U.S. House moves to give Army Corps of Engineers management of V.A. projects

Healthcare Facilities

U.S. House moves to give Army Corps of Engineers management of V.A. projects

Bill would also put restrictions on planning and design funding.


By Peter Fabris, Contributing Editor | February 19, 2016
U.S. House moves to give Army Corps of Engineers management of V.A. projects

The 182-bed Aurora, Colo., hospital has incurred more than $1 billion in cost overruns. The Army Corps of Engineers has taken over the management of the project. Rendering: V.A.

The U.S. House of Representatives approved a bill that increases oversight and management of Department of Veterans Affairs projects costing more than $100 million. 

The bill would put management of these projects into the hands of the Army Corps of Engineers or other federal agencies. It would also require that the V.A. provide Congress with progress reports.

The legislation would also place financial restrictions on V.A. projects, with a 60-day notice requirement for planning and design funding. The House’s action came after concerns over mismanagement and cost overruns on a new V.A. hospital project in Aurora, Colo. That project is now expected to cost $1.7 billion — three times the original contract price — and is scheduled to open four years behind schedule in 2018. 

Investigators say the project’s problems stem from design changes, and the V.A.'s decision to use a complicated contract process. The bill also authorizes expansion of a Tampa, Fla., V.A. hospital, and provides $561.4 million for five other projects.

The bill will go to the Senate for a vote.

Related Stories

| Aug 11, 2010

Research Facility Breaks the Mold

In the market for state-of-the-art biomedical research space in Boston's Longwood Medical Area? Good news: there are still two floors available in the Center for Life Science | Boston, a multi-tenant, speculative high-rise research building designed by Tsoi/Kobus & Associates, Boston, and developed by Lyme Properties, Hanover, N.

| Aug 11, 2010

3 Hospitals, 3 Building Teams, 1 Mission: Optimum Sustainability

It's big news in any city when a new billion-dollar hospital is announced. Imagine what it must be like to have not one, not two, but three such blockbusters in the works, each of them tracking LEED-NC Gold certification from the U.S. Green Building Council. That's the case in San Francisco, where three new billion-dollar-plus healthcare facilities are in various stages of design and constructi...

| Aug 11, 2010

Holyoke Health Center

The team behind the new Holyoke (Mass.) Health Center was aiming for more than the renovation of a single building—they were hoping to revive an entire community. Holyoke's central business district was built in the 19th century as part of a planned industrial town, but over the years it had fallen into disrepair.

| Aug 11, 2010

Right-Sizing Healthcare

Over the past 30 years or so, the healthcare industry has quietly super-sized its healthcare facilities. Since 1980, ORs have bulked up in size by 53%, acute-care patient rooms by 77%. The slow creep went unlabeled until recently, when consultant H. Scot Latimer applied the super-sizing moniker to hospitals, inpatient rooms, operating rooms, and other treatment and administrative spaces.

| Aug 11, 2010

Great Solutions: Healthcare

11. Operating Room-Integrated MRI will Help Neurosurgeons Get it Right the First Time A major limitation of traditional brain cancer surgery is the lack of scanning capability in the operating room. Neurosurgeons do their best to visually identify and remove the cancerous tissue, but only an MRI scan will confirm if the operation was a complete success or not.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021