flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

AIA expands Documents-On-Demand service??

AIA expands Documents-On-Demand service??

Six new documents added, DOD offers nearly 100 contract documents.
 


By Posted by Tim Gregorski, Senior Editor | May 29, 2012

The AIA announced the inclusion of six new documents into its popular Documents-on-Demand service, which for nearly four years has offered PC, MAC and tablet users easy access to AIA Contract Documents’ cost effective contracts anytime and anywhere they have Internet access.

The latest additions, which bring the total number of documents available to 98, cover aspects of every common project delivery method the building industry uses to support construction and design projects.

The following documents have been added to AIA Documents-on-Demand:

  1. A141™–2004, Standard Form of Agreement Between Owner and Design-Builder
  2. ?2. A142™–2004, Standard Form of Agreement Between Design-Builder and Contractor ?
  3. 3. A441™–2008, Standard Form of Agreement Between Contractor and Subcontractor for a Design-Build Project?
  4. 4. B142™–2004, Standard Form of Agreement Between Owner and Consultant where the Owner contemplates using the design-build method of project delivery?
  5. 5. B143™–2004, Standard Form of Agreement Between Design-Builder and Architect ?
  6. 6. C441™–2008, Standard Form of Agreement Between Architect and Consultant for a Design-Build Project

Availability?AIA Documents-on-Demand is a free service. Users can purchase and download only the AIA Contract Document forms and agreements necessary for the project at hand with a price per document ranging from $6.95 to $21.95. Please visit: http://documentsondemand.aia.org.

More information about AIA Contract Documents can be found at www.aia.org/contractdocs. +

Related Stories

| Aug 11, 2010

Carpenters' union helping build its own headquarters

The New England Regional Council of Carpenters headquarters in Dorchester, Mass., is taking shape within a 1940s industrial building. The Building Team of ADD Inc., RDK Engineers, Suffolk Construction, and the carpenters' Joint Apprenticeship Training Committee, is giving the old facility a modern makeover by converting the existing two-story structure into a three-story, 75,000-sf, LEED-certif...

| Aug 11, 2010

Utah research facility reflects Native American architecture

A $130 million research facility is being built at University of Utah's Salt Lake City campus. The James L. Sorenson Molecular Biotechnology Building—a USTAR Innovation Center—is being designed by the Atlanta office of Lord Aeck & Sargent, in association with Salt-Lake City-based Architectural Nexus.

| Aug 11, 2010

San Bernardino health center doubles in size

Temecula, Calif.-based EDGE was awarded the contract for California State University San Bernardino's health center renovation and expansion. The two-phase, $4 million project was designed by RSK Associates, San Francisco, and includes an 11,000-sf, tilt-up concrete expansion—which doubles the size of the facility—and site and infrastructure work.

| Aug 11, 2010

Goettsch Partners wins design competition for Soochow Securities HQ in China

Chicago-based Goettsch Partners has been selected to design the Soochow Securities Headquarters, the new office and stock exchange building for Soochow Securities Co. Ltd. The 21-story, 441,300-sf project includes 344,400 sf of office space, an 86,100-sf stock exchange, classrooms, and underground parking.

| Aug 11, 2010

New hospital expands Idaho healthcare options

Ascension Group Architects, Arlington, Texas, is designing a $150 million replacement hospital for Portneuf Medical Center in Pocatello, Idaho. An existing facility will be renovated as part of the project. The new six-story, 320-000-sf complex will house 187 beds, along with an intensive care unit, a cardiovascular care unit, pediatrics, psychiatry, surgical suites, rehabilitation clinic, and ...

| Aug 11, 2010

Colonnade fixes setback problem in Brooklyn condo project

The New York firm Scarano Architects was brought in by the developers of Olive Park condominiums in the Williamsburg section of Brooklyn to bring the facility up to code after frame out was completed. The architects designed colonnades along the building's perimeter to create the 15-foot setback required by the New York City Planning Commission.

| Aug 11, 2010

Wisconsin becomes the first state to require BIM on public projects

As of July 1, the Wisconsin Division of State Facilities will require all state projects with a total budget of $5 million or more and all new construction with a budget of $2.5 million or more to have their designs begin with a Building Information Model. The new guidelines and standards require A/E services in a design-bid-build project delivery format to use BIM and 3D software from initial ...

| Aug 11, 2010

Opening night close for Kent State performing arts center

The curtain opens on the Tuscarawas Performing Arts Center at Kent State University in early 2010, giving the New Philadelphia, Ohio, school a 1,100-seat multipurpose theater. The team of Legat & Kingscott of Columbus, Ohio, and Schorr Architects of Dublin, Ohio, designed the 50,000-sf facility with a curving metal and glass façade to create a sense of movement and activity.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021