The kehoe iron works occupies a 6.3-acre site on the Savannah River, in the Savannah National Historic Landmark District. Built in 1873 and 1902 and closed in 1930, it was acquired by the Savannah Gas Company in the 1940s; it later sat unused for 28 years.
Twelve years ago, Georgia newspaper magnate and philanthropist Charles H. Morris purchased the site with the goal of turning it into a community asset.
In 2013, Morris’s Randolph Street Development firm brought in Lominack Kolman Smith Architects to lead the reconstruction. The five-year effort married three modern additions to Kehoe’s four historic buildings.
Three different shoring systems were used to restore the brick on the historic buildings. Toxic heavy metals from gas tanks on the site had to be remediated.
Entire sections of the machine shop’s corrugated metal cladding were missing; several rusted columns were dangling from trusses. Some historic columns were saved by splicing them with new base materials.
Photo: Richard Leo Johnson/Atlantic Archives.
To address the settling at one corner of one of the historic buildings, the structural and geotechnical engineers designed a system of concrete grade beams placed below the brick foundation wall; these were supported by helical piers to “carry” the brick wall.
A specialty metalworks fabricator recreated a historic walk baluster—part of the complex’s unusual Second Empire tower—based on an 1898 photo.
The new performing arts and events venue has a catering kitchen, a soundproof green room, conference spaces, and a teaching kitchen.
Since opening earlier this year, Kehoe Iron Works has hosted the Savannah Music Festival, Chamber of Commerce events, the Best of Savannah party, and an “American Idol” audition.
Photo: Richard Leo Johnson/Atlantic Archives.
Gold Award Winner
BUILDING TEAM Lominack Kolman Smith Architects (submitting firm, architect) Randolph Street Development (owner) Saussy Engineering (SE) Dulohery Weeks Engineers (MEP) Gueoming Lin (geotechnical engineer) New South Construction (GC, CM) DETAILS 19,782 sf Total cost $18.5 million Construction time June 2013 to November 2017 Delivery method Design-negotiate-build
CLICK HERE TO GO TO THE 2018 RECONSTRUCTION AWARDS LANDING PAGE
Related Stories
Reconstruction Awards | Dec 1, 2017
Rescue mission: Historic movie palace is now the centerpiece of Baltimore’s burgeoning arts hub
In restoring the theater, the design team employed what it calls a “rescued ruin” preservation approach.
Reconstruction Awards | Dec 1, 2017
Gothic revival: The nation’s first residential college is meticulously restored
This project involved the renovation and restoration of the 57,000-sf hall, and the construction of a 4,200-sf addition.
Reconstruction Awards | Dec 1, 2017
Rockefeller remake: Iconic New York tower is modernized for its next life
To make way for new ground-floor retail and a more dramatic entrance and lobby, the team removed four columns at the ground floor.
Reconstruction Awards | Nov 30, 2017
BD+C's 2017 Reconstruction Award Winners
Provo City Center Temple, the Union Trust Building, and the General Motors Factory One are just a few of the projects recognized as 2017 Reconstruction Award winners.
Reconstruction Awards | Nov 29, 2017
College credit: Historic rehab saves 50% on energy costs
The project team conducted surveys of students, faculty, and staff to get their input.
Reconstruction Awards | Nov 29, 2017
Amazing grace: Renovation turns a church into elegant condos
The windows became The Sanctuary’s chief sales edge.
Reconstruction Awards | Nov 28, 2017
Broadway melody: Glass walls set just the right tone for a historic lobby in Lower Manhattan
The adaptation of the 45,000-sf neoclassical lobby at 195 Broadway created three retail spaces and a public walkway.
Reconstruction Awards | Nov 27, 2017
Higher education: The rebirth of a Washington, D.C., high school
The project team, led by architect Perkins Eastman, restored the original cupola.
Reconstruction Awards | Nov 27, 2017
Bank statement: A project team saves a historic bank, yielding 100% leaseup for the developer
The project team had to fix poor renovations made in the ’50s.
Reconstruction Awards | Nov 27, 2017
Patient friendly: The University of Chicago Medicine Center for Care and Discovery adds 203 new beds
Strict infection control and life safety measures were implemented to protect patients on other floors as work proceeded.