Eyesore no more: People come together to expand a much-needed daycare center

Building Team Awards

Eyesore no more: People come together to expand a much-needed daycare center

Silver Award: Two problems quickly emerged: high concentrations of arsenic in the soil, and stormwater runoff into nearby wetlands and neighboring properties.


By Robert Cassidy, Executive Editor | June 18, 2019

The I CAN Center’s peeled-up canopy and rainscreen façade are clad in natural cedar. Photos: Yuzhu Zheng

The I CAN Child Care & Learning Center, Hampton, Va., is proof that good things come in small, economical packages. This 9,000-sf facility, built at a cost of $206/sf by Mark Turner Construction, a minority-owned CM firm, provides much-needed daycare primarily to families of local military personnel and shipyard workers.

Recognizing that I CAN had outgrown its previous facility located in a strip mall, the owners, a minority-run business, secured a long-abandoned site once used for vehicle auctions.

Two problems quickly emerged: high concentrations of arsenic in the soil, and stormwater runoff into nearby wetlands and neighboring properties.

The usual approach to remediating tainted soil would have been excavation and removal. To hold down costs, the project team elected to encapsulate the infected soil with additional landscaping and hardscape. As for the runoff problem, the team worked with city officials to reconfigure the site layout and convert large portions of impervious coverage into pervious area.

 

The new facility has eight classrooms with built-in AV and security systems, a library, office space, a kitchen, a staff break room, and play areas. Doors open at 6:30 a.m. to meet the needs of local military and shipbuilding families.

 

Cost-efficient finishes, such as seal concrete in the kitchen, kept the project on budget, but not at the cost of quality. Luxury vinyl tile, level 5 gypsum wallboard, solid surface countertops, vibrant artwork, energy-efficient windows and appliances, high-SEER HVAC, and water-saving plumbing fixtures speak to the quality of materials and construction.

The center serves children ages six weeks to five years. Since opening last fall, I CAN’s enrollment has gone up, and more teachers have been hired.+


Building Team — Submitting firm Mark Turner Construction (CM), Owner I CAN Child Care & Learning Center, Architect PMA, Inc., SE Speight, Marshall & Francis, MEP ENGINEER Hickman Ambrose, Inc.

General information — Size 9,000 sf, Construction cost $1.85 million, Construction time March 2018 to September 2018, Delivery method CM at risk

 

Return to the Building Team Awards landing page

Related Stories

Building Team Awards | May 27, 2016

Big police academy trains thousands of New York's finest

The Police Training Academy in Queens, N.Y., consists of a 480,000-sf academic/administration building and a 240,000-sf physical training facility, linked by an aerial pedestrian bridge.

Building Team Awards | May 26, 2016

Cimpress office complex built during historically brutal Massachusetts winter

Lean construction techniques were used to build 275 Wyman Street during a winter that brought more than 100 inches of snow to suburban Boston.

Building Team Awards | May 25, 2016

New health center campus provides affordable care for thousands of Northern Californians

The 38,000-sf, two-level John & Susan Sobrato Campus in Palo Alto is expected to serve 25,000 patients a year by the end of the decade.

Building Team Awards | May 24, 2016

Los Angeles bus depot squeezes the most from a tight site

The Building Team for the MTA Division 13 Bus Operations and Maintenance Facility fit 12 acres’ worth of programming in a multi-level structure on a 4.8-acre site.

Building Team Awards | May 23, 2016

'Greenest ballpark' proves a winner for St. Paul Saints

Solar arrays, a public art courtyard, and a picnic-friendly “park within a park" make the 7,210-seat CHS Field the first ballpark to meet Minnesota sustainable building standards.

Building Team Awards | May 20, 2016

Pittsburgh's Tower at PNC Plaza raises the bar on high-rise greenness

The Building Team designed the 800,000-sf tower to use 50% less energy than a comparable building. A 1,200-sf mockup allowed the team to test for efficiency, functionality, and potential impact on the building’s occupants.

Building Team Awards | May 19, 2016

Chinatown library unites and serves two emerging Chicago neighborhoods

The 16,000-sf, pebble-shaped Chinatown Branch Library was built at the intersection of new and old Chinatown neighborhoods. The goal is for the building to unite the communities and serve as a catalyst for the developing area.

Building Team Awards | May 19, 2016

NYC subway station lights the way for 300,000 riders a day

Fulton Center, which handles 85% of the riders coming to Lower Manhattan, is like no other station in the city’s vast underground transit web—and that’s a good thing.

Building Team Awards | May 16, 2016

Upstate New York performing arts center revives once-toxic lakefront site

Early coordination, prefabrication, and judicious value engineering contributed to the accelerated completion of the Onondaga Lakeview Ampitheater, a Upstate New York design-build project.     

Building Team Awards | May 16, 2016

12 building projects that represent the best in AEC team collaboration

A busy, light-filled Manhattan subway station and a pebble-shaped Chicago library are among the winners of the 19th annual Building Team Awards. 

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021