SILVER AWARD
Buddy Holly Hall of Performing Arts and Sciences, Lubbock, Texas
Project Information
Project size: 218,000 sf
Project cost: $158 million
Construction time: April 2017 – February 2021
Delivery method: Alternate Financing and Procurement
Building Team
Submitting firm: Diamond Schmitt Architects
Owner/developer: Garfield/Public Private LLC
Client: Lubbock Entertainment and Performing Arts Association
Architect: Diamond Schmitt Architects
Architect of record: Parkhill
Associate architect: MWM Architects
Structural engineers: Entuitive, MWM Architects, Parkhill
General contractor: Lee Lewis Construction
Acoustics, AV, IT consultant: Jaffe Holden Acoustics
Mechanical engineers: Crossey Engineering, Parkhill
Plumbing engineer: Parkhill
Theater planners and consultants: Schuler Shook
Market and business planning consultant: Webb Management Services
Judges’ comments
“Collaborative mix of clients, as well as collaborative design/engineering team, are very impressive. Stair seemed to be a complex and impressive design solution.”
Essay from Diamond Schmitt Architects
Buddy Holly Hall, the largest performing space in West Texas, combines multiple user groups into one facility, including the Lubbock Independent School District, the Lubbock Symphony Orchestra, and Ballet Lubbock, along with a variety of professional touring productions.
Extensive stakeholder engagement
This project dates back to 2013, and was informed by a market study conducted by Schuler Shook that concluded that Lubbock’s existing buildings were not adequate to meet the community’s needs.
The project was abetted by extensive stakeholder and user engagement. Dozens of meetings and charrettes conducted with stakeholders helped to develop a blueprint about how to proceed. The client formed a 501(c)(3) ownership and fundraising entity, and engaged Garfield as the developer to select the building team. The project’s architect Diamond Schmitt came on board in 2014.
Project team collaboration
The decision to engage the building’s operator early in the design process was invaluable to the team delivering a design that was operationally efficient and cost effective. Periodic estimates were performed independently by the GC and a cost estimator. The developer, architect, and GC managed the change order process based partly on ROI analysis.
The project’s structural engineering team worked within one Revit model, and produced a consolidated set of construction documents. Another example of teamwork: the stage, where extensive rigging and lighting required additional performance steel for galleries, loft beams, catwalks, and the grid iron.
Collaboration was the key to reducing the cost of this project from its original estimate of $225 million. It also played a role in the decision of the Lubbock Independent School District to enter into a usage contract with Buddy Holly Hall rather than build its own stand-alone 70,000-sf performing arts center that would have cost the district $30 million.
Multipurpose facility
Buddy Holly Hall has numerous distinguishing features that include:
•The 2,297-seat Helen DeVItt Jones Theater, with a 12,000-sf main lobby whose wall depicts the musician Buddy Holly playing his Stratocaster. The sculpture, by local artist Brad Oldham, weaves together 9,000 aluminum brushed bronze guitar picks into an image of the Hall’s namesake. Its balconies are framed with structural steel rather than concrete; this was only achievable through 3D modeling.
The theater is a curved saddle shape, and structural steel had to be bent to fit the curvature. Columns were placed in the back of the hall, which meant the balcony rakers cantilever out up to 31 ft 6 inches. The theater has been engineered to provide each theatergoer with an unobstructed view of the stage, and can be reconfigured for different programming.
•A dramatic helical staircase in the main lobby is over 56 ft tall across three stories, and features a central spine that supports cantilevering stair treads that vary in length between 8 and 14 ft. The stair weighs about 145 tons, and is constructed from Hollow Structural Sections and steel plate. The HSS had to be bent in two directions to achieve the desired effect. The construction mitigated vibration through engineering and dampers.
•The Bird’s Tail, a 64x90-ft covered outdoor venue space, which is supported by only one column that splays out at four acute angles. (One of the Hall’s multipurpose rooms opens to the Bird’s Tail in the east.)
•The Hall’s use of glass at ground-level entrances creates an inviting and seamless transition for visitors coming and going. A truss that spans over 153 ft supports the roof and keeps the lobby column free. Hangers extend from the truss to support exterior cladding, a combination of solid panels and linear windows.
From the second level floor, custom-tapered plate girders cantilever out 25 ft to form the main entrance canopy that supports the fins.
•Targeting LEED Silver, the building’s façade balances various approaches to creating shade to counter Lubbock’s extreme temperature fluctuations. A long overhang, angled concrete trim, and deep set ribbon windows all act as architectural drapery to cool the building and filter light without obstructing the views of the wide vistas surrounding the Hall.
•The more intimate, 415-seat Crickets Theater, named after Buddy Holly’s band, has 53-ft-tall tilt-up concrete walls that are formed with acoustically determined horizontal waves on the interior that perform structurally and act as a finished surface.
•The Hall provides a 22,000-sf two-story home for Ballet Lubbock that has its own separate entrance, and includes a large rehearsal space, physical therapy room, offices, smaller practice area, and a digital interface for parents to watch their children practice.
The Hall also offers other flexible rehearsal and performance spaces, two multipurpose rooms, and a restaurant.
Related Stories
Building Team Awards | May 21, 2018
Campus builder: Everett University Center at Washington State University
Silver Award: WSU kicks off its new branch campus with a high-tech innovation center designed to engage students, businesses, and the community.
Building Team Awards | May 21, 2018
Promise fulfilled: Park West, Texas A&M University
Silver Award: A P3-driven team completes this mega off-campus student housing complex ahead of its fast-track schedule.
Building Team Awards | May 18, 2018
Prognosis: Positive: Rutgers University-Camden Nursing and Science Building
Gold Award: Can a new nursing school breathe life into America’s third-poorest city?
Building Team Awards | May 17, 2018
Patient priorities: Cleveland Clinic Taussig Cancer Center
Gold Award: Cleveland Clinic’s new cancer center is a transparent, collaborative hub for improved patient experiences and enhanced communication with caregivers.
Building Team Awards | May 16, 2018
Game, set, match: United States Tennis Association National Campus
Gold Award: With 100 courts and more than 260,000 sf of vertical construction, the USTA National Campus is a sanctuary for tennis enthusiasts.
Building Team Awards | May 15, 2018
High court, big impact: San Diego Central Courthouse
Gold Award: San Diego’s high-rise courthouse increases access to justice for citizens by consolidating 71 court departments.
Building Team Awards | May 14, 2018
Sweat equity marks landscaping effort
The design was grounded in therapeutic landscape and environmental psychology theory.
Building Team Awards | May 14, 2018
Rethinking prison design: Iowa Correctional Institution for Women
Platinum Award: Iowa's new women's correctional institution offers a revolutionary model for rehabilitating female inmates.
Building Team Awards | May 14, 2018
Dream delivered: McCormick Square Marriott Marquis and Wintrust Arena
Platinum Award: A daring hotel and sports development in Chicago’s South Loop aims to invigorate the city’s convention business.
Building Team Awards | Jun 14, 2017
17 projects earn BD+C's 2017 Building Team Awards
Of the 17 projects, one received a Platinum Award, six received Gold Awards, six received Silver Awards, two received Bronze Awards, and two received Honorable Mentions.