Springfield Technical Community College: Goodbye to 'the shuffle'

Reconstruction Awards

Springfield Technical Community College: Goodbye to 'the shuffle'

College unites student services under one roof.


By Robert Cassidy, Executive Editor | November 19, 2019
Springfield Technical Community College

Corten steel canopies along the 764-foot façade mark new entrances into Springfield Technical Community College. All photos: Chuck  Choi

Springfield, Mass., the site of America’s first armory, served as the center of U.S. military munitions manufacturing and research until 1968, when the historic site and buildings were deeded to Springfield Technical Community College. One of those buildings is now the STCC’s Campus Center, which unites student services covering enrollment, academic advising, student life, and a learning commons in a 170-year-old, 764-foot-long structure.

Previously, students had to navigate six departments in five buildings to access basic services in what was known as the “STCC Shuffle.” The college, a federally designated Hispanic-serving institution, found that many prospective students just gave up and never registered.

A project team led by Ann Beha Architects worked with the National Park Service and the Massachusetts Historical Commission to develop a design for new windows, which made up half the exterior, to enclose the previously open-air building while bringing in daylight and controlling solar heat gain.

Consigli Construction (CM) shaved four months off the project schedule by 3D printing mockups for sections of the 203 custom windows. The contractor reused, recycled, or salvaged >90% of C&D debris and remediated a brownfield.

Ancient brick-lined drains were replaced with modern storm structures and separated from the sanitary system. An asphalt parking lot was turned into a 20,000-sf greenspace that forms a new unifying campus quad.

 

The Student Life Center and Dining Commons at Springfield Tech

 

Carefully selected hardscape and softscape materials were used to treat roof and surface runoff. Rain gardens were planted to enhance on-site water management.

An archeological team was on hand to monitor all excavations. Work was paused to allow them to photograph and measure dishes (dated 1810) and a vegetable cellar. Conservation experts helped determine the exterior paint color of the building and fenestration.

STCC has instituted a Green Cleaning Policy for maintenance operations. The project is targeted to achieve LEED Silver certification.

 

SILVER AWARD WINNER

BUILDING TEAM Ann Beha Architects (submitting firm, architect) Division of Capital Asset Management and Maintenance (owner) RSE Associates (SE) Altieri Sebor Wieber (MEP) Consigli Construction (CM) DETAILS 100,100 sf Total cost $42.7 million Construction time May 2016 to December 2018 Delivery method CM at risk

Related Stories

Reconstruction Awards | Nov 27, 2017

The birthplace of General Motors

The automotive giant salvages the place from which it sprang, 131 years ago.

Reconstruction Awards | Nov 21, 2017

Honor Guard: San Francisco’s historic Veterans Building pays homage to those who served in World War I and other foreign wars

The Veterans Building houses the War Memorial staff, the city’s Arts Commission, the Opera’s learning center and practice/performance node, the Green Room reception venue, and the 916-seat Herbst Theatre.

Reconstruction Awards | Nov 20, 2017

Eyes wide open: Students can see their new home’s building elements

The two-phase project revamped an opaque, horseshoe-shaped labyrinth of seven buildings from the ’60s and ’70s.

Reconstruction Awards | Nov 17, 2017

Gray lady no more: A facelift erases a landmark’s wrinkles, but not her heritage

The Building Team restored the granite and terra cotta façade and reclaimed more than 500 double-hung windows.

Reconstruction Awards | Nov 17, 2017

Elegance personified: New life for a neglected but still imposing retail/office space

The building was in such disrepair that much of the reconstruction budget had to go toward structural, mechanical, and electrical infrastructure improvements.

Reconstruction Awards | Nov 16, 2017

Back to the '20s: Coney Island gets a new eatery reminiscent of the past

This project included the restoration of the landmark Childs Restaurant.

Reconstruction Awards | Nov 15, 2017

Foyer fantastique: Faded images provide the key to a historic theater's lobby restoration

The restoration relied heavily on historic photos and drawings.

Reconstruction Awards | Nov 14, 2017

Hallowed ground: A Mormon temple rises from the ashes of a fire-ravaged historic tabernacle

Parts of the tabernacle’s exterior shell were the only things that survived the blaze.

Reconstruction Awards | Nov 13, 2017

Harlem Renaissance: A vacant school provides much-needed housing and a clubhouse for children

Word that PS 186 might be demolished brought out the preservationists, whose letter-writing campaign gained the support of the New York Landmarks Conservancy.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021