A performing arts center celebrates a legendary rocker and his birthplace

Building Team Awards

A performing arts center celebrates a legendary rocker and his birthplace

Buddy Holly Hall in Texas receives BD+C’s Silver Building Team Award.


By John Caulfield, Senior Editor | December 8, 2021
Buddy Holly Hall is the largest performing arts venue in West Texas. Images: Casey Dunn Photography
Buddy Holly Hall in Lubbock is the largest performing arts facility in West Texas, and is being used by several artistic organizations and the local school district. Images: Casey Dunn Photography.

 

SILVER AWARD

Buddy Holly Hall of Performing Arts and Sciences, Lubbock, Texas

Project Information

Project size: 218,000 sf

Project cost: $158 million

Construction time: April 2017 – February 2021

Delivery method: Alternate Financing and Procurement

Building Team

Submitting firm: Diamond Schmitt Architects

Owner/developer: Garfield/Public Private LLC

Client: Lubbock Entertainment and Performing Arts Association

Architect: Diamond Schmitt Architects

Architect of record: Parkhill

Associate architect: MWM Architects

Structural engineers: Entuitive, MWM Architects, Parkhill

General contractor: Lee Lewis Construction

Acoustics, AV, IT consultant: Jaffe Holden Acoustics

Mechanical engineers: Crossey Engineering, Parkhill

Plumbing engineer: Parkhill

Theater planners and consultants: Schuler Shook

Market and business planning consultant: Webb Management Services

Judges’ comments

“Collaborative mix of clients, as well as collaborative design/engineering team, are very impressive. Stair seemed to be a complex and impressive design solution.”

Essay from Diamond Schmitt Architects

Buddy Holly Hall, the largest performing space in West Texas, combines multiple user groups into one facility, including the Lubbock Independent School District, the Lubbock Symphony Orchestra, and Ballet Lubbock, along with a variety of professional touring productions.

Extensive stakeholder engagement

This project dates back to 2013, and was informed by a market study conducted by Schuler Shook that concluded that Lubbock’s existing buildings were not adequate to meet the community’s needs.

The project was abetted by extensive stakeholder and user engagement. Dozens of meetings and charrettes conducted with stakeholders helped to develop a blueprint about how to proceed. The client formed a 501(c)(3) ownership and fundraising entity, and engaged Garfield as the developer to select the building team. The project’s architect Diamond Schmitt came on board in 2014.

Project team collaboration

The decision to engage the building’s operator early in the design process was invaluable to the team delivering a design that was operationally efficient and cost effective. Periodic estimates were performed independently by the GC and a cost estimator. The developer, architect, and GC managed the change order process based partly on ROI analysis.

The project’s structural engineering team worked within one Revit model, and produced a consolidated set of construction documents. Another example of teamwork: the stage, where extensive rigging and lighting required additional performance steel for galleries, loft beams, catwalks, and the grid iron.

Collaboration was the key to reducing the cost of this project from its original estimate of $225 million. It also played a role in the decision of the Lubbock Independent School District to enter into a usage contract with Buddy Holly Hall rather than build its own stand-alone 70,000-sf performing arts center that would have cost the district $30 million.

Multipurpose facility

Buddy Holly Hall has numerous distinguishing features that include:

The Helen DeVitt Jones Theater inside Buddy Holly Hall.
The Helen DeVitt Jones Theater is a curved saddle shape that required manipulation of its structured steel framing.
 

•The 2,297-seat Helen DeVItt Jones Theater, with a 12,000-sf main lobby whose wall depicts the musician Buddy Holly playing his Stratocaster. The sculpture, by local artist Brad Oldham, weaves together 9,000 aluminum brushed bronze guitar picks into an image of the Hall’s namesake. Its balconies are framed with structural steel rather than concrete; this was only achievable through 3D modeling.

The theater is a curved saddle shape, and structural steel had to be bent to fit the curvature. Columns were placed in the back of the hall, which meant the balcony rakers cantilever out up to 31 ft 6 inches. The theater has been engineered to provide each theatergoer with an unobstructed view of the stage, and can be reconfigured for different programming.

The helical staircase inside of the hall.
A 56-ft-tall helix-shaped staircase runs through the Hall.
 

•A dramatic helical staircase in the main lobby is over 56 ft tall across three stories, and features a central spine that supports cantilevering stair treads that vary in length between 8 and 14 ft. The stair weighs about 145 tons, and is constructed from Hollow Structural Sections and steel plate. The HSS had to be bent in two directions to achieve the desired effect. The construction mitigated vibration through engineering and dampers.

•The Bird’s Tail, a 64x90-ft covered outdoor venue space, which is supported by only one column that splays out at four acute angles. (One of the Hall’s multipurpose rooms opens to the Bird’s Tail in the east.)

Extensive use of glass on the ground floor.
Ground-floor glass creates a seamless transition for visitors entering and leaving the building. Custom-tapered plate girders cantilever out 25 ft to form the main entrance canopy that supports the fins.
 

 

Trusses keep the main lobby column-free•The Hall’s use of glass at ground-level entrances creates an inviting and seamless transition for visitors coming and going. A truss that spans over 153 ft supports the roof and keeps the lobby column free. Hangers extend from the truss to support exterior cladding, a combination of solid panels and linear windows.

From the second level floor, custom-tapered plate girders cantilever out 25 ft to form the main entrance canopy that supports the fins.

•Targeting LEED Silver, the building’s façade balances various approaches to creating shade to counter Lubbock’s extreme temperature fluctuations. A long overhang, angled concrete trim, and deep set ribbon windows all act as architectural drapery to cool the building and filter light without obstructing the views of the wide vistas surrounding the Hall.

•The more intimate, 415-seat Crickets Theater, named after Buddy Holly’s band, has 53-ft-tall tilt-up concrete walls that are formed with acoustically determined horizontal waves on the interior that perform structurally and act as a finished surface.

 

Space for Ballet Lubbock
The Hall provides practice, rehearsal, and performance space for Ballet Lubbock.
 

•The Hall provides a 22,000-sf two-story home for Ballet Lubbock that has its own separate entrance, and includes a large rehearsal space, physical therapy room, offices, smaller practice area, and a digital interface for parents to watch their children practice.

The Hall also offers other flexible rehearsal and performance spaces, two multipurpose rooms, and a restaurant.

The Hall includes two multipurpose rooms and a restaurant.
This floor plan shows all of the Hall's many features, which include multipurpose spaces and a restaurant.
 

 

Related Stories

Building Team Awards | May 27, 2016

Big police academy trains thousands of New York's finest

The Police Training Academy in Queens, N.Y., consists of a 480,000-sf academic/administration building and a 240,000-sf physical training facility, linked by an aerial pedestrian bridge.

Building Team Awards | May 26, 2016

Cimpress office complex built during historically brutal Massachusetts winter

Lean construction techniques were used to build 275 Wyman Street during a winter that brought more than 100 inches of snow to suburban Boston.

Building Team Awards | May 25, 2016

New health center campus provides affordable care for thousands of Northern Californians

The 38,000-sf, two-level John & Susan Sobrato Campus in Palo Alto is expected to serve 25,000 patients a year by the end of the decade.

Building Team Awards | May 24, 2016

Los Angeles bus depot squeezes the most from a tight site

The Building Team for the MTA Division 13 Bus Operations and Maintenance Facility fit 12 acres’ worth of programming in a multi-level structure on a 4.8-acre site.

Building Team Awards | May 23, 2016

'Greenest ballpark' proves a winner for St. Paul Saints

Solar arrays, a public art courtyard, and a picnic-friendly “park within a park" make the 7,210-seat CHS Field the first ballpark to meet Minnesota sustainable building standards.

Building Team Awards | May 20, 2016

Pittsburgh's Tower at PNC Plaza raises the bar on high-rise greenness

The Building Team designed the 800,000-sf tower to use 50% less energy than a comparable building. A 1,200-sf mockup allowed the team to test for efficiency, functionality, and potential impact on the building’s occupants.

Building Team Awards | May 19, 2016

Chinatown library unites and serves two emerging Chicago neighborhoods

The 16,000-sf, pebble-shaped Chinatown Branch Library was built at the intersection of new and old Chinatown neighborhoods. The goal is for the building to unite the communities and serve as a catalyst for the developing area.

Building Team Awards | May 19, 2016

NYC subway station lights the way for 300,000 riders a day

Fulton Center, which handles 85% of the riders coming to Lower Manhattan, is like no other station in the city’s vast underground transit web—and that’s a good thing.

Building Team Awards | May 16, 2016

Upstate New York performing arts center revives once-toxic lakefront site

Early coordination, prefabrication, and judicious value engineering contributed to the accelerated completion of the Onondaga Lakeview Ampitheater, a Upstate New York design-build project.     

Building Team Awards | May 16, 2016

12 building projects that represent the best in AEC team collaboration

A busy, light-filled Manhattan subway station and a pebble-shaped Chicago library are among the winners of the 19th annual Building Team Awards. 

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021