PPP gets the job done: Three-party deal saves time and money for client

Building Team Awards

PPP gets the job done: Three-party deal saves time and money for client

Bronze Award: Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project.


By Robert Cassidy, Executive Editor | June 20, 2019

The 330-room Hilton Des Moines Downtown was developed through a three-party public-private partnership. Inset: Pivotek delivers one of 300 bath pods use in the project. Photos: Michael Robinson.

Four years ago, The Weitz Company formed a public-private partnership with the city of Des Moines and Polk County, Iowa, for a $101 million hotel/convention center in downtown Des Moines.

Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project. The city and county formed the nonprofit Iowa Events Center Hotel Corp. to create a lease-purchase agreement for the property upon completion.

Weitz, DLR Group (design architect), RDG Planning & Design (AOR), and Raker Rhodes Engineering (SE) employed upfront planning to create parallel paths of construction. They used virtual reality to integrate 3D design models with the 3D construction model. The VR model served as a sales tool for Hilton and Greater Des Moines Convention & Visitors Bureau.

To address the shortage of skilled labor, Weitz, M/P engineer Waldinger, and Pivotek installed 300 bathroom pods that were built off site at Pivotek’s West Chester, Ohio, factory. This saved 11% in labor hours for each prefabbed bathroom and saved 7.5% in total construction costs.

 

Photo: Phillip Nicolino.

 

The team used 12 modular components—drain assemblies, PEX risers, aquatherm pressurized piping, framing, and pre-hardware doors. Weitz calculates the use of prefab components saved 3,750 trips to collect materials or remove trash from the job site.

The project was delivered 10 days ahead of schedule. Hilton took occupancy 30 days sooner than planned.+

 

Building Team — Submitting firm The Weitz Company (developer/design-builder) Owner Polk County, Iowa Hotel consultant Project Management Consultants Design architect DLR Group AOR RDG Planning & Design SE Raker Rhodes Engineering CE Snyder and Associates M/P The Waldinger Corp. EE Baker Electric Interior framing/finish Allied Construction Services

General information — Size 336,000 sf with conference space Cost $101 million Construction time April 2016 to March 2018 Delivery method Design-build lump-sum public-private partnership

 

Return to the Building Team Awards landing page

Related Stories

Building Team Awards | Jun 14, 2017

3D-printed office: Office of the Future

Dubai kicks off 3D-printing tech initiative with a novel office project.

Building Team Awards | Jun 14, 2017

A space for all: Lighthouse for the Blind and Visually Impaired

Nonprofit HQ fitout improves functionality, accessibility for blind and low-vision individuals.

Building Team Awards | Jun 13, 2017

Government campus reimagined: Intelligence Community Campus

Building Team converts 1940s campus into a sleek, modern home for U.S. intelligence agencies.

Building Team Awards | Jun 13, 2017

Secluded sanctuary: Alnoba leadership training center

Leadership training center becomes New England’s first Passive House building.

Building Team Awards | Jun 12, 2017

Circles and squares: Faena Arts Center

Silver Award: The Faena Arts Center’s forum is divided into two volumes, one a cylinder, the other a cube.

Building Team Awards | Jun 12, 2017

The right prescription: University of North Dakota School of Medicine & Health Sciences

Silver Award: North Dakota builds a new medical/health sciences school to train and retain more physicians.

Building Team Awards | Jun 12, 2017

Texas technopark: TechnipFMC John T. Gremp Campus

Silver Award: TechnipFMC’s new campus marks the start of a massive planned community in north Houston.

Building Team Awards | Jun 8, 2017

Quick turnaround: Partners HealthCare

Silver Award: A 2½-year project brings Partners HealthCare’s sprawling administrative functions under one roof.

Building Team Awards | Jun 8, 2017

Raising the bar: Zurich North American Headquarters

Silver Award: Forgoing a typical center-core design, the Zurich North America Headquarters rises 11 stories across three stacked bars.

Building Team Awards | Jun 8, 2017

Team win: Clemson University Allen N. Reeves Football Operations Complex

Silver Award: Clemson gets a new football operations palace, thanks to its building partners’ ability to improvise.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021