2012 Reconstruction Award Platinum Winner: Building 1500, Naval Air Station Pensacola Pensacola, Fla.

2012 Reconstruction Award Platinum Winner: Building 1500, Naval Air Station Pensacola Pensacola, Fla.

The Building Team, led by local firms Caldwell Associates Architects and Greenhut Construction, had to tackle several difficult problems to make the historic building meet current Defense Department standards having to do with anti-terrorism, force protection, blast-proofing, and progressive collapse.


October 4, 2012
The historic naval facility at NAS Pensacola, Fla., required extensive renovatio
The historic naval facility at NAS Pensacola, Fla., required extensive renovation to adhere to military anti-terrorism/force pro
This article first appeared in the October 2012 issue of BD+C.

Building 1500 at Naval Air Station Pensacola, Fla., was constructed in 1939 as an Army barracks. Over the years, it was renovated a number of times and at one time served as the home of the Navy School of Photography. When funding became available under the American Recovery and Reinvestment Act of 2009, the Naval Facilities Engineering Command put together a design-build best value team to turn the vacant building into NAS Pensacola’s Base Command Headquarters.

The Building Team, led by local firms Caldwell Associates Architects and Greenhut Construction, had to tackle several difficult problems to make the historic building meet current Defense Department standards having to do with anti-terrorism, force protection, blast-proofing, and progressive collapse. Due to its location in a designated high-wind zone, the building also had to meet stringent wind load requirements.

Addressing anti-terrorism, force protection, and progressive collapse

Structural analysis of the exterior walls, which were constructed of terra cotta and finished with cement, determined that they could not meet anti-terrorism/force protection blast requirements or applicable wind-load standards. Given that the exterior could not be touched, AT/FP remedies had to be made from the inside out. The Building Team reinforced the interior face of the wall with six-inch-deep 18-gauge studs anchored into the terra cotta wall. Steel tracks at the base and head of the wall transferred loads into the existing concrete frame.

PROJECT SUMMARY


BUILDING 1500, NAVAL AIR STATION PENSACOLA
Pensacola, Fla.

Building Team
Submitting firm: Caldwell Associates Architects (architect)
Owner: Department of the Navy, NAVFAC Southeast
Interior design: Simpson Design Group
Structural engineer: Berube-Leonard
Mechanical/plumbing engineer: MEP Engineering Solutions
Electrical engineer: Klocke & Associates
Civil engineer: Fabre Engineering & Surveying
Fire protection engineer: FireLogix Engineering
Blast structural engineer: Simpson Gumpertz & Heger
General contractor: Greenhut Construction Co.

General Information
Size: 69,565 sf
Construction cost: $11,218,898
Construction time: October 2009 to November 2011
Delivery method: Design-build best value

Next, the team took on the replacement of the windows on the exterior walls. Any new windows had to be “historically consistent” with the original double-hung wood sash windows. The Building Team got approval to use aluminum sash windows that matched the sash profiles and glass-to-frame ratios, and a manufacturer (Graham Architectural Products) was able to produce windows that met AT/FP blast-resistance requirements.

Installing the windows to meet AT/FP demands was the next hurdle. Historic considerations dictated that the new windows be installed to the depth of the original windows in the existing masonry openings; however, doing so would not provide sufficient anchorage for blast and wind loads.

The Building Team devised a scheme that involved installing a steel frame and plate system on the interior side of the exterior wall to anchor the windows. They bolted tube steel jamb frames into the concrete frame at top and bottom and welded tube steel head and sill frames to the jamb pieces. Steel plate was welded to these frames to extend into the existing masonry window at the correct depth to allow the windows to be attached consistent with historic standards.

As for progressive collapse, the team determined that conventional steel or concrete reinforcement would be cumbersome and consume valuable space within the building shell, so they went to a carbon fiber reinforcement wrap over the existing concrete frame components, taking care not to allow penetrations into the system from other building infrastructure elements.

Not only is Building 1500 historic in nature, so is the archaeological site on which it sits. Early in construction, when post holes were being dug for the construction fence, the on-site archeologist consultant (required by the Navy) found artifacts of interest.

A full-blown archeological dig would have played havoc with the ARRA-based budget. As an alternative, the team dug “test pits” in a 5x5-meter grid across the site. Only a few areas requiring further excavation were discovered, and the project was able to proceed on schedule.

BD+C Reconstruction Awards Judge Daniel Moser, PE, summarized the project this way: “It was a really unique solution to solving the blast requirements while preserving the historic aspect of the building.” +

Related Stories

Construction Costs | Apr 18, 2024

New download: BD+C's April 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.

MFPRO+ New Projects | Apr 16, 2024

Marvel-designed Gowanus Green will offer 955 affordable rental units in Brooklyn

The community consists of approximately 955 units of 100% affordable housing, 28,000 sf of neighborhood service retail and community space, a site for a new public school, and a new 1.5-acre public park.

Construction Costs | Apr 16, 2024

How the new prevailing wage calculation will impact construction labor costs

Looking ahead to 2024 and beyond, two pivotal changes in federal construction labor dynamics are likely to exacerbate increasing construction labor costs, according to Gordian's Samuel Giffin.

Healthcare Facilities | Apr 16, 2024

Mexico’s ‘premier private academic health center’ under design

The design and construction contract for what is envisioned to be “the premier private academic health center in Mexico and Latin America” was recently awarded to The Beck Group. The TecSalud Health Sciences Campus will be located at Tec De Monterrey’s flagship healthcare facility, Zambrano Hellion Hospital, in Monterrey, Mexico.

Market Data | Apr 16, 2024

The average U.S. contractor has 8.2 months worth of construction work in the pipeline, as of March 2024

Associated Builders and Contractors reported today that its Construction Backlog Indicator increased to 8.2 months in March from 8.1 months in February, according to an ABC member survey conducted March 20 to April 3. The reading is down 0.5 months from March 2023.

Laboratories | Apr 15, 2024

HGA unveils plans to transform an abandoned rock quarry into a new research and innovation campus

In the coastal town of Manchester-by-the-Sea, Mass., an abandoned rock quarry will be transformed into a new research and innovation campus designed by HGA. The campus will reuse and upcycle the granite left onsite. The project for Cell Signaling Technology (CST), a life sciences technology company, will turn an environmentally depleted site into a net-zero laboratory campus, with building electrification and onsite renewables.

Codes and Standards | Apr 12, 2024

ICC eliminates building electrification provisions from 2024 update

The International Code Council stripped out provisions from the 2024 update to the International Energy Conservation Code (IECC) that would have included beefed up circuitry for hooking up electric appliances and car chargers.

Urban Planning | Apr 12, 2024

Popular Denver e-bike voucher program aids carbon reduction goals

Denver’s e-bike voucher program that helps citizens pay for e-bikes, a component of the city’s carbon reduction plan, has proven extremely popular with residents. Earlier this year, Denver’s effort to get residents to swap some motor vehicle trips for bike trips ran out of vouchers in less than 10 minutes after the program opened to online applications.

Laboratories | Apr 12, 2024

Life science construction completions will peak this year, then drop off substantially

There will be a record amount of construction completions in the U.S. life science market in 2024, followed by a dramatic drop in 2025, according to CBRE. In 2024, 21.3 million sf of life science space will be completed in the 13 largest U.S. markets. That’s up from 13.9 million sf last year and 5.6 million sf in 2022.

Multifamily Housing | Apr 12, 2024

Habitat starts leasing Cassidy on Canal, a new luxury rental high-rise in Chicago

New 33-story Class A rental tower, designed by SCB, will offer 343 rental units. 

boombox1 - default
boombox2 -
native1 -

More In Category

Mass Timber

Charlotte's new multifamily mid-rise will feature exposed mass timber

Construction recently kicked off for Oxbow, a multifamily community in Charlotte’s The Mill District. The $97.8 million project, consisting of 389 rental units and 14,300 sf of commercial space, sits on 4.3 acres that formerly housed four commercial buildings. The street-level retail is designed for boutiques, coffee shops, and other neighborhood services.


Construction Costs

New download: BD+C's May 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021