In popular culture, it hasn’t been cool to “raise the roof” since the late 1990s. But one company is trying to start a new, very literal “raise the roof” trend in the AEC industry.
That company is Upbrella Construction (upbrella.com), and the trend is to build the roof of a structure early in the construction process, and then raise it up as the building progresses.
This alternative process for building tall concrete or steel buildings consists of a mobile permanent roof, a roof lifting mechanism, a protective enclosure, and a high-capacity hoist.
The first step of the Upbrella process begins as soon as the first repeating floor is completed on the foundation. During this phase, an adapted roof that is suitable and equipped to support the construction is installed. The roof can remain on the building throughout construction and after the building is completed if it has the desired geometry. It can also be adapted at the end of the project.
Once the roof is in place, a protective enclosure, consisting of a metal structure covered with a reinforced canvas, is installed up to the parapet and descends to the working gateway. This enclosure keeps the work environment and the workers completely sheltered and allows the project team to better control risks associated with construction.
The floor above is assembled on the previous floor inside the sheltered environment and then positioned using the adapted roof and its hoisting system. The subassembly is finished prior to positioning it to its final height. Once the floor is installed, the entire roof system is raised and work can progress to the next level, where the process is repeated.
See Also: When is wood not really wood?
A large-format carrier replaces conventional elevators and can route all the necessary workers and building materials to the floors. The hoist comprises at least two masts anchored to the structure and remains in place during the entirety of the construction period. The capacity and quantity of the carriers can be adjusted to the size and scope of the project.
The adaptable roof and associated protective enclosure allow for finishing touches and occupancy of the lower floors faster. If sales stagnate, construction can be suspended while the completed floors can become and remain occupied. Then, if sales or demand increase, construction can quickly proceed once more.
Other benefits the company cites: reduced insurance costs; the elimination of lost days due to inclement weather; the reduction of overhead and high winter costs; an increased energy efficiency for the building site; and the reduction of public occupancy costs.
Related Stories
75 Top Building Products | Aug 7, 2023
Enter today! BD+C's 75 Top Building Products for 2023
BD+C editors are now accepting submissions for the annual 75 Top Building Products awards. The winners will be featured in the November/December 2023 issue of Building Design+Construction.
Resiliency | Aug 7, 2023
Creative ways cities are seeking to beat urban heat gain
As temperatures in many areas hit record highs this summer, cities around the world are turning to creative solutions to cope with the heat. Here are several creative ways cities are seeking to beat urban heat gain.
AEC Innovators | Jun 15, 2023
Rogers-O'Brien Construction pilots wearables to reduce heat-related injuries on jobsites
Rogers-O'Brien Construction (RO) has launched a pilot program utilizing SafeGuard, a safety-as-a-service platform for real-time health and safety risk assessment. Non-invasive wearables connected to SafeGuard continuously monitor personnel to prevent heat exhaustion on jobsites, reducing the risk of related injuries. RO is the first general contractor to pilot this program.
Office Buildings | May 15, 2023
Sixteen-story office tower will use 40% less energy than an average NYC office building
This month marks the completion of a new 16-story office tower that is being promoted as New York City’s most sustainable office structure. That boast is backed by an innovative HVAC system that features geothermal wells, dedicated outdoor air system (DOAS) units, radiant heating and cooling, and a sophisticated control system to ensure that the elements work optimally together.
Design Innovation Report | Apr 27, 2023
BD+C's 2023 Design Innovation Report
Building Design+Construction’s Design Innovation Report presents projects, spaces, and initiatives—and the AEC professionals behind them—that push the boundaries of building design. This year, we feature four novel projects and one building science innovation.
Design Innovation Report | Apr 19, 2023
Reinforced concrete walls and fins stiffen and shade the National Bank of Kuwait skyscraper
When the National Bank of Kuwait first conceived its new headquarters more than a decade ago, it wanted to make a statement about passive design with a soaring tower that could withstand the extreme heat of Kuwait City, the country’s desert capital.
Design Innovation Report | Apr 19, 2023
HDR uses artificial intelligence tools to help design a vital health clinic in India
Architects from HDR worked pro bono with iKure, a technology-centric healthcare provider, to build a healthcare clinic in rural India.
3D Printing | Apr 11, 2023
University of Michigan’s DART Laboratory unveils Shell Wall—a concrete wall that’s lightweight and freeform 3D printed
The University of Michigan’s DART Laboratory has unveiled a new product called Shell Wall—which the organization describes as the first lightweight, freeform 3D printed and structurally reinforced concrete wall. The innovative product leverages DART Laboratory’s research and development on the use of 3D-printing technology to build structures that require less concrete.
Cladding and Facade Systems | Apr 5, 2023
Façade innovation: University of Stuttgart tests a ‘saturated building skin’ for lessening heat islands
HydroSKIN is a façade made with textiles that stores rainwater and uses it later to cool hot building exteriors. The façade innovation consists of an external, multilayered 3D textile that acts as a water collector and evaporator.
Transportation & Parking Facilities | Mar 23, 2023
Amsterdam debuts underwater bicycle parking facility that can accommodate over 4,000 bikes
In February, Amsterdam saw the opening of a new underwater bicycle parking facility. Located in the heart of the city—next to Amsterdam Central Station and under the river IJ (Amsterdam’s waterfront)—the facility, dubbed IJboulevard, has parking spots for over 4,000 bicycles, freeing up space on the street.