Promise fulfilled: Park West, Texas A&M University

Building Team Awards

Promise fulfilled: Park West, Texas A&M University

Silver Award: A P3-driven team completes this mega off-campus student housing complex ahead of its fast-track schedule.


By David Barista, Editorial Director | May 21, 2018
Park West Aerial View
Park West Aerial View

Fifteen buildings, 2.2 million sf, 3,406 beds, spread across 47 acres. If the scale of the new Park West student housing development at Texas A&M University does not impress, then the pace of work just might. This massive project, built under a public-private partnership, was completed in just two years, much of it ahead of the original schedule.

The team employed a fast-track design-build delivery method that synchronized design with construction (sequenced east to west on the project site) to compress the overall schedule. Using this approach, combined with prefabrication techniques and Lean construction strategies, the project team determined that it could complete half of the flats buildings—representing 120 units, 216 beds—one year ahead of schedule (fall 2016). The second row of flats (216 beds) was turned over six months early (January 2017). This allowed the client, student housing development and property management firm Servitas, to open a sizable portion of the development early for leasing opportunities to Texas A&M students.

To further support leasing efforts, the project team modeled 1.4 million sf of the Park West development in a virtual environment. This allowed prospective tenants to take VR tours of the units and building amenities before construction was completed. The VR model also assisted with client decision making and advanced coordination among the various subcontractors, including structural, mechanical, electrical, and plumbing.

Located on the west side of campus, adjacent to the football stadium, Park West is designed as a self-contained community, with four shuttle bus stops, a convenience store, coffee shop, and a host of amenities: three pools, a jogging trail, three fitness centers, 50+ study lounges, and pet-friendly living. The centerpiece is a 50,000-sf rooftop lounge and deck, with a football field-sized pool, hot tub, and cabanas.

The team partnered with Texas A&M’s engineering and construction services departments to educate students on the project, by hiring interns, offering on-site learning, and guest speaking in the classroom.

“I had a vision that needed to be completed in a very small window of time to meet the demand Texas A&M University had for its growing student population,” says Rafael Figueroa, CEO, Servitas. “Weitz was the only firm with which I felt comfortable entrusting my company’s reputation, and they executed to perfection.”

 

More than 200 units were completed six months to a year ahead of the original schedule using prefabrication and Lean construction techniques. Jim Joham.

 

Building Team – Submitting firm, general contractor The Weitz Company Owner Servitas Architect PGAL Structural engineer SCA Consulting Engineers Mechanical, plumbing engineer Kilgore Industries Electrical engineer Power Design

General Information — Size 2.2 million sf Construction cost $252 million Construction time August 2015 to July 2017 Delivery method Design-build

 

Return to the 2018 Building Team Awards Landing Page

Related Stories

Building Team Awards | Jun 24, 2019

14 projects earn BD+C's 2019 Building Team Awards

The McDonald's Headquarters, the Rancho Los Amigos National Rehabilitation Center, and Pacific Visions at the Aquarium of the Pacific are three of the projects awarded with BD+C's 2019 Building Team Awards.

Building Team Awards | Jun 21, 2019

Up, up and away: Dutch hospitality chain completes the world's tallest modular hotel

Honorable mention: At 21 stories (15 of them modular), it is the world’s tallest modular hotel.

Building Team Awards | Jun 20, 2019

PPP gets the job done: Three-party deal saves time and money for client

Bronze Award: Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project.

Building Team Awards | Jun 20, 2019

Making waves: The façade of Pacific Visions suggests the movement of water, day and night

Bronze Award: The new wing holds an exhibition space, a state-of-the-art 300-seat theater with a 32-foot-tall, 180-degree arc, 130-foot-long projection wall.

Building Team Awards | Jun 19, 2019

Unsung heroes: Two hurricanes couldn't stop this project team

Bronze Award: St. Lucie County’s population exploded to the point where the hospital needed lots more space.

Building Team Awards | Jun 19, 2019

Crime fighter: San Diego County's new forensic facility helps battle crime in three ways

Silver Award: The 158,000-sf addition collocates three crime-fighting functions.

Building Team Awards | Jun 18, 2019

Eyesore no more: People come together to expand a much-needed daycare center

Silver Award: Two problems quickly emerged: high concentrations of arsenic in the soil, and stormwater runoff into nearby wetlands and neighboring properties.

Building Team Awards | Jun 17, 2019

Campus renewal: Community effort saves a crucial healthcare resource

Silver Award: Taylor Design (architect) and SmithGroup (AOR) led an integrated design-build team anchored by McCarthy Building Companies (GC).

Building Team Awards | Jun 13, 2019

In the spotlight: Kinder High School for the Performing and Visual Arts shines a new beacon on Houston’s downtown

Gold Award: Kinder High School, which can accommodate 750 9th through 12th graders, is one of only three public schools in the U.S. that offer programs for both visual and performing arts.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021