Data centers keep cool while staying hot-hot-hot

Data Centers

Data centers keep cool while staying hot-hot-hot

Cooling mission critical facilities efficiently is critical to their operations and profitability.


By John Caulfield, Senior Editor | July 25, 2018
Data centers keep cool while staying hot-hot-hot

The $28 million data center at St Jude’s Children's Research Hospital, Memphis. The project team for the three-story, 55,000-sf facility: Gensler (architect), Paradigm Structural Engineers (SE), Syska Hennessy Group (ME), Liles Energy Design Consultants (EE), Jensen Hughes (fire/life safety), and Flintco Inc. (GC). Photo: Joe Luther

Last January, Bcause LLC brought online a $65 million data center in Virginia Beach, Va., whose sole purpose is to mine Bitcoin. This is the largest cryptocurrency data center in North America. Bcause chose this location to serve Northern Virginia, the largest data center market in the U.S.

Last year, the U.S., Canada, Europe, and Asia Pacific absorbed 583.5 MW of new data center capacity. At least 400 MW more is under construction, according to JLL.

Over the past five years, data center construction has outpaced all other real estate categories, according to Site Selection Group. AEC firms active in the sector are enjoying the ride. Last year, the top five contractors in the sector put $4.4 billion worth of mission-critical facilities in place.

Ben Kaplan, SVP/GM of Turner Construction’s Global Critical Facilities Group, says demand for colocation data centers “remains quite strong,” even among cloud service providers that are building their own facilities. ("Colos" are data centers that rent server space to multiple entities.)

 

See also: Top 40 Data Center Architecture + AE Firms - 2018 Giants 300 rankings
See also: Top 55 Data Center Engineering + EA Firms - 2018 Giants 300 rankings
See also: Top 45 Data Center Contractors + CM Firms - 2018 Giants 300 rankings

 

One of Turner’s recent data centers, for colo/hybrid services provider QTS, is Project Joshua, a 445,000-sf greenfield building in Ashburn, Va., with 32 MW capacity, 180,000 sf in raised floor space, 60,000 sf of office and storage space, and reinforced walls that can withstand 125-mph winds.

 

One case where size really matters

Mega-facilities that exceed one million sf and 100 MW in capacity are impacting what’s getting built and where. Site Selection Group says seven of the biggest 13 centers under construction exceed a million square feet. In Huawei, China, a 4.3-million-sf data center is under construction.

Data center operator Raging Wire is building a 42-acre campus in Garland, Texas, that will house five buildings totaling one million sf and 80 MW of IT load. The first phase (201,000 sf, 16 MW), known as TX-1, was completed in June 2017. Page is providing master planning, architecture, MEP/FP design, interiors, and LEED consulting on the project.

John Major, AIA, Page’s Principal for Science & Technology, says the Raging Wire facility is unique in that its amenities are located at the center of the building. “Data centers aren’t typically workplaces,” he says. TX-1 incorporates Class A office space and hospitality-themed amenities to differentiate it from competitors and encourage prospective tenants to station dedicated teams at the facility.

Major says clients' approach to building mega–data centers seem to be shifting. While large campuses are certainly being developed, “the tranches of deployment have been scaled down dramatically to facilitate faster speed-to-market and lower first-tranche cost,” he says.

Speed-to-market and capital cost advantages have made constructing single-tenant data centers via third-party developers an “increasingly popular delivery model” for large technology users in cloud services and media offerings, note Gensler's Vaughn Lamar, LEED AP, Senior Associate and Project Architect, and Jackson Metcalf, LEED AP, Associate and Technical Designer.

Among such projects is Gensler’s work for St. Jude’s Children’s Research Hospital, Memphis, Tenn., which consolidated operations of three buildings. A new fiber ring around the campus provides faster service and better connectivity.

 

Controlling water use for cooling

Reliability, especially as a hedge against natural disasters, is paramount to any data center’s operations. The BBVA Technology Center, Atizapan, Mexico, provides critical IT support for the bank’s worldwide operations. Its location—on high ground at the edge of Mexico City, an active earthquake region—made it imperative that this 31,025-sm facility be designed to the highest levels of safety and redundancy.

Skidmore, Owings & Merrill, lead designer on this Tier IV data center, protected the building from seismic events through progressive collapse design strategies and a foundation isolator beneath the building, explains Kim Van Holsbeke, Associate Director in SOM’s New York office.

Data center operators are also paying close attention to the environmental impact of their facilities.

“Right now, the big trend is water,” says Robert Ioanna, PE, LEED AP, Senior Principal, Syska Hennessy Group. Newer data centers are turning to cooling systems that run on little or even no water.

For a recent 300,000-sf, 30 MW data center in Mexico, Syska Hennessy was going to go with water cooling, only to have the property owner revoke the client’s water-use privileges. Syska redesigned the mechanical and electrical systems to operate without water, using air-cooled chillers with integrated economizer cycles.

Page's Major foresees more liquefied immersion cooling, where servers get submerged in thermally conducted dielectric liquid. This method typically doesn’t require fans and allows the data center to run at hotter temperatures.

  

Related Stories

Giants 400 | Aug 21, 2022

Top 110 Architecture/Engineering Firms for 2022

Stantec, HDR, HOK, and Skidmore, Owings & Merrill top the rankings of the nation's largest architecture engineering (AE) firms for nonresidential and multifamily buildings work, as reported in Building Design+Construction's 2022 Giants 400 Report.

Giants 400 | Aug 20, 2022

Top 180 Architecture Firms for 2022

Gensler, Perkins and Will, HKS, and Perkins Eastman top the rankings of the nation's largest architecture firms for nonresidential and multifamily buildings work, as reported in Building Design+Construction's 2022 Giants 400 Report.

Giants 400 | Aug 19, 2022

2022 Giants 400 Report: Tracking the nation's largest architecture, engineering, and construction firms

Now 46 years running, Building Design+Construction's 2022 Giants 400 Report rankings the largest architecture, engineering, and construction firms in the U.S. This year a record 519 AEC firms participated in BD+C's Giants 400 report. The final report includes more than 130 rankings across 25 building sectors and specialty categories. 

Data Centers | Feb 15, 2022

Data center boom: How two AEC firms plan to meet unprecedented demand for data center facilities

Ramboll's Jim Fox and EYP Mission Critical Facilities' Rick Einhorn discuss the recent joining of their companies at a time of unprecedented data center demand. BD+C's John Caulfield leads the discussion with Fox, Ramboll's Managing Director for the Americas, and Einhorn, EYP Mission Critical Facilities' Managing Director.

Data Centers | Nov 1, 2021

Construction begins on Facebook’s Mesa Data Center

The project represents Facebook’s first major investment in Arizona.

Data Centers | Sep 22, 2021

Wasted energy from data centers could power nearby buildings

A Canadian architecture firm comes up with a concept for a community that’s part of a direct-current microgrid.

Giants 400 | Aug 30, 2021

2021 Giants 400 Report: Ranking the largest architecture, engineering, and construction firms in the U.S.

The 2021 Giants 400 Report includes more than 130 rankings across 25 building sectors and specialty categories.

Giants 400 | Aug 26, 2021

2021 Data Center Giants: Top architecture, engineering, and construction firms in the U.S. data center facilities sector

Corgan, Holder Construction, Jacobs, and Whiting-Turner top BD+C's rankings of the nation's largest data center facilities sector architecture, engineering, and construction firms, as reported in the 2021 Giants 400 Report.

Contractors | Jul 23, 2021

The aggressive growth of Salas O'Brien, with CEO Darin Anderson

Engineering firm Salas O'Brien has made multiple acquisitions over the past two years to achieve its Be Local Everywhere business model. In this exclusive interview for HorizonTV, BD+C's John Caulfield sits down with the firm's Chairman and CEO, Darin Anderson, to discuss its business model.

Data Centers | Mar 20, 2021

Japan’s NTT pushes U.S. data center expansion

Two new facilities opened last month, with several others under construction.

boombox1 - default
boombox2 -
native1 -

More In Category

Data Centers

What’s next for data center design in 2024

Nuclear power, direct-to-chip liquid cooling, and data centers as learning destinations are among the emerging design trends in the data center sector, according to Scott Hays, Sector Leader, Sustainable Design, with HED. 




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021