Elgin Tower: Elgin's heart beats again

Reconstruction Awards

Elgin Tower: Elgin's heart beats again

A project team brings this Chicago suburb’s landmark tower back to life.


By David Barista, Editorial Director | December 3, 2018
Elgin Tower

The Elgin Tower has been successsfully converted into a 44-unit rental property. Photo: Skender

Completed in May 1929 as the headquarters for Home National Bank and Home National Savings and Trust, the 15-story Elgin Tower has had a tumultuous history. The Crash of ’29 forced the savings institution to declare bankruptcy. From that point on, the Art Deco building housed a wide range of owners and tenants, from Walgreens to the Elgin National Watch Company. Other than a short stint of prosperity in the late 1940s, the tower never achieved its promise as the city’s landmark commercial building.

Until now.

Working with the current owner, Capstone Development Group, the city of Elgin in 2016 endeavored to rehabilitate the historic tower as the centerpiece of its 20-year, $50 million downtown redevelopment plan.

“When this building was built, it signified the transition of Elgin from a rural town to a city,” said Elgin’s mayor, Dave Kaptain, referring to this suburban city of 112,000 northwest of Chicago. “That’s why it was so important that we preserve this building. This is the capstone.”

Contractor Skender and architect Webster Design were determined to save the building, which was added to the National Register of Historic Places in 2002 but had been condemned and partially destroyed by arson.

Using city/state tax increment financing and federal historic tax credits, the project team completed a 60,000-sf, $12 million gut rehabilitation that converted the office/retail building into 44 market-rate apartment units.

They salvaged original terrazzo in the corridors, refinished or recreated wooden landmark unit entries (formerly storefronts), repainted and patched all the plaster, installed elevators that would operate within the existing shafts, replaced exterior windows, and conducted a host of exterior façade treatments—tuck pointing, stone replacement, and abatement.

It was a logistical quagmire. With no alley, street-facing operations, or loading dock, the team had to file for multiple street closures. A hoist was only possible on the outside of the building to floor 11; there was no elevator service or hoist access on floors 11 through 15, so materials and supplies had to be carried by hand. New stairwells were cut between floors 1-3 and 11-14. Window replacement work required a 45- to 60-day approval process from both state and federal landmark commissions.

All the hard work paid off. For the first time in its long history, the Elgin Tower is at near capacity (90% occupancy at press time).

Said Weber Design’s Damon Femmer, AIA, LEED AP, “The heart of the city is beating again.”

 

 

Bronze Award Winner

BUILDING TEAM Skender (submitting firm, GC) Capstone Development Group (developer) Webster Design (architect) The WT Group (SE, MEP) DETAILS 60,000 sf Total cost $12 million Construction time April 2016 to December 2017 Delivery method Guaranteed maximum price

 

CLICK HERE TO GO TO THE 2018 RECONSTRUCTION AWARDS LANDING PAGE

Related Stories

Reconstruction Awards | Jan 6, 2021

University of Pennsylvania’s Stemmler Hall forgoes retrofit in favor of complete renovation

The Edward J. Stemmler Hall project has won a Bronze Award in BD+C’s 2020 Reconstruction Awards.

Reconstruction Awards | Dec 29, 2020

The reenvisioned Sazerac House: A delectable cocktail that's just perfect for the Big Easy

The 51,987-sf Sazerac House is an interactive cocktail museum, active distillery, corporate headquarters, and event venue, all under one roof, next to the historic French Quarter of New Orleans.

Reconstruction Awards | Dec 18, 2020

Can converting a landmark office to a clinic raise up a downtrodden Philadelphia neighborhood?

BD+C’s Reconstruction Awards recognize the adaptive reuse of the Kensington Trust building.

Reconstruction Awards | Dec 18, 2020

Spokane Riverfront Park U.S. Pavilion project creates a refreshed gathering place in Spokane

The project has won a Bronze Award in BD+C's 2020 Reconstruction Awards.

Reconstruction Awards | Dec 16, 2020

Voters resuscitate an abandoned high school in northern California

A 2014 bond issue provided financing to seismically stabilize and modernize Historic Alameda High School, a 2020 Silver Reconstruction Award winner.

Reconstruction Awards | Dec 14, 2020

Wyoming Capitol Square renovation project is all about the details

The Wyoming Capitol Square project has won a Gold Award in BD+C's 2020 Reconstruction Awards.

Reconstruction Awards | Dec 12, 2020

A famed dome of a historic glasshouse is revived to its rightful glory

Scaffolding played a critical role in the repair and restoration of the Enid A. Haupt Conservatory’s Palm Dome at the New York Botanical Gardens, a Gold winner of BD&C’s 2020 Reconstruction Awards

Reconstruction Awards | Dec 8, 2020

A synagogue in Toronto is renewed while preserving its history

Holy Blossom Temple is a Platinum winner in BD+C’s 2020 Reconstruction Awards.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021