11 tips on how to install EV charging stations in multifamily housing

Multifamily Housing

11 tips on how to install EV charging stations in multifamily housing

A top sustainability expert gives the whys and wherefores of installing electric vehicle charging posts in your next multifamily enterprise.


By PAUL BERGERON, CONTRIBUTING EDITOR, MULTIFAMILY DESIGN+CONSTRUCTION | June 23, 2020
EV charging port at The Kensington, Boston. Photo:

EV charging port at The Kensington, Boston. Photo: Gustav Hoiland

Electric vehicle adoption is expected to grow at a 25% annual clip over next five years. That’s going to make the installation of electric charging stations a must at apartment communities in most major real estate markets. Having EV stations on your property can lift its value, help you retain residents, and give your marketers another plus to attract prospective renters in competitive multifamily markets.

For advice on how best to install EV charging stations in multifamily enterprises, we turned to Pete Zadoretzky, LEED AP O+M, Vice President – Sustainability, Bozzuto Management Company. The company owns and manages more than 250 apartment communities, about two-thirds of which have EV stations. Bozzuto recently was named Energy Star’s Partner of the Year–Energy Management for the fourth year in a row—the only 100% multifamily management company to do so.

 

THE TIME IS RIGHT FOR EV CHARGING PORTS IN MULTIFAMILY HOUSING

1. Start thinking now about EV charging stations.

Nearly half of respondents (48.6%) to our exclusive Multifamily Design+Construction “Amenities Survey 2019” said they had installed EV chargers  in multifamily projects, up from 42.0% in our 2017 survey. That means most multifamily developers and their project teams have yet to install EV charging stations.

“It used to be, developers would ask, How much? And when they saw the price, it was, Thanks, but no thanks,” said Zadoretzky, a Fitwell Ambassador. (A 2016 study in San Francisco found that the cost of installing 12 PV ports in a 60-space parking lot was about $860/port, $2,370/port for a retrofit.) According to Zadoretzky, sticker shock has all but evaporated as the cost to install and operate EV stations keeps coming down.

 

2. Do your homework early in the planning process.

Apartment owners and investors must take the pulse of local market EV demand. Zadoretzky said his company’s preferred charging-station provider, ChargePoint, helps him track the number of EV vehicle registrations at a given time in a given market. “You’ll find a big difference between the number of EVs in, say, suburban Pennsylvania compared to Northern Virginia,” where it’s much higher, he said.

 

3. Determine the right number of EV charging ports for your property.

“For new construction, it’s important to be thinking strategically about what makes sense when the property first opens and what, when, and how you will be able to increase your capabilities at that property as it matures,” Zadoretzky said.

There was a time when two ports were enough, he said. “Now, we have apartment communities delivering with dozens of stations,” said Zadoretzky. “You don’t want to lose a single lease because there aren’t enough charging stations.”

There’s no perfect yardstick, but the “Guide to EV-Ready Communities” suggests that about 10% of all parking spaces in multifamily housing complexes should be dedicated to charging electric vehicles.

 

4. Check out the plentiful equipment and supplier options.

 “Plug in America,” a resource site for all things EV, lists more than 50 manufacturers and installers; Energy Star profiles about 20. Blink Charging, ChargePoint, and SemaConnect are the best-known full-service providers for multifamily and mixed-use communities. Electrify America, EVGo, and Volta Charging are more common for the retail-facing side of mixed-use communities. Tesla has its own proprietary stations.

Do your homework, advised Zadoretzky. “Looking back on Bozzuto’s history with EV stations, we learned the hard way that not all equipment is created equal,” he said. “You get what you pay for.”

 

Electric vehicle charging station in an apartment complex

Electric vehicle charging station in an apartment complex: just tap to start the charging process. Photo: Courtesy ChargePoint

 

Zadoretzky said his company chose ChargePoint because it offered an open platform, fully integrated with Bozzuto’s property management software. The ports’ LCD screens and messaging functions are user friendly.

The stations are open to the public. EV drivers can locate a charging station by searching and getting alerts via the ChargePoint EV app or the PlugShare app, which lists more than 140,000 charging stations in the U.S. and Canada. Retail guests patronizing the mixed-use complex’s restaurants and stores can charge their EVs while they dine and shop; they pay via the ChargePoint app. “Apartment management companies love having cars visiting the property because it brings prospective residents onto the property,” said Zadoretzky.

A second option—at roughly one-third the price—provides an assigned space, one port per customer for the term of the lease, as long as the lessee has an electric vehicle. “It’s a stripped-down version,” Zadoretzky said. “It’s more efficient, but only one car can use it.”

 

DEVELOP YOUR SCOPE OF WORK FOR EV CHARGING PORTS

5. Dig into the physical demands of installing EV charging stations.

Initial costs should be baked into your project’s electrical contracting scope of work and budget. A lot of questions have to be answered, said Zadoretzky: How close will the EV spaces be to the electrical room? Will you have to run a lot of conduit? Will you need to expand the size of the nearest electrical panel from original design loads? If it’s a retrofit in, say, a garden apartment community, how much trenching needs to be done to lay the conduit? How deep will you have to dig? Will you have to dig through established landscaping? Through asphalt? If you’re installing the EV stations in a structured parking garage, will the installers need to x-ray the concrete?

As for the cost of installing EV chargers in existing apartment properties, Zadoretzky offered these crystal clear guidelines: “You can analyze numbers all you want, but we know for sure that it can cost three times or even five times more to build EV ports on an existing property compared to new development.”

 

6. Determine your operating costs.

“There’s no blanket answer to operating costs,” Zadoretzky said. Among the many variables to consider: Will the EV stations be installed in a  mixed-use project or a 100% residential one? Is parking assigned to the residents, or is the lot first come, first served? Is there a monthly parking fee for an assigned space? Is there a shortage of parking spaces in the complex? Will parking spaces have to be removed to make way for the ports’ electrical equipment? Will the EV chargers be located on the property or in an adjacent area?

Zadoretzky described a property Bozzuto manages in Boston. Its six ports consumed 19MWh over a 12-month period, at a rate of $0.135/kWh. “That’s about $2,550 for the year, or about $425/port,” he said. “A lot for a building amenity for sure, but a drop in the bucket of the overall building’s energy use—and a non-issue in most cases, as we are recouping the cost of electricity directly from our EV-charging residents.”

 

7. Look for financial subsidies and incentives.

Government subsidies at the federal, state, and local level can significantly reduce first costs.

“You need to check out any state subsidy programs and combine those with incentives from utility companies for real savings,” Zadoretzky said. “The subsidies vary from state to state, and they are constantly changing. Right now, Massachusetts has one of the best around—not quite 100%, but pretty close. Maryland has excellent state and utility incentives.” Zadoretzky said he’s been surprised that some cities, like Washington, D.C., and whole states (Florida, for example) offer no incentives at all.

According to RCLCO’s 2020 EV Charging Report, commercial incentives can be significant, often covering 50–100% of an EV charger’s hardware, make-ready, ongoing service costs, and station/infrastructure installation. For example, Colorado provides rebates to multifamily property owners for up to 80% of charging station cost. Hawaii will subsidize 100% of the cost of installation.

A 2018 industry survey by CleanTechnica revealed that about 16% of charging station installations obtained government subsidies totaling more than $1,000 per connector, while another 20% received benefits of less than $1,000 per port. But in California, various jurisdictions offer incentives ranging from $3,000 per port to as high as $10,000 for ports in affordable housing communities. A Colorado program offers $9,000 per port for Level 2 smart chargers. Check cleantechnica.com for state-by-state data.

 

8. Think ahead about the day-to-day management of EV charging stations.

Zadoretzky said Bozzuto’s EV partner, ChargePoint, provides a customer-facing app and a management-facing dashboard that produce real-time information for both property staff and residents. If, for example, a tenant has been using the charger for too long, the dashboard will alert the property manager, who can then ask the tenant to unplug and move the car. Or, the property manager could program the dashboard not to charge a new tenant for a stipulated period as part of the lease signing.

ChargePoint has a Wi-Fi–enabled solution that provides real-time diagnostic data to property management staff. It also tracks and reports carbon emissions data, which is crucial when sharing information with investors or in complying with mandated benchmarking ordinances, said Zadoretzky.

“They’re monitoring our stations 24/7/365. If something goes wrong, their team is there to support us, right away, he said. “That’s crucial.” Usually it’s just a matter of a FaceTime phone call between ChargePoint and a Bozzuto maintenance technician to fix the problem using the display screen on the port.

 

9. Don’t forget to play the sustainability card.

Properties can earn points toward LEED certification by providing charging stations to serve at least 2% of parking spaces. To qualify for LEED points, EV charging spots must be Level 2 or higher, connected to a network, capable of supporting demand response or time-of-use charging, and compatible with universal EV charging connectors.

 

10. Beef up your EV marketing and signage.

Zadoretzky said his company made a strategic decision that EV charging stations would be an extension of the apartment community’s brand, and that they must match the customer service levels residents expect from Bozzuto. The availability of EV charging ports should also be highlighted in the community’s marketing package and in the walking tour.

Zadoretzky said he’s amazed that Craigslist is the only apartment listing site that allows prospects to list the availability of EV charging ports. “At Bozzuto, we get an average of about two requests per month via searches for each of our properties that has EV stations,” he said.

At the property management level, Zadoretzky strongly recommended putting up clearly visible signage that identifies the EV ports to residents and guests. “EV owners do not want to come home to their apartment, only to find another car parked in the space with the EV charging port,” he said. “Apply penalties if you have to.”

 

'EV READY' CHARGING IS IN YOUR FUTURE

11. Bone up on “EV-ready” building code requirements.

An EV-ready code is one that requires that a building’s electrical capacity and other infrastructure to be ready to install charging posts if and when there is sufficient demand. According to EVConnect, EV-ready codes may require a certain percentage of parking spots to have:

  • A dedicated electrical circuit with sufficient capacity for each charging spot
  • Installation of the conduit and wire necessary to run electricity to EV charging spots
  • Electrical panels labeled “EV-ready” and positioned near where tenants will park
  • Preparation for EV charging at a certain percentage of parking spots in multifamily housing

Since 2017, Atlanta has required new multifamily communities to make 20% of parking spaces EV ready. St. Louis Park, a suburb of Minneapolis (2018 population: 49,039), requires 10% of all parking in new apartment complexes to be EV ready. In 2019, Seattle started requiring apartment projects with one to six units to have an equal number of EV-ready spaces; those with seven to 25 units must have at least six EV-ready slots, and those with more than 25 parking spaces must make 20% EV ready.

In January, the International Code Council approved a provision that, if implemented by states or local jurisdictions, will require multifamily projects with three or more than units to have one EV-ready parking space if there is only one parking spot; two EV-ready slots if there are up to 25 parking spaces; and 20% of total parking spaces (rounded up, if there’s a remainder) for apartment communities with more than 25 spaces.

 

TIME TO GET CHARGED UP

So, if you’re a newby to electric vehicles, when is the right time to start installing EV charging stations in your apartment communities? “The best time,” said Zadoretzky, “is before you even know you want one.”

 

THE DOE’S THREE LEVELS OF EV CHARGING PORTS

There are three major categories of EV chargers (sometimes referred to as EVSEs, for “electric vehicle supply equipment”), based on the maximum amount of power the charger can provide to the battery.

  • Level 1 Uses a 120-volt AC plug. Delivers 2–5 miles of range per hour of charging. Used primarily in single-family homes.
  • Level 2 Provides charging through a 240-volt (for residential) or 208-volt (for commercial) plug. Requires installation of additional charging equipment. Can deliver 10–20 miles of range per hour of charging. The most common station type for multifamily communities.
  • DC Fast Charge Provides charging through 480-volt AC input. Requires highly specialized, high-powered equipment as well as special equipment in the vehicle itself. (Plug-in hybrid electric vehicles typically do not have fast-charging capabilities.) Can deliver 60–80 miles of range in 20 minutes of charging. Used most often in public charging stations.

Charging times range from less than 30 minutes to 20 hours or more based on the type of electric vehicle supply equipment in use, as well as the type of battery, how depleted it is, and its capacity.

 

Related Stories

| Aug 11, 2010

RMJM unveils design details for $1B green development in Turkey

International architecture company RMJM today announced details of the $1 billion Varyap Meridian development it is designing in Istanbul’s new residential and business district, which will be one of the "greenest" projects in Turkey. The luxury 372,000-square-meter development on a site totalling 107,000 square meters will be located in the Atasehir district of Istanbul, which the Turkish government intends to transform into the country’s new financial district and business center.

| Aug 11, 2010

Urban Land Institute honors five 'outstanding' developments in Europe, Middle East, and Africa

Five outstanding developments have been selected as winners of the Urban Land Institute (ULI) 2009 Awards for Excellence: Europe, Middle East, and Africa (EMEA) competition. This year, the competition also included the announcement of two special award winners. The Awards for Excellence competition is widely regarded as the land use industry’s most prestigious recognition program.

| Aug 11, 2010

10 tips for mitigating influenza in buildings

Adopting simple, common-sense measures and proper maintenance protocols can help mitigate the spread of influenza in buildings. In addition, there are system upgrades that can be performed to further mitigate risks. Trane Commercial Systems offers 10 tips to consider during the cold and flu season.

| Aug 11, 2010

Brad Pitt’s foundation unveils 14 duplex designs for New Orleans’ Lower 9th Ward

Gehry Partners, William McDonough + Partners, and BNIM are among 14 architecture firms commissioned by Brad Pitt's Make It Right foundation to develop duplex housing concepts specifically for rebuilding the Lower 9th Ward in New Orleans. All 14 concepts were released yesterday.

| Aug 11, 2010

NAVFAC releases guidelines for sustainable reconstruction of Navy facilities

The guidelines provide specific guidance for installation commanders, assessment teams, estimators, programmers and building designers for identifying the sustainable opportunities, synergies, strategies, features and benefits for improving installations following a disaster instead of simply repairing or replacing them as they were prior to the disaster.

| Aug 11, 2010

MulvannyG2 Architecture wins “Best Mixed-use Development—Future” award

MulvannyG2 Architecture’s project, Aquapearl in Taipei, Taiwan, was honored by Cityscape Asia 2009 as the “Best Mixed-use Development -Future” on May 20, 2009 at the annual conference in Singapore.

| Aug 11, 2010

REDD and Corcoran Group Real Estate developing eco-friendly boutique condos in Brooklyn's Vinegar Hill

REDD and Corcoran Group Real Estate are developing 100 Gold, a 10-unit boutique condominium complex in Brooklyn's Vinegar Hill that consists of (6) one bedrooms, (2) duplex studios—one with a private yard, and (2) penthouses—duplex apartments with one bedroom and loft, and private terraces.

| Aug 11, 2010

AECOM, Arup, Gensler most active in commercial building design, according to BD+C's Giants 300 report

A ranking of the Top 100 Commercial Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants

| Aug 11, 2010

Turner Building Cost Index dips nearly 4% in second quarter 2009

Turner Construction Company announced that the second quarter 2009 Turner Building Cost Index, which measures nonresidential building construction costs in the U.S., has decreased 3.35% from the first quarter 2009 and is 8.92% lower than its peak in the second quarter of 2008. The Turner Building Cost Index number for second quarter 2009 is 837.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021