Back on track: Union Terminal renovation and restoration

Reconstruction Awards

Back on track: Union Terminal renovation and restoration

Painstaking care went into restoring Cincinnati’s train terminal/museum complex.


By John Caulfield, Senior Editor | November 15, 2019
Union Terminal exterior

The restoration of Union Terminal and the massive fountain at its entrance took 2½ years. The rotunda spans 180 feet. Eight mosaic and 22 painted murals were restored. Photo: Brad Feinknopf.

After Cincinnati’s Union Terminal was completed, in 1933, it was deemed one of America’s most important Art Deco buildings. And certainly one of the more imposing. The rotunda alone spans 180 feet, making it the world’s second-largest half-dome (after the Sydney Opera House). Since the late 1990s, the terminal has been home to the Cincinnati Museum Center, a complex of six organizations that include a children’s museum and one devoted to natural history and science.

But Union Terminal had fallen on hard times. Its extensive renovation took 2½ years and over 1.1 million manhours to complete. To understand the terminal’s existing conditions, the reconstruction team conducted a 3D point cloud scan that generated 4.3 billion data points.

The project focused on restoring the integrity of the terminal’s structure and providing new mechanical systems. More than 478,000 pounds of ductwork were installed. A cooling tower ties into 23 new air handlers and three new centrifugal chillers. Five boilers were replaced.

Also replaced were eight structural steel beams in the ceiling of the children’s museum that had endured decades of water damage. Each beam weighed eight tons and was 40 feet long and 36 inches in height.

 

Inside Union Terminal with American flagPhoto: ©Cincinnati Museum Center. 

 

The terminal’s restoration also entailed:

• Removing and reassembling a massive fountain at the front of the building so that a waterproofing membrane could be installed.

• Applying 5,200 lbs of SonaKrete, an acoustical finish, to the rotunda’s interior wall before it was repainted.

• Replacing, restoring, or thoroughly cleaning 1,060 doors and 1,270 windows, as well as eight mosaic murals and 22 painted murals in the rotunda and exhibit wing.

Brick and stone were removed from the terminal’s façade and replaced once a watertight barrier was installed. A critical component of the project was the detailed coordination of opening up small sections to ensure a temporary weatherproofed system was in place without exposing the interior work.

 

GOLD AWARD WINNER

BUILDING TEAM Turner Construction (submitting firm, GC) Cincinnati Museum Center (owner) GBBN Architects (design architect) THP Limited (SE) The Kleingers Group (CE) Arup (MEP) Heapy Engineering (engineering consultant) John G. Waite Associates Architects (historic preservation contractor) DETAILS 500,000 sf Total cost $172.7 million Construction time July 2016 to November 2018 Delivery method CM at risk

Related Stories

Reconstruction Awards | Nov 8, 2019

2019 Reconstruction Awards: The 1060 Project at Wrigley Field

Venerable Wrigley Field is raised up in a top-to-bottom restoration that took five years to complete.

Reconstruction Awards | Nov 6, 2019

2019 Reconstruction Awards: Betting on a city's future

Can a new resort and casino pump life into a city once renowned as the nation’s arms maker?

Reconstruction Awards | Dec 4, 2018

BD+C's 2018 Reconstruction Award Winners

Cincinnati Music Hall, MASS MoCA Building 6, and 20 Times Square are just a few of the projects recognized as 2018 Reconstruction Award winners.

Reconstruction Awards | Dec 3, 2018

2018 Reconstruction Awards: Honorable mentions

These four projects won honorable mentions in BD+C's 2018 Reconstruction Awards.

Reconstruction Awards | Dec 3, 2018

Elgin Tower: Elgin's heart beats again

A project team brings this Chicago suburb’s landmark tower back to life.

Reconstruction Awards | Nov 30, 2018

Hawaiian Dredging Construction Company Building: GC to the rescue

Hawaii’s largest contractor saves one of the state’s prized architectural landmarks—and now calls it home.

Reconstruction Awards | Nov 30, 2018

5 Beekman Hotel and Residences: Back in business

A landmark office tower becomes one of N.Y.’s hottest lifestyle hotel destinations.

Reconstruction Awards | Nov 29, 2018

700 Constitution: Healthy living

Hospital turned apartment brings luxury living to a D.C. neighborhood – and saves a valued piece of architecture.

Reconstruction Awards | Nov 28, 2018

IBEW Local 134 Union Hall: Union lights a 'beacon'

Electrical workers’ local converts an abandoned Chicago school into a brightly lit union hall.

Reconstruction Awards | Nov 27, 2018

Bedford Square: Revivifying urbanity

A suburban mixed-use redevelopment restores ‘the lost art of living closely.'

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021