Demand for data center space overshadowed economic uncertainty and concerns around power availability in the first half of the year. Construction of North American data centers is at an all-time high in part due to the continued growth of artificial intelligence, according to CBRE.
CBRE’s latest North American Data Center Trends Report found there is 2,287.6 megawatts (MW) of data center supply currently under construction in primary markets, reaching a new all-time high with more than 70% already preleased. At the same time last year, there was 1,830.3 MW under construction. Companies are leasing space up to 36 months in advance of construction completion in anticipation of future demand and to secure data center space at current pricing.
“Data center construction is at an all-time high, driven by strong demand from all users, including AI, hyperscale and enterprise,” said Pat Lynch, executive managing director for CBRE’s Data Centers Solution. “New and existing uses of artificial intelligence cases grew tremendously in the first half of the year, and we expect demand to remain strong with AI driving leasing opportunities in the second half of the year.”
Absorption in the eight primary U.S. data center markets* remained resilient in H1 2023, totaling 468.8 MW despite challenges within the supply chain. While supply increased 19.2% year-over-year, vacancy remains near a record low of 3.3%. Strong demand paired with a lack of available power and extended timelines have kept asking rental rates climbing. Average primary market asking rents rose to $147.80 per kW/month from $127.50 (a 15.9% year-over-year increase).
Top Data Center Construction Markets
Northern Virginia remained the most active data center market in the first half of 2023 with 918 MW under construction. The market set a record low vacancy rate of 0.94% while power improvement projects are underway. Separately, Chicago recorded a 125% spike in under-construction activity - the largest increase among all U.S. data center markets.
“Most major markets are grappling with power constraints, and developers are facing challenges within their supply chain, but it’s not slowing down the demand for data center space,” said Gordon Dolven, director of Americas Data Center Research at CBRE. “Data center operators are prioritizing power availability, rather than selecting markets based on traditional factors such as location, connectivity, water and land pricing.”
Top 10 most active data center construction markets | ||
Market | H1 2023 Total Inventory | H1 2023 Under Construction |
Northern Virginia | 2,254.1 MW | 918 MW |
Hillsboro | 248.4 MW | 267.3 MW |
Silicon Valley | 410.7 MW | 125 MW |
Chicago | 367.5 MW | 205 MW |
Dallas-Fort Worth | 499.4 MW | 273.3 MW |
Phoenix | 360 MW | 163.5 MW |
Toronto | 291.3 MW | 99.6 MW |
New York Tri-State | 177.5 MW | 99.9 MW |
Atlanta | 271 MW | 235.6 MW |
Montreal | 135.5 MW | 106.5 MW |
Other market highlights include Dallas-Fort Worth, which saw the greatest year-over-year increase in absorption of 327%, jumping to 110.6 MW from 25.89 MW. Hillsboro also experienced the largest inventory growth of all primary markets, increasing to 248.4 MW from 139.4 MW (78% year-over-year growth).
To view the full report, click here.
Related Stories
Data Centers | Feb 18, 2021
Arcari Cimini Architettura designs Data Center Floating Island
The concept looks to create an entire floating city centered around a data center.
Data Centers | Jan 21, 2021
The Weekly show, Jan 21, 2021: Data centers in a pandemic world, and LGBT certification for AEC firms
This week on The Weekly show, BD+C editors speak with AEC industry leaders about LGBT certification for architecture, engineering, and construction firms, and the current state of data centers in a pandemic world.
Giants 400 | Dec 16, 2020
Download a PDF of all 2020 Giants 400 Rankings
This 70-page PDF features AEC firm rankings across 51 building sectors, disciplines, and specialty services.
Data Centers | Dec 9, 2020
COVID-19 pandemic elevates data centers to key priority market for investors
But supply-chain and labor problems could slow deliveries, according to Turner & Townsend’s 2020 report that looks at 40 markets.
Giants 400 | Dec 3, 2020
2020 Data Center Giants: Top architecture, engineering, and construction firms in the U.S. data center facilities sector
Corgan, Jacobs, and Whiting-Turner Contracting Company top BD+C's rankings of the nation's largest data center facilities sector architecture, engineering, and construction firms, as reported in the 2020 Giants 400 Report.
Data Centers | Oct 26, 2020
Speed to market is biggest obstacle for burgeoning data center construction sector
Hyperscale and edge computing are driving growth in data center and mission critical facilities construction.
Data Centers | Sep 17, 2020
Data center provider Aligned links new financing to sustainability performance
One goal: 100% renewable energy consumption by 2024.
Data Centers | Jun 30, 2020
Facebook to build $800 million data center in DeKalb, Ill.
Mortenson Construction is the project’s general contractor.
Data Centers | May 8, 2020
Data centers as a service: The next big opportunity for design teams
As data centers compete to process more data with lower latency, the AEC industry is ideally positioned to develop design standards that ensure long-term flexibility.
Giants 400 | Aug 28, 2019
Top 45 Data Center Construction Firms for 2019
Whiting-Turner, Turner, Holder, DPR, and Fortis top the rankings of the nation's largest data center sector contractors and construction management firms, as reported in Building Design+Construction's 2019 Giants 300 Report.