2012 Reconstruction Award Platinum Winner: Building 1500, Naval Air Station Pensacola Pensacola, Fla.

2012 Reconstruction Award Platinum Winner: Building 1500, Naval Air Station Pensacola Pensacola, Fla.

The Building Team, led by local firms Caldwell Associates Architects and Greenhut Construction, had to tackle several difficult problems to make the historic building meet current Defense Department standards having to do with anti-terrorism, force protection, blast-proofing, and progressive collapse.


October 4, 2012
The historic naval facility at NAS Pensacola, Fla., required extensive renovatio
The historic naval facility at NAS Pensacola, Fla., required extensive renovation to adhere to military anti-terrorism/force pro
This article first appeared in the October 2012 issue of BD+C.

Building 1500 at Naval Air Station Pensacola, Fla., was constructed in 1939 as an Army barracks. Over the years, it was renovated a number of times and at one time served as the home of the Navy School of Photography. When funding became available under the American Recovery and Reinvestment Act of 2009, the Naval Facilities Engineering Command put together a design-build best value team to turn the vacant building into NAS Pensacola’s Base Command Headquarters.

The Building Team, led by local firms Caldwell Associates Architects and Greenhut Construction, had to tackle several difficult problems to make the historic building meet current Defense Department standards having to do with anti-terrorism, force protection, blast-proofing, and progressive collapse. Due to its location in a designated high-wind zone, the building also had to meet stringent wind load requirements.

Addressing anti-terrorism, force protection, and progressive collapse

Structural analysis of the exterior walls, which were constructed of terra cotta and finished with cement, determined that they could not meet anti-terrorism/force protection blast requirements or applicable wind-load standards. Given that the exterior could not be touched, AT/FP remedies had to be made from the inside out. The Building Team reinforced the interior face of the wall with six-inch-deep 18-gauge studs anchored into the terra cotta wall. Steel tracks at the base and head of the wall transferred loads into the existing concrete frame.

PROJECT SUMMARY


BUILDING 1500, NAVAL AIR STATION PENSACOLA
Pensacola, Fla.

Building Team
Submitting firm: Caldwell Associates Architects (architect)
Owner: Department of the Navy, NAVFAC Southeast
Interior design: Simpson Design Group
Structural engineer: Berube-Leonard
Mechanical/plumbing engineer: MEP Engineering Solutions
Electrical engineer: Klocke & Associates
Civil engineer: Fabre Engineering & Surveying
Fire protection engineer: FireLogix Engineering
Blast structural engineer: Simpson Gumpertz & Heger
General contractor: Greenhut Construction Co.

General Information
Size: 69,565 sf
Construction cost: $11,218,898
Construction time: October 2009 to November 2011
Delivery method: Design-build best value

Next, the team took on the replacement of the windows on the exterior walls. Any new windows had to be “historically consistent” with the original double-hung wood sash windows. The Building Team got approval to use aluminum sash windows that matched the sash profiles and glass-to-frame ratios, and a manufacturer (Graham Architectural Products) was able to produce windows that met AT/FP blast-resistance requirements.

Installing the windows to meet AT/FP demands was the next hurdle. Historic considerations dictated that the new windows be installed to the depth of the original windows in the existing masonry openings; however, doing so would not provide sufficient anchorage for blast and wind loads.

The Building Team devised a scheme that involved installing a steel frame and plate system on the interior side of the exterior wall to anchor the windows. They bolted tube steel jamb frames into the concrete frame at top and bottom and welded tube steel head and sill frames to the jamb pieces. Steel plate was welded to these frames to extend into the existing masonry window at the correct depth to allow the windows to be attached consistent with historic standards.

As for progressive collapse, the team determined that conventional steel or concrete reinforcement would be cumbersome and consume valuable space within the building shell, so they went to a carbon fiber reinforcement wrap over the existing concrete frame components, taking care not to allow penetrations into the system from other building infrastructure elements.

Not only is Building 1500 historic in nature, so is the archaeological site on which it sits. Early in construction, when post holes were being dug for the construction fence, the on-site archeologist consultant (required by the Navy) found artifacts of interest.

A full-blown archeological dig would have played havoc with the ARRA-based budget. As an alternative, the team dug “test pits” in a 5x5-meter grid across the site. Only a few areas requiring further excavation were discovered, and the project was able to proceed on schedule.

BD+C Reconstruction Awards Judge Daniel Moser, PE, summarized the project this way: “It was a really unique solution to solving the blast requirements while preserving the historic aspect of the building.” +

Related Stories

Hotel Facilities | Apr 24, 2024

The U.S. hotel construction market sees record highs in the first quarter of 2024

As seen in the Q1 2024 U.S. Hotel Construction Pipeline Trend Report from Lodging Econometrics (LE), at the end of the first quarter, there are 6,065 projects with 702,990 rooms in the pipeline. This new all-time high represents a 9% year-over-year (YOY) increase in projects and a 7% YOY increase in rooms compared to last year.

Architects | Apr 24, 2024

Shepley Bulfinch appoints new Board of Director: Evelyn Lee, FAIA

Shepley Bulfinch, a national architecture firm announced the appointment of new Board of Director member Evelyn Lee, FAIA as an outside director. With this new appointment, Lucia Quinn has stepped down from the firm’s Board, after serving many years as an outside board advisor and then as an outside director. 

ProConnect Events | Apr 23, 2024

5 more ProConnect events scheduled for 2024, including all-new 'AEC Giants'

SGC Horizon present 7 ProConnect events in 2024.

75 Top Building Products | Apr 22, 2024

Enter today! BD+C's 75 Top Building Products for 2024

BD+C editors are now accepting submissions for the annual 75 Top Building Products awards. The winners will be featured in the November/December 2024 issue of Building Design+Construction. 

Laboratories | Apr 22, 2024

Why lab designers should aim to ‘speak the language’ of scientists

Learning more about the scientific work being done in the lab gives designers of those spaces an edge, according to Adrian Walters, AIA, LEED AP BD+C, Principal and Director of SMMA's Science & Technology team.

Resiliency | Apr 22, 2024

Controversy erupts in Florida over how homes are being rebuilt after Hurricane Ian

The Federal Emergency Management Agency recently sent a letter to officials in Lee County, Florida alleging that hundreds of homes were rebuilt in violation of the agency’s rules following Hurricane Ian. The letter provoked a sharp backlash as homeowners struggle to rebuild following the devastating 2022 storm that destroyed a large swath of the county.

Mass Timber | Apr 22, 2024

British Columbia changing building code to allow mass timber structures of up to 18 stories

The Canadian Province of British Columbia is updating its building code to expand the use of mass timber in building construction. The code will allow for encapsulated mass-timber construction (EMTC) buildings as tall as 18 stories for residential and office buildings, an increase from the previous 12-story limit. 

Standards | Apr 22, 2024

Design guide offers details on rain loads and ponding on roofs

The American Institute of Steel Construction and the Steel Joist Institute recently released a comprehensive roof design guide addressing rain loads and ponding. Design Guide 40, Rain Loads and Ponding provides guidance for designing roof systems to avoid or resist water accumulation and any resulting instability.

Building Materials | Apr 22, 2024

Tacoma, Wash., investigating policy to reuse and recycle building materials

Tacoma, Wash., recently initiated a study to find ways to increase building material reuse through deconstruction and salvage. The city council unanimously voted to direct the city manager to investigate deconstruction options and estimate costs. 

Student Housing | Apr 19, 2024

$115 million Cal State Long Beach student housing project will add 424 beds

A new $115 million project recently broke ground at California State University, Long Beach (CSULB) that will add housing for 424 students at below-market rates. The 108,000 sf La Playa Residence Hall, funded by the State of California’s Higher Education Student Housing Grant Program, will consist of three five-story structures connected by bridges.

boombox1 - default
boombox2 -
native1 -

More In Category

Mass Timber

Charlotte's new multifamily mid-rise will feature exposed mass timber

Construction recently kicked off for Oxbow, a multifamily community in Charlotte’s The Mill District. The $97.8 million project, consisting of 389 rental units and 14,300 sf of commercial space, sits on 4.3 acres that formerly housed four commercial buildings. The street-level retail is designed for boutiques, coffee shops, and other neighborhood services.


Construction Costs

New download: BD+C's May 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021