Stackable steel modules speed building core construction

Great Solutions

Stackable steel modules speed building core construction

With this patented, steel-and-concrete hybrid system, the service core will no longer be the schedule bottleneck on new construction projects.


By David Malone, Associate Editor | February 8, 2018

The CorTek system has been used on five projects to date, including the One Steamboat Place resort in Steamboat Springs, Colo. Images: Vulcraft

Engineered as an alternative to traditional building core construction methods, such as cast-in-place concrete, precast concrete, and masonry, this patented, steel-and-concrete hybrid system can simplify and accelerate the construction of reinforced concrete stair and elevator core structures.

The CorTek Core System is supplied by Vulcraft, a fabricator of steel joist and deck components, in collaboration with its parent company, steel producer Nucor.

The newly launched system has been used on five projects to date, including the One Steamboat Place resort in Steamboat Springs, Colo., the Taxi II mixed-use residential building in Denver, and Limelight Lodge in Aspen, Colo.

 

The CorTek system

 

The system is made up of modular, stackable cores that are factory-built and shipped ready to install. Modular construction minimizes site time and provides easy on-site installation. Stairs are pre-installed at the factory, and the stair rails are shipped inside the cores. This allows for safer, earlier, and more efficient trade access to floors. Workers can begin setting steel right away without having to wait on core curing.

Each CorTek system is custom-built to the requirements of the specific project. The architect and structural engineer are responsible for producing drawings and specifications that define the requirements for the core walls and stairs in the final constructed form. These drawings and specifications are given to the CorTek sub-contractor in order to begin shop drawings.

Once the all-steel cores are delivered on site, the CorTek installation process entails three steps: stack the cores; connect the steel, then continue erecting the structure; and pour concrete inside the core walls as erection continues.

 

 

The CorTek system is compatible with steel, concrete, and wood framing, and is structurally equivalent to cast-in-place concrete walls of various thicknesses, according to the makers. The modules go up with floor framing and do not require stripping. The interior surfaces can be left as is or finished with any standard wall
finish, such as paint, drywall, or laminate.

 

Related Stories

Great Solutions | Jul 9, 2021

MojoDesk creates a new solution for managing open office distractions

The MojoDome allows for a private work space while also maintaining a collaborative environment.

Great Solutions | Mar 18, 2021

Follow the leader: New following technology better equips robots for the jobsite

New proof-of-concept from Piaggio Fast Forward and Trimble enables robots and machines to follow humans.

Great Solutions | Feb 11, 2021

Simplifying the return to the office

A new web-based tool from Sasaki takes the guesswork out of heading back to the workplace.

Great Solutions | Oct 6, 2020

Could water-filled windows help buildings save energy?

New research shows how water-filled glass could help heat and cool buildings.

Great Solutions | Aug 10, 2020

From lobby to penthouse, elevators can be a 100% touch-free experience

The Toe-To-Go elevator system allows riders to operate the elevator entirely with their feet.

Great Solutions | Jul 13, 2020

Essential protection for businesses

Custom protective barriers help keep essential business employees safe.

Great Solutions | Apr 13, 2020

Family workstations highlight the new Fairfield Area Library

The workstations are the perfect remedy for squirming, restless children and toddlers.

Great Solutions | Feb 5, 2020

Power moves: The Shed

Precise positioning of mechanicals above its lighting keeps New York’s kinetic event space, The Shed, running.

Great Solutions | Dec 18, 2019

Robot uprising

Thyssenkrupp’s robotics interface platform helps robots use elevators like humans.

Great Solutions | Nov 12, 2019

Skanska designs personal protective equipment tailor-made for the female workforce

A safety vest is the first piece of equipment to undergo an update.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021