Rising above adversity: National Museum of African American History and Culture

Building Team Awards

Rising above adversity: National Museum of African American History and Culture

Gold Award: The Smithsonian Institution’s newest museum is a story of historical and construction resolve.


By John Caulfield, Senior Editor | June 7, 2017

Its striking cast-aluminum, 3,600-panel façade provides transparency into the museum’s above- ground interior space. Courtesy Brad Feinknopf.

This much-ballyhooed project, which sits on the last available lot within the National Mall in Washington, D.C., was first conceived 100 years ago. Its 56-month realization involved three GCs, four architects, more than 30 consultants, 200 subcontractors, and 5,000 craft workers.

At almost every turn, the Building Team faced obstacles, not the least being the District of Columbia’s high water table. Three-fifths of the museum is below grade, and its construction entailed a 70-foot-deep excavation of 350,000 cubic yards of dirt. The Building Team developed a support-of-excavation system that could withstand water pressure of 37,000 pounds per sf.

To meet the client’s request that all ground-floor and above-grade spaces be column free, the Building Team used four steel/cement structural cores to support the building’s superstructure and façade. 

 

Its below-ground attractions include a Contemplative Court, illuminated by natural light coming through an oculus onto a waterpool. Courtesy Brad Feinknop.

 

The museum, whose silhouette is designed to resemble a West African crown, is distinguished by “The Corona,” a striking curtain wall consisting of 3,600 panels, modeeld after ironwork in the American South. The original cast-bronze design was deemed too expensive, so the Building Team chose cast-aluminum panels that reduced the cost by $20 million. It also experimented with 20 colors and finishes to achieve the façade’s bronze tint.

Natural light streams through a 20-foot-diameter oculus into an underground Contemplative Court. Outside, a 200-foot-long porch, supported by two 32-ton columns, cantilevers 40 feet over a water feature.

The museum houses 36,000-plus artifacts and was literally built around two of them—an 80-foot-long Pullman railway car, and a guard tower from Louisiana’s notorious Angola Prison—that two 550-ton cranes lowered into place early in construction.

 

Building Team – Submitting firm, contractor: Clark Construction Group; Owner: The Smithsonian Institution; Architects: Adjaye Associates, Davis Brody Bond, SmithGroupJJR, The Freelon Group; Interior architects: Perkins+Will, Davis Brody Bond (below grade); Exhibit designer: Ralph Appelbaum Associates Structural engineers:   Robert Silman Associates (below grade), Guy Nordenson and Associates (above grade); MEP engineer: WSP USA; General contractor: Joint venture of Clark Construction, Smoot Construction, and H.J. Russell & Company' Construction manager: McKissack & McKissack; Landscape architect: Gustafson Guthrie Nichol

General Information – Size 409,000 sf Cost $413 million Construction time January 2012 to September 2016 Delivery method Design-bid-build

 

Return to the 2017 Building Team Awards landing page

Related Stories

Giants 400 | Aug 11, 2021

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400

Building Team Awards | Mar 12, 2021

2021 Building Team Awards Entry Information

Only new construction projects completed on or after January 1, 2020 are eligible. Deadline for submissions: May 14, 2021.

Building Team Awards | Mar 12, 2021

Deadline extended for the 2021 Building Team Awards

BD+C's Building Team Awards is the industry's only recognition program to honor projects that achieve excellence in both design/construction and collaboration of the AEC/O team. Deadline for entries: May 14, 2021.

Building Team Awards | Nov 4, 2020

12 projects earn BD+C's 2020 Building Team Awards

The Statue of Liberty Museum, Allianz Field, and the Long Beach Civic Center are three of the projects awarded with BD+C's 2020 Building Team Awards.

Building Team Awards | Nov 3, 2020

Birmingham's haven for the homeless

A coalition of ministries raised millions to build a new home for homeless men in Alabama’s largest city. The Firehouse Shelter wins Honorable Mention in the 2020 Building Team Awards.

Building Team Awards | Nov 2, 2020

It's back to the future for this contractor

Poettker Construction’s new headquarters in rural Breese, Ill., is recognized with a Bronze Award in BD+C’s 2020 Building Team Awards.

Building Team Awards | Nov 2, 2020

Long Beach gets a municipal marvel

The Long Beach Civic Center is honored with a Bronze Award in the 2020 Building Team Awards.  

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021