River flooded twice during construction.

The team traveled to Germany to review and approve the glass fabricator’s mockup of the canopy enclosure system for the new 2,000-sf west entrance. A reinforced cast-in-place post-tensioned concrete lid beam and slab system spans 80 feet over the museum addition.

Alper Audi and McCarthy Building Companies co-developed a concrete mockup with sensors that enabled the team to make sure that temperatures achieved during curing were within recommended tolerances for the 2,400 cubic yards of concrete that were used.

 

The mezzanineThe mezzanine features a giant map of North America where visitors can walk the path of explorers Lewis and Clark.

 

The project team routed ductwork and piping through a mechanical tunnel from the existing mechanical room to and through the exhibit level, up a vertical cast-in-place concrete chase in the mezzanine, and across an underground duct system at entry level.

MEP systems were overhauled and reconfigured, resulting in the removal of 11 of 15 heating units and adding new systems inside ground-level mechanical rooms for easier maintenance.

 

GOLD AWARD WINNER

BUILDING TEAM IMEG Corp. (submitting firm, ME, telecommunications engineer) National Park Service, Gateway Arch Park Foundation (owners) Michael Van Valkenburgh Associates (architect for City Arch River Initiative) Cooper Robertson (museum design architect) James Carpenter Design Associates, Trivers Associates (associate architects) Alper Audi (SE) KAI (PE) Castle Contracting (earthwork/utilities contractor) David Mason + Associates (CE) National Park Service Denver Service Center (PM) Eckersley O’Callaghan (façade engineer) Haley Sharpe Design (exhibit designer) Shen Milsom & Wilke (A/V) Tillotson Design Associates (lighting) Jaffe Holden (acoustics) Alpha Corporation (CM) McCarthy Building Companies (GC) DETAILS 146,000 sf Total cost $176.4 million Construction time April 2015 to June 2018 Delivery method Design-bid-build

Related Stories

Reconstruction Awards | Dec 19, 2019

BD+C's 2019 Reconstruction Award Winners

The Museum at the Gateway Arch, the Senate of Canada building, and Google, Spruce Goose are just a few of the projects recognized with 2019 Reconstruction Awards.

Reconstruction Awards | Dec 13, 2019

A manse makeover: The Dahod Family Alumni Center at the Castle

A 1915 castle on BU’s campus is carefully restored for alumni events.

Reconstruction Awards | Dec 13, 2019

Community effort: Rose Collaborative

This post-Katrina project has become a citadel of the arts and education in the Crescent City.

Reconstruction Awards | Dec 12, 2019

New flight pattern: Google, Spruce Goose

The hangar that once housed the Spruce Goose is adapted to meet a tech giant’s workplace needs.

Reconstruction Awards | Dec 10, 2019

Enter the world of deep time: David H. Koch Hall of Fossils

The new enclosed FossiLab gives visitors a glimpse into the exacting work of Smithsonian scientists and preservationists.

Reconstruction Awards | Dec 6, 2019

TWA Hotel at JFK International Airport: Home away from home

A dormant, 1960s-era flight center is converted into a snazzy hotel and conference facility.

Reconstruction Awards | Dec 6, 2019

Columbus Metro Library Hilliard Branch

Senior living clubhouse becomes a modern library in central Ohio.

Reconstruction Awards | Dec 5, 2019

The 428: St. Paul's office corner

A long-forgotten five-and-dime store becomes a  speculative office property in Minnesota’s capital.

Reconstruction Awards | Dec 4, 2019

The squeeze is on: The Revolution Hotel

Once a 1950s-era YWCA, The Revolution is now a hip new hotel in The Hub.

Reconstruction Awards | Dec 2, 2019

Hudson Commons: Over the top

A project team converts a 1960s industrial structure into a Class A office gem.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021