Temporary quarters: Senate of Canada Building

Reconstruction Awards

Temporary quarters: Senate of Canada Building

Canada’s Senate gets an interim home in what was once the capital’s main train station.


By Robert Cassidy, Executive Editor | November 21, 2019

The east façade of the Ottawa train station,  now the new home of Canada’s Senate.

Canada’s Parliamentary complex, in Ottawa, is undergoing a massive 10-year restoration that includes the Centre Block, which houses the government’s two parliamentary chambers. A project team led by Diamond Schmitt Architects and KWC Architects has converted the city’s 1912 train station into a stately interim home for one of those chambers, the Senate.

The building is a prominent component of the Confederation Square Historic site and is located within the Rideau Canal World Heritage Site’s buffer zone. The train station closed in 1968 but the building was repurposed as the Government Conference Centre.

Numerous ad hoc renovations that marred the Beaux Arts classicism of the original were made, as well as seismic and life safety improvements and restoration work to reestablish its character-defining elements.

 

The renovated Senate ChamberThe renovated Senate Chamber.

 

The design introduced a contemporary language of interventions and insertions within the monumental and finely detailed General Waiting Room and Concourse.

The chief technical problem involved the rehabilitation of two magnificent suspended plaster ceilings. Several precast coffered panels were tested to determine their strength and typical failure mechanisms. No North American precedent existed, so the team tried a conservation strategy from the United Kingdom to determine its suitability for this ceiling type. The system now serves as a new precedent for plaster conservation in Canada.

Other heritage features, such as Diocletian windows, original door frames, trim, and wainscoting, were salvaged, repaired, and refinished. The gross area was increased to 192,000 sf, from 135,000 sf.

Ninety percent of construction costs went toward making the building reusable as office and conference space once the Centre Block restoration is completed.

General contractor PCL diverted 93% of construction waste from landfill. Building envelope upgrades saved 162,000 kg of carbon emissions. The project earned Green Globes 4 certification.

 

SILVER AWARD WINNER

BUILDING TEAM Diamond Schmitt Architects and KWC Architects (submitting firms, architects in joint venture) Public Services and Procurement Canada (owner) ERA Architects (conservation architect) John G. Cooke & Associates (SE) Crossey Engineering (M/E engineer) PCL (CM) DETAILS 130,000 sf Total cost $219 million Construction time March 2014 to January 2019 Delivery method CM fast-track

Related Stories

Reconstruction Awards | Nov 27, 2017

The birthplace of General Motors

The automotive giant salvages the place from which it sprang, 131 years ago.

Reconstruction Awards | Nov 21, 2017

Honor Guard: San Francisco’s historic Veterans Building pays homage to those who served in World War I and other foreign wars

The Veterans Building houses the War Memorial staff, the city’s Arts Commission, the Opera’s learning center and practice/performance node, the Green Room reception venue, and the 916-seat Herbst Theatre.

Reconstruction Awards | Nov 20, 2017

Eyes wide open: Students can see their new home’s building elements

The two-phase project revamped an opaque, horseshoe-shaped labyrinth of seven buildings from the ’60s and ’70s.

Reconstruction Awards | Nov 17, 2017

Gray lady no more: A facelift erases a landmark’s wrinkles, but not her heritage

The Building Team restored the granite and terra cotta façade and reclaimed more than 500 double-hung windows.

Reconstruction Awards | Nov 17, 2017

Elegance personified: New life for a neglected but still imposing retail/office space

The building was in such disrepair that much of the reconstruction budget had to go toward structural, mechanical, and electrical infrastructure improvements.

Reconstruction Awards | Nov 16, 2017

Back to the '20s: Coney Island gets a new eatery reminiscent of the past

This project included the restoration of the landmark Childs Restaurant.

Reconstruction Awards | Nov 15, 2017

Foyer fantastique: Faded images provide the key to a historic theater's lobby restoration

The restoration relied heavily on historic photos and drawings.

Reconstruction Awards | Nov 14, 2017

Hallowed ground: A Mormon temple rises from the ashes of a fire-ravaged historic tabernacle

Parts of the tabernacle’s exterior shell were the only things that survived the blaze.

Reconstruction Awards | Nov 13, 2017

Harlem Renaissance: A vacant school provides much-needed housing and a clubhouse for children

Word that PS 186 might be demolished brought out the preservationists, whose letter-writing campaign gained the support of the New York Landmarks Conservancy.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021