Multiskilling can shorten construction schedules by as much as 38%
Multiskilling can shorten construction schedules by up to 38%, according to research by the Simplar Foundation, and that could alleviate strain on projects caused by a labor shortage in the U.S.
“By expanding workers’ skills and improving workforce flexibility, contractors can increase their capacity to meet growing construction demands without relying solely on an already-constrained labor market,” according to Associated Builders and Contractors’ analysis of the research.
“By investing in our craft professionals, expanding their skills and removing unnecessary barriers to using those skills, we can create more opportunity for workers and greater capacity for contractors to build America,” said Michael Bellaman, ABC president and CEO.
The report, Schedule Duration and Labor-Curve Outcomes Associated with a Multiskilled Labor Strategy, analyzed nearly 90,000 labor hours across 18 construction projects involving 11 contractors. Researchers examined project labor records to evaluate how multiskilled workers helped contractors match available skills to changing project needs, maintain workflow continuity, and manage daily staffing demands.
The report’s findings include:
- Shorter project schedules: Multiskilled crews completed work in 22% to 38% fewer workdays than a modeled single-trade labor strategy was estimated to require. Conversely, restricting workers to one trade required 28% to 62% more workdays to accomplish the same work.
- Improved workforce availability: On most project days (73%), relying on single-trade staffing would have left at least one trade without sufficient available labor compared to multiskilled crews.
- Greater staffing flexibility: A single-trade strategy required more than one-third additional staffing on the busiest project days, underscoring the value of workers with multiple skills who can adapt to changing project needs.
- Broader worker capabilities: Researchers documented 80 unique trade and skill combinations across 18 trades. Multiskilled workers performed an average of 3.2 different trades or skills over the course of their projects.