The University of Chicago Harris School at the Keller Center

Reconstruction Awards

The University of Chicago Harris School at the Keller Center

Project team goes all out for LEED Platinum and the Living Building Challenge.


By Robert Cassidy, Executive Editor | November 25, 2019
North elevation of the University of Chicago Harris School at the Keller Center

Photos: Tom Rossiter

Extreme sustainability was the chief goal for the reconstruction of Edward Durrell Stone’s Kellogg Center for Continuing Education at the University of Chicago.

Mortenson (CM) and Farr Associates (architect) put Stone’s New Formalism structure, built in 1963, on track to be the healthiest building in the Chicago area—the first LEED Platinum on the Maroons’ campus, and only the third project in the city to seek Petal certification (materials, equity, beauty) from the Living Building Challenge.

To meet the LBC’s “red list” requirements, all materials used by trade partners had to be vetted for banned chemicals. The carbon footprint of laborers and trade partners was tracked to reduce greenhouse gas emissions.

En route to achieving those standards, Mortenson and its CM partner, minority-owned contractor Ardmore Roderick, exceeded the university’s social hiring goals: 59% MWBE participation (vs. a goal of 30%) and an amazing 81% minority labor participation (vs. a 40% goal).

 

Inside the University of Chicago Harris School at the Keller CenterThe wood for the Harris Family Forum was recycled from trees felled by the emerald ash borer. The Keller Center was originally built in 1963.

 

The CM team used Lean strategies (Last Planner, 5S) to streamline workflow and improve safety. The project had a total recordable incident rate of 0.71, compared to the industry standard of 3.20. MEP subcontractors were brought on early to provide design-assist expertise.

Farr Associates designed the 150,000 kWh/year rooftop PV system, which supplies 11% of the building’s energy, so that the 354 panels could be relocated in the event of future expansion of the Harris School of Public Policy.

The project team won a variance from the city to reduce the required size of the building’s green roof by installing a 15,000-gallon cistern, which stores rainwater for reuse in landscaping and toilet flushing, diverting 525,000 gallons of fresh water from the sewer system.

Three light courts were carved into the concrete structure to provide a balance of daylight between the borrowed light of perimeter windows across the deep floor plates.

 

SILVER AWARD WINNER

BUILDING TEAM Mortenson (submitting firm, CM) The University of Chicago (owner) Farr Associates (architect) Woodhouse Tinucci Architects (collaborating architect, interior designer) Stearn Joglekar, Ltd. (SE) dbHMS (MEP/FP) WJE (building forensics) Shen Milsom Wilke (acoustics/AV) WSP (LBC Red List consultant) site design group (landscape) Ardmore Roderick (CM partner) DETAILS 125,000 sf Total cost $60 million Construction time April 2017 to December 2018 Delivery method CM at risk

Related Stories

Reconstruction Awards | Nov 16, 2016

BD+C's 2016 Reconstruction Award Winners

St. Patrick’s Cathedral, Lovejoy Wharf, and the Bay Area Metro Center are just a few of the projects recognized as 2016 Reconstruction Award winners.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: The Renwick Gallery of The Smithsonian American Art Museum

The renovation restored two long-concealed vaulted ceilings in the second-floor galleries and recreated the original 19th-century window configuration.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Massachusetts Maritime Academy

The two-story “overbuild” employed block and plank construction with drag strut detailing to connect it to the existing building.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: The Masonic Temple

The building team suspended a new eighth-floor mezzanine and added 18 9x15-foot windows to the north, south, and west façades.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: San Francisco War Memorial Veterans Building

The building team used a system of rocking concrete shear walls, which eliminated the need for deep foundations and reduced the shear force on each wall.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Arc at Old Colony

The Arc at Old Colony's vintage floor plans, voluminous lobby, and myriad elevators were perfect for redevelopment as a historically charming residential building.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Noble Chapel

In May 2013 the 124-year-old Noble Chapel, suffered a three-alarm fire that almost completely destroyed its 1937 crematorium.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Bay Area Metro Center

The structure’s 60,000-sf floor plates made the interior dark and foreboding, and BAHA wanted to improve working conditions for its employees and tenants. 

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021