PPP gets the job done: Three-party deal saves time and money for client

Building Team Awards

PPP gets the job done: Three-party deal saves time and money for client

Bronze Award: Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project.


By Robert Cassidy, Executive Editor | June 20, 2019

The 330-room Hilton Des Moines Downtown was developed through a three-party public-private partnership. Inset: Pivotek delivers one of 300 bath pods use in the project. Photos: Michael Robinson.

Four years ago, The Weitz Company formed a public-private partnership with the city of Des Moines and Polk County, Iowa, for a $101 million hotel/convention center in downtown Des Moines.

Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project. The city and county formed the nonprofit Iowa Events Center Hotel Corp. to create a lease-purchase agreement for the property upon completion.

Weitz, DLR Group (design architect), RDG Planning & Design (AOR), and Raker Rhodes Engineering (SE) employed upfront planning to create parallel paths of construction. They used virtual reality to integrate 3D design models with the 3D construction model. The VR model served as a sales tool for Hilton and Greater Des Moines Convention & Visitors Bureau.

To address the shortage of skilled labor, Weitz, M/P engineer Waldinger, and Pivotek installed 300 bathroom pods that were built off site at Pivotek’s West Chester, Ohio, factory. This saved 11% in labor hours for each prefabbed bathroom and saved 7.5% in total construction costs.

 

Photo: Phillip Nicolino.

 

The team used 12 modular components—drain assemblies, PEX risers, aquatherm pressurized piping, framing, and pre-hardware doors. Weitz calculates the use of prefab components saved 3,750 trips to collect materials or remove trash from the job site.

The project was delivered 10 days ahead of schedule. Hilton took occupancy 30 days sooner than planned.+

 

Building Team — Submitting firm The Weitz Company (developer/design-builder) Owner Polk County, Iowa Hotel consultant Project Management Consultants Design architect DLR Group AOR RDG Planning & Design SE Raker Rhodes Engineering CE Snyder and Associates M/P The Waldinger Corp. EE Baker Electric Interior framing/finish Allied Construction Services

General information — Size 336,000 sf with conference space Cost $101 million Construction time April 2016 to March 2018 Delivery method Design-build lump-sum public-private partnership

 

Return to the Building Team Awards landing page

Related Stories

Building Team Awards | Nov 2, 2020

Fans come first at Allianz Field

The new home of the Minnesota United soccer club wins a Silver Award in BD+C’s 2020 Building Team Awards. 

Building Team Awards | Oct 24, 2020

Emory University Student Center wins the top award in 2020 Building Team Awards

Emory University Student Center wins the top award in 2020 Building Team Awards

Building Team Awards | Oct 22, 2020

Look up to the skies

The Mori Hosseini Student Union at Embry-Riddle Aeronautical University takes home a Silver Award in the 2020 Building Team Awards.

Building Team Awards | Oct 22, 2020

Judging a book by its cover

The New York Presbyterian David H. Koch Center wins a Silver Award in BD+C’s 2020 Building Team Awards.

Building Team Awards | Oct 21, 2020

Big Room equals big results

Tucson’s Banner University Medical Center is honored with a Gold Award in the 2020 Building Team Awards. 

Building Team Awards | Oct 21, 2020

New York’s STEM epicenter and career gateway

The CUNY New York City College of Technology Academic Building wins a Gold Award in BD+C’s 2020 Building Team Awards. 

Building Team Awards | Oct 20, 2020

Seamless speed to market drives Texas hospital’s growth

Learn why the Methodist Richardson Medical Center Vertical Expansion, in Richardson, Texas, was honored with a Gold Award in the 2020 Building Team Awards.

Building Team Awards | Oct 20, 2020

Winning with teamwork

The new home of the NBA’s Golden State Warriors, Chase Center, is honored with a Gold Award in the 2020 Building Team Awards.

Coronavirus | Oct 8, 2020

The Weekly show: Statue of Liberty Museum, emotional learning in K-12, LA's climate change vulnerability

The October 8 episode of BD+C's "The Weekly" is available for viewing on demand.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021