In popular culture, it hasn’t been cool to “raise the roof” since the late 1990s. But one company is trying to start a new, very literal “raise the roof” trend in the AEC industry.
That company is Upbrella Construction (upbrella.com), and the trend is to build the roof of a structure early in the construction process, and then raise it up as the building progresses.
This alternative process for building tall concrete or steel buildings consists of a mobile permanent roof, a roof lifting mechanism, a protective enclosure, and a high-capacity hoist.
The first step of the Upbrella process begins as soon as the first repeating floor is completed on the foundation. During this phase, an adapted roof that is suitable and equipped to support the construction is installed. The roof can remain on the building throughout construction and after the building is completed if it has the desired geometry. It can also be adapted at the end of the project.
Once the roof is in place, a protective enclosure, consisting of a metal structure covered with a reinforced canvas, is installed up to the parapet and descends to the working gateway. This enclosure keeps the work environment and the workers completely sheltered and allows the project team to better control risks associated with construction.
The floor above is assembled on the previous floor inside the sheltered environment and then positioned using the adapted roof and its hoisting system. The subassembly is finished prior to positioning it to its final height. Once the floor is installed, the entire roof system is raised and work can progress to the next level, where the process is repeated.
See Also: When is wood not really wood?
A large-format carrier replaces conventional elevators and can route all the necessary workers and building materials to the floors. The hoist comprises at least two masts anchored to the structure and remains in place during the entirety of the construction period. The capacity and quantity of the carriers can be adjusted to the size and scope of the project.
The adaptable roof and associated protective enclosure allow for finishing touches and occupancy of the lower floors faster. If sales stagnate, construction can be suspended while the completed floors can become and remain occupied. Then, if sales or demand increase, construction can quickly proceed once more.
Other benefits the company cites: reduced insurance costs; the elimination of lost days due to inclement weather; the reduction of overhead and high winter costs; an increased energy efficiency for the building site; and the reduction of public occupancy costs.
Related Stories
Great Solutions | Sep 28, 2018
When pigs fly? How about when cows float?
Merwehaven Harbor in Rotterdam will be home to the world’s first floating farm.
Great Solutions | Sep 17, 2018
Curtain walls go circadian
Catering to our natural circadian rhythm is a task designers are taking to heart.
Great Solutions | Aug 8, 2018
Warehouses rise up to serve downtown
Multistory industrial buildings provide the best chance at keeping up with the rapid growth of e-commerce in North America.
Great Solutions | Jul 13, 2018
Fungus may be the key to colonizing mars
A Cleveland-based architect and a NASA Ames researcher have a novel idea for building on Mars.
Great Solutions | May 14, 2018
It’s not Ripley’s loader, but this industrial exoskeleton makes physical labor a breeze
SuitX modules can be used separately or combined to form a full-body exoskeleton.
Great Solutions | Apr 5, 2018
IAQ monitoring for all
San Francisco startup Bitfinder debuts a commercial-grade version of its air quality monitoring system.
Great Solutions | Mar 9, 2018
Forget the wall thermostat: Wear one on your wrist instead
The Embr Wave Wristband acts like a personal thermostat and could become a user-friendly component in building energy-saving strategies.
Great Solutions | Feb 8, 2018
Stackable steel modules speed building core construction
With this patented, steel-and-concrete hybrid system, the service core will no longer be the schedule bottleneck on new construction projects.
Great Solutions | Jan 10, 2018
Blue lagoon technology brings the beach anywhere in the world
From coastal resorts to inner cities, these large-scale clear-water lagoons offer a slice of paradise.
Great Solutions | Oct 17, 2017
Loop NYC would reclaim 24 miles of park space from Manhattan’s street grid
A new proposal leverages driverless cars to free up almost all of Manhattan’s Park Avenue and Broadway for pedestrian paths.