20 Times Square: Conquering Times Square

Reconstruction Awards

20 Times Square: Conquering Times Square

The 20 Times Square mixed-used project at the corner of 47th and Seventh Avenue is indicative of the great lengths Building Teams will go in order to maximize real estate and media opportunities in Times Square.


By David Barista, Editorial Director | November 13, 2018

The project involved saving the street-facing portions of the Cecil B. DeMille building to maintain its billboard rights. Photo: Ralph D’Angelo/CIG Digital.

No other place in the country generates more advertising revenue from building façades than Times Square. A single billboard can command upwards of $4 million per advertiser per year. Using the latest digital signage technology and creative building redevelopment plans, building owners and developers jockey for the primo positions to capture eyeballs along this famed commercial intersection.

The 20 Times Square mixed-used project at the corner of 47th and Seventh Avenue is indicative of the great lengths Building Teams will go in order to maximize real estate and media opportunities in Times Square. The project involved redeveloping portions of the historic Cecil B. DeMille building, pouring new foundations for the entire site, and then erecting a 42-story luxury hotel, retail, and entertainment tower on the compact, 16,000-sf property.

Demolishing the DeMille building would have been the easy route, but it would cost the developers precious billboard real estate. For new construction, the city requires a setback at 60 feet in height. This would have nearly halved the 110-foot-tall street wall that wrapped the DeMille building. To save its street wall height, the team would have to qualify for a special Alteration 1 permit.

 

20 Times Square exterior facade

 

The solution entailed demolishing 70% of the existing building, leaving a 10-story, L-shaped configuration along 47th Street and Seventh Avenue. The team took painstaking measures to save the street-facing structure of the DeMille, a plan that met the city’s requirement for saving at least 25% of the existing floor levels. It included: temporary shoring and bracing of the existing structure until the permanent foundations could be poured; removal of the small Pig & Whistle pub building and an accompanying party wall shared by the adjacent New York Hotel (different owner); the discovery of misplaced columns and undocumented structural framing that required re-engineering on a weekly basis to maintain the shoring/bracing; and the install of vibration monitors and telltales to monitor movement of the existing “L” structure during construction.

The combination of a complex project, with numerous unforeseen issues, on a tight site, in one of the world’s busiest intersections made 20 Times Square the “most taxing, yet exhilarating” project in the 40-year career of CNY’s President Kenneth Colao. The risks “were very material.”

 

Bronze Award Winner

BUILDING TEAM CNY Construction (submitting firm, CM) Maefield Development (owner) The Witkoff Organization (developer) Platt Byard Dovell White (architect) Adamson Associates Architects (interior architect) Severud Associates (SE) Cosentini Associates (MEP) DETAILS 378,000 sf Total cost Confidential Construction time 2015 to 2018 Delivery method CM at risk with GMP

 

CLICK HERE TO GO TO THE 2018 RECONSTRUCTION AWARDS LANDING PAGE

Related Stories

Reconstruction Awards | Dec 1, 2017

Rescue mission: Historic movie palace is now the centerpiece of Baltimore’s burgeoning arts hub

In restoring the theater, the design team employed what it calls a “rescued ruin” preservation approach.

Reconstruction Awards | Dec 1, 2017

Gothic revival: The nation’s first residential college is meticulously restored

This project involved the renovation and restoration of the 57,000-sf hall, and the construction of a 4,200-sf addition.

Reconstruction Awards | Dec 1, 2017

Rockefeller remake: Iconic New York tower is modernized for its next life

To make way for new ground-floor retail and a more dramatic entrance and lobby, the team removed four columns at the ground floor.

Reconstruction Awards | Nov 30, 2017

BD+C's 2017 Reconstruction Award Winners

Provo City Center Temple, the Union Trust Building, and the General Motors Factory One are just a few of the projects recognized as 2017 Reconstruction Award winners.

Reconstruction Awards | Nov 29, 2017

College credit: Historic rehab saves 50% on energy costs

The project team conducted surveys of students, faculty, and staff to get their input.

Reconstruction Awards | Nov 29, 2017

Amazing grace: Renovation turns a church into elegant condos

The windows became The Sanctuary’s chief sales edge.

Reconstruction Awards | Nov 28, 2017

Broadway melody: Glass walls set just the right tone for a historic lobby in Lower Manhattan

The adaptation of the 45,000-sf neoclassical lobby at 195 Broadway created three retail spaces and a public walkway.

Reconstruction Awards | Nov 27, 2017

Higher education: The rebirth of a Washington, D.C., high school

The project team, led by architect Perkins Eastman, restored the original cupola.

Reconstruction Awards | Nov 27, 2017

Bank statement: A project team saves a historic bank, yielding 100% leaseup for the developer

The project team had to fix poor renovations made in the ’50s.

Reconstruction Awards | Nov 27, 2017

Patient friendly: The University of Chicago Medicine Center for Care and Discovery adds 203 new beds

Strict infection control and life safety measures were implemented to protect patients on other floors as work proceeded.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021