UC Riverside’s Plant Growth Environments Facility receives BD+C’s Bronze Building Team Award.


By John Caulfield, Senior Editor | December 3, 2021
UC-Riverside's new Plant Growth facility replaces 40-year-old greenhouses. Images: Paul Vu/Here and Now Agency
The construction of UC-Riverside's new Plant Growth facility was a textbook example of how the design-build process should work. Images: Paul Vu/Here and Now Agency

BRONZE AWARD

University of California, Riverside Plant Growth Environments Facility, Riverside, Calif.

 

Project Information

Project size: 31,500 sf

Project cost: $21,993,111

Construction time: May 27, 2019 – November 23, 2020

Delivery method: Design-Build

 

Building Team

Submitting firm: DPR Construction

Owner: University of California, Riverside

Architect: Perkins and Will

Structural engineer: Coffman Engineers

Mechanical engineer: TK1SC

General contractor and Construction manager: DPR Construction

 

Judges’ comments:

“Amazing design and construction efforts can be very simple in concept. This project provides an elegant, detailed, collaborative solution that utilized all of the talents of the builder.”

“The raw and honest materials tie in well to the project’s agrarian roots. The GC’s ability to supplement/take over the work of a sub-tier contractor that went under reinforced its team commitment to the project.”

Essay from submitting firm:

Throughout its history, UC Riverside has been associated with the agricultural and natural sciences. Its main campus includes a district of greenhouses that were built in the 1960s. Nearly four decades later, the design-build team of DPR and Perkins and Will, along with subcontractor Stuppy Greenhouse, was responsible for creating a state-of-the-art research facility that puts science at UC Riverside on display.

The design team looked at this project as an opportunity to continue the tradition of campus architecture and create a design that balances being a contextual building with programmatic and campus goals. These include a focus on sustainability, enhancing the greenways of the campus, and fostering the collaborative culture of the campus and program.

Raw materials for the project were chosen to honor the surrounding landscape.
The raw construction materials used on UCR’s Plant Growth Environments Facility were selected to provide an unvarnished look in honor of the simplicity and beauty of the landscape.
 

Goals and Objectives

The two-story facility on one acre replaced older greenhouses made from wooden slats. It was constructed with concrete walls on the first floor and glass-encased greenhouses elevated above. The design used the concrete façade as the enclosure, structure, shading, and thermal mass, which links the building systems to eliminate the need for insulation, relying purely on the concrete’s thermal characteristics.

Individual growth chambers on the first-floor house plants, pathogens, and insects in separate, controlled environments. Each greenhouse module on the top floor incorporates wireless technology to adjust its own temperature, humidity, and lighting, allowing an array of plants to grow there. The facility also includes laboratory and workspaces and is the first in a series of plant growth spaces planned to replace aging greenhouses at UC-Riverside. 

The raw construction materials used on the Plant Growth Environments Facility were selected to provide an unvarnished look in honor of the simplicity and beauty of the landscape.

Performance was imperative for this utilitarian building.
The building's interior design is utilitarian and performance-oriented.
 

BUILDING TEAM COLLABORATION

From the beginning of the project, the design-build team analyzed design, programming, and construction simultaneously. Concepts and solutions were assessed for design merit, functionality, constructability, and coordination. That team brought vetted ideas to design and planning meetings, through which it suggested a new planning strategy that resulted in a more than 15 percent increase of research space within the greenhouses, with no increase in cost or gross square footage.

Filling an unexpected labor gap

However, the project team faced a significant challenge when a sub-tier contractor that was slated to assist Kansas City-based design-build subcontractor Stuppy Greenhouse with the specialized greenhouse construction process went out of business. The team had to devise a way to get the project back on track and ensure it would be completed as planned and to the satisfaction of the owner.

DPR provided self-perform crews when a sub on this project went under.
DPR Construction provided self-perform crews after a sub on this project went out of business.
 

DPR provided self-perform crews when a sub on this project went under.

Facing the need for labor and crews to help erect the specialized greenhouse structure, DPR brought on its own self-perform carpenters to supplement Stuppy’s workforce, ultimately delivering about 10 percent of that subcontract volume. DPR’s self-perform concrete crews were responsible for delivering approximately 15 percent of the total project contract volume.

DPR superintendents were fully integrated into the subcontractor’s crews; likewise, DPR integrated Stuppy’s management team into the onsite project management team, according to project manager Paul Brown. “We took a ‘lean in’ approach to figure out a different way to get this done,” he said. “We brought everyone together to figure out a solution that would best serve the project.”

At the time work was to begin on framing the greenhouse, DPR’s concrete crew was on-site, completing the cast-in-place structure that would serve as the first-floor foundation for the glass building.

Managed material handling

The site was tight, with only one point of access and limited space between the site wall and finished concrete structure to receive and offload material. Because of the high risk of loading and offloading materials and the lack of a certified forklift driver on the part of the greenhouse vendor, DPR’s self-perform group pivoted to take on the scope of managing the hundreds of thousands of intricate pieces making up the state-of-the-art research facility.

“Given the small site and elevated work platform, material management was no small task,” said Damon Hole, who served as superintendent on the project.

Read about all Building Team Award Winners

Related Stories

Building Team Awards | Jun 11, 2019

Learning by doing: Students took an active role in the design of the Bay Area's d.tech high school

Gold Award: D.tech had been occupying temporary spaces that were hardly suited for design thinking.

Building Team Awards | Jun 10, 2019

Technology showcase: PTC's new digs combine lively workspaces with exhibits for its products and platforms

Gold Award: PTC began its fitout even as 121 Seaport was still under construction.

Building Team Awards | Jun 7, 2019

Fast delivery: Construction of McDonald's global headquarters was completed in under seven months

Gold Award: The building has a remarkably diverse array of spaces that include “work neighborhoods.”

Building Team Awards | Jun 7, 2019

Unifying force: A place where a million Tulsans can connect, one by one

Platinum Award: Gathering Place is a 66½-acre public park and playground serving the nearly one million residents of greater Tulsa, Okla.

Building Team Awards | May 24, 2018

Green machine: Janet Durgin Guild and Commons at Sonoma Academy

Honorable Mention: A college prep school gets an uber-green maker space and cooking lab.

Building Team Awards | May 24, 2018

Good neighbor: Wentz Science Center at North Central College

Bronze Award: A conscientious Building Team takes steps to minimize the impact of this large-scale science center project in a historic neighborhood.

Building Team Awards | May 23, 2018

13 projects earn BD+C's 2018 Building Team Awards

Iowa’s game-changing correctional institution and Chicago’s daring hotel and sports development are among 13 projects to earn honors in BD+C’s 2018 Building Team Awards.

Building Team Awards | May 23, 2018

Engineered for extremes: Talan Towers

Bronze Award: Astana’s shimmering mixed-use towers are made to stand up to the region’s harsh, long winters.

Building Team Awards | May 22, 2018

High-tech haven: The Spark at Washington State University

Silver Award: A ‘teaching in the round’ classroom highlights this innovation hub at Washington State University’s Pullman campus.

Building Team Awards | May 22, 2018

LA's game changer: Wilshire Grand Center

Silver Award: This billion-dollar mixed-use tower will alter the Los Angeles skyline in more ways.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021