Temporary quarters: Senate of Canada Building

Reconstruction Awards

Temporary quarters: Senate of Canada Building

Canada’s Senate gets an interim home in what was once the capital’s main train station.


By Robert Cassidy, Executive Editor | November 21, 2019

The east façade of the Ottawa train station,  now the new home of Canada’s Senate.

Canada’s Parliamentary complex, in Ottawa, is undergoing a massive 10-year restoration that includes the Centre Block, which houses the government’s two parliamentary chambers. A project team led by Diamond Schmitt Architects and KWC Architects has converted the city’s 1912 train station into a stately interim home for one of those chambers, the Senate.

The building is a prominent component of the Confederation Square Historic site and is located within the Rideau Canal World Heritage Site’s buffer zone. The train station closed in 1968 but the building was repurposed as the Government Conference Centre.

Numerous ad hoc renovations that marred the Beaux Arts classicism of the original were made, as well as seismic and life safety improvements and restoration work to reestablish its character-defining elements.

 

The renovated Senate ChamberThe renovated Senate Chamber.

 

The design introduced a contemporary language of interventions and insertions within the monumental and finely detailed General Waiting Room and Concourse.

The chief technical problem involved the rehabilitation of two magnificent suspended plaster ceilings. Several precast coffered panels were tested to determine their strength and typical failure mechanisms. No North American precedent existed, so the team tried a conservation strategy from the United Kingdom to determine its suitability for this ceiling type. The system now serves as a new precedent for plaster conservation in Canada.

Other heritage features, such as Diocletian windows, original door frames, trim, and wainscoting, were salvaged, repaired, and refinished. The gross area was increased to 192,000 sf, from 135,000 sf.

Ninety percent of construction costs went toward making the building reusable as office and conference space once the Centre Block restoration is completed.

General contractor PCL diverted 93% of construction waste from landfill. Building envelope upgrades saved 162,000 kg of carbon emissions. The project earned Green Globes 4 certification.

 

SILVER AWARD WINNER

BUILDING TEAM Diamond Schmitt Architects and KWC Architects (submitting firms, architects in joint venture) Public Services and Procurement Canada (owner) ERA Architects (conservation architect) John G. Cooke & Associates (SE) Crossey Engineering (M/E engineer) PCL (CM) DETAILS 130,000 sf Total cost $219 million Construction time March 2014 to January 2019 Delivery method CM fast-track

Related Stories

Reconstruction Awards | Nov 26, 2018

Yarn works: Neverending yarn

111-year-old mill becomes a mixed-income multifamily community.

Reconstruction Awards | Nov 20, 2018

Wiseburn High School: New kind of P3

A California school district and a charter school system join forces to open a skills-based high school.

Reconstruction Awards | Nov 19, 2018

Kehoe Iron Works: Industrial strength makeover

A project team turns a toxic site into a civic treasure.

Reconstruction Awards | Nov 19, 2018

Weiser Hall, University of Michigan: Campus upgrade

A Mid-century building becomes home to a new International Institute.

Reconstruction Awards | Nov 16, 2018

Mass MoCA Building 6: The Robert W. Wilson Building

A textile mill becomes an arts center that energizes a New England town and its region.

Reconstruction Awards | Nov 15, 2018

Charles L. Tutt Library, Colorado College: Net-zero in the Rockies

Library expansion reinforces Colorado College’s commitment to carbon neutrality.

Reconstruction Awards | Nov 14, 2018

National Arts Centre: O, Canada

Three new wings and a flashy AV display add luster to the nation’s cultural gem.

Reconstruction Awards | Nov 13, 2018

20 Times Square: Conquering Times Square

The 20 Times Square mixed-used project at the corner of 47th and Seventh Avenue is indicative of the great lengths Building Teams will go in order to maximize real estate and media opportunities in Times Square.

Reconstruction Awards | Nov 12, 2018

Crosstown Concourse: An 'organic' urban village

Memphians band together to rebuild a gigantic Sears distribution facility into a multifaceted community crossroads.

Reconstruction Awards | Nov 12, 2018

Cincinnati Music Hall: Saving a cultural anchor

Cincinnati uses ‘skillful triage’ to bring its endangered Music Hall up to date.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021