Denver sets the bar for water reclamation and reuse

Building Team Awards

Denver sets the bar for water reclamation and reuse

A new administration building for the city’s water utility company scores Platinum in BD+C’s 2021 Building Team Awards.


December 1, 2021
The new Denver Water Administration building brings wastewater management to a new level
Denver Water's new administration building brings water management and sustainability to new levels for that city. Images: Frank Ooms Photography

PLATINUM AWARD

Denver Water Administration Building, Denver, Colo.

 

Project Information

Project size: 186,930 sf

Project cost: $57 million (construction)

Construction time: January 2018-January 2020

Delivery method: Design-Bid-Build

 

Building Team

Submitting firm: Stantec Architecture Inc.

Owner: Denver Water

Architect, Interior design, Landscape architect, Lighting design: Stantec Architecture

Structural engineer: KL&A

Civil engineer: Martin/Martin

MEP engineer: IMEG

General contractor: Mortenson

Conceptual engineering, energy, daylight analysis: Integral Group

LEED facilitation: Ambient Energy

Judges’ comments

“The way the design team pushed the client’s thinking to evolve not just this building but the way the city thinks about water and sustainable design is commendable.”

“Excellent community mission and engagement. The new innovative design features required careful construction coordination and teamwork.”

“The exterior design is attractive in its sleek lines. It’s a prime example of water conservation in an area of the country that is desperate for examples. Combine that with the electrical savings with solar that will reduce forest fires based on electrical failures. The collaboration and willingness to be flexible among unions and agencies are noteworthy. Imagine taking children here to learn about the importance of water and changing [their] view of immediately reusing wastewater.”

ESSAY BY SUBMITTING FIRM:

Denver Water hired a diverse creative team to ensure the design of its new administration complex became a vehicle for change in both the building industry and regulatory landscape of the city and country. The complex is a showcase for innovative use of water reclamation via its on-site wastewater treatment and rainwater capture systems—a first-of-its-kind installation in Colorado. The project’s One Water approach will have broader social impacts, as Denver Water serves as a catalyst to push and redefine water stewardship across the arid west.

Denver Water’s new headquarters also is located strategically to act as a starting point for development within an otherwise industrial zone of the city, creating current and future connections to neighboring residential, arts, and higher education districts. 

 

On-site wastewater treatment system
Denver Water's on-site wastewater treatment system reuses every drop possible. Rendering: Courtesy of
Stantec Architecture

Project Goals and Objectives

The centerpiece of this project is the six-story, 186,000-sf administration building that forms the heart of Denver Water’s revitalized eight-building, 35-acre operations complex and workplace for nearly 700 employees. 

This LEED-NC Platinum certified building achieved net-zero energy within its first year of operation. The building’s sustainable features include an on-site wastewater treatment system; on-site solar; a radiant slab powered by the complex’s central utility plant to conserve heat and energy; a high-efficiency triple pane-glazed window system; displacement underfloor ventilation, and biophilic design.

Perhaps the most pioneering aspect of this campus revitalization, and particularly of the admin building, is how the client and design team addressed the goal of a sustainable approach to water use via a “One Water” holistic plan for water efficiency and reuse to promote the right water source for the right use.

The facility’s two most innovative One Water strategies are the rainwater capture for irrigation and on-site wastewater treatment and recycling for toilet flushing and irrigation purposes. The implementation of these systems is a first in Colorado, with Denver Water working to expand state regulations, clearing the way for other new developments to work on its own One Water solutions. In the context of Colorado’s restrictive water rights, going beyond standard practice involved not only innovative engineering, but changing an ecosystem of regulations. 

All black water generated in the building is collected in an underground tank west of the building where it receives treatment processing like a conventional wastewater treatment plant. The plants in the lobby planter beds act as wetlands providing additional filtration and nutrient removal. After final disinfection (UV and Chlorine) the purified water is used for flushing toilets, with any excess diverted for irrigation use. 

Sustainable design

 

Daylight pervades the new administration building
Ninety percent of the building's regularly occupied spaces are daylit.
 

The “One Water” concept minimizes consumption through efficiency whenever possible. The campus uses potable water treated and provided by Denver Water for potable requirements while maximizing reclamation and recycled water for other non-potable uses: The campus was designed to avoid using water for building cooling; no evaporative cooling was used, which is virtually unheard of for a campus this size.  

Carbon use reduction was another sustainability goal for the campus. Primary heating is accomplished through electrically driven heat pump compressors, eliminating on-site combustion while also increasing system operational efficiency. Campus Energy Recovery is utilized to achieve operational sustainability goals. A central heat recovery system, with 70,000 gallons of thermal storage, can achieve system coefficient of performance (COP) near 30 as energy is captured and distributed. 

To provide central heat pump system an energy source when energy recovery is not available, the Building Team tapped into the immense water volume flowing though Denver Water’s potable water conduit to create a variable temperature heat-sync.

Another key to achieving net zero energy was the installation of 1.3 MW producing photovoltaics on the building’s roof, parking garage, and employee parking carport.

The building also features myriad health and wellness elements: low VOC-emitting materials, a combination radiant slab/underfloor air system, the use of 100 percent outside air with carbon and MERV 13 filtration, and biophilic design principles that resulted in 90 percent of all regularly occupied spaces within the building being daylit.

A centralized waste management system helps support Denver Water’s goal of reducing the amount of solid waste going to the landfill by 25 percent from 2016 to 2020. This waste reduction goal extended to construction of the Operations Complex, which achieved over 80 percent waste diversion through reuse and recycling.

BUILDING TEAM COLLABORATION

 

A conference room in the new admin building.
Lean principles and rightsizing of rooms were at the forefront of this project's design.
 

Denver Water posed this challenge to the design team from the project’s onset: “If this facility is to demonstrate fiscal responsibility to our utility rate payers, and if it is to be replicable  for the development community to emulate, then it must be designed and constructed within range of a traditional facility’s budget, while still achieving its established water, performance, and wellness goals.”

Incorporating Lean principles and Workplace 2020 right-sizing methods, the architectural and interiors team worked closely with the client to control building size to 256 sf per occupant, while simultaneously accounting for legacy equipment downsizing, employee personal wellness, varied workplace typologies, and future needs over the next generation.

The design and construction teams identified priorities and challenges to be resolved with the owner during a series of visioning sessions, design charettes and planning procedures at all stages of design. This process developed myriad design strategies that balanced first cost limits with long-term performance and payback opportunities. Such collaborative planning resulted in a $200,000 cost savings for the project.

The team facilitated multiple building/campus automation control system meetings with the owner, contractors, equipment vendors, and commission agents to uncover best practices solutions and to established team-member continuity. The MEP team worked alongside the architects, landscape architects, and clients to make sure the water reclamation system is a visual educational opportunity for visitors to build awareness of water conservation strategies.  

There was also substantial community involvement, with local, city, and regional water officials brought into early project discussions. Stakeholders were solicited for their feedback on ways to improve the project’s design. (Denver Water intends to continue its community engagement via tours of the facility.)

In addition to full-service design, the integrated team assisted Denver Water in establishing its first full-time Sustainability Manager and Energy Manager positions. It also worked closely with the Denver Water legal team on pushing the One Water requirements through the legislative process, looked extensively at opportunities for public education of the entire process, and worked closely on even the most detailed aspects of the long-term energy management solutions for the administration spaces. These provided invaluable lessons learned on the importance of setting clients up for long term success in operating and managing the building systems in place to achieve any net zero goals, from energy to water to waste.

Read about all Building Team Award Winners

 

Related Stories

Building Team Awards | Oct 24, 2020

Emory University Student Center wins the top award in 2020 Building Team Awards

Emory University Student Center wins the top award in 2020 Building Team Awards

Building Team Awards | Oct 22, 2020

Look up to the skies

The Mori Hosseini Student Union at Embry-Riddle Aeronautical University takes home a Silver Award in the 2020 Building Team Awards.

Building Team Awards | Oct 22, 2020

Judging a book by its cover

The New York Presbyterian David H. Koch Center wins a Silver Award in BD+C’s 2020 Building Team Awards.

Building Team Awards | Oct 21, 2020

Big Room equals big results

Tucson’s Banner University Medical Center is honored with a Gold Award in the 2020 Building Team Awards. 

Building Team Awards | Oct 21, 2020

New York’s STEM epicenter and career gateway

The CUNY New York City College of Technology Academic Building wins a Gold Award in BD+C’s 2020 Building Team Awards. 

Building Team Awards | Oct 20, 2020

Seamless speed to market drives Texas hospital’s growth

Learn why the Methodist Richardson Medical Center Vertical Expansion, in Richardson, Texas, was honored with a Gold Award in the 2020 Building Team Awards.

Building Team Awards | Oct 20, 2020

Winning with teamwork

The new home of the NBA’s Golden State Warriors, Chase Center, is honored with a Gold Award in the 2020 Building Team Awards.

Coronavirus | Oct 8, 2020

The Weekly show: Statue of Liberty Museum, emotional learning in K-12, LA's climate change vulnerability

The October 8 episode of BD+C's "The Weekly" is available for viewing on demand.

Building Team Awards | Jun 24, 2019

14 projects earn BD+C's 2019 Building Team Awards

The McDonald's Headquarters, the Rancho Los Amigos National Rehabilitation Center, and Pacific Visions at the Aquarium of the Pacific are three of the projects awarded with BD+C's 2019 Building Team Awards.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021