Christopher Aker, CEO of cloud-hosting company Linode, could have built a new headquarters anywhere he darned well pleased. Instead, he chose to put nearly $10 million into making Philadelphia’s 1906 Corn Exchange National Bank a high-powered magnet that would attract and retain high-tech talent for his fast-growing company.
The new headquarters combines Beaux Arts authenticity (“It has so much character,” says Aker) with high-tech buzz. Located next to the Betsy Ross House in the historic Old City, it has become a lively addition to Philadelphia’s N3rd (“nerd”) Street tech and design hub.
The project team, led by design firm Ballinger, negotiated with city building code and historic preservation officials to obtain compromises that would meet Linode’s spatial needs and municipal life safety requirements.
A narrow, non-code-compliant staircase was extended to the basement to meet egress requirements. A sprinkler system was installed throughout the building as a concession to keeping certain original elements.
A secured-access third floor with open offices under an original skylight. The interior windows can be opened for acoustical flexibility.
The city’s historic commission wanted to make sure that exterior lighting fixtures would not detract from the historic appearance of the building. The project team used existing conduits to channel power to new light fixtures mounted along existing joint lines, thereby reducing the number of penetrations in the historic façade.
The entire project team was composed of locally based firms, including conservators and specialty crafts workers who restored materials and windows. Conservators used scagliola, a centuries-old technique in which plaster is mixed by hand to create imitation marble, to replace tiles in the basement vault area, a popular gathering spot. (They also kept the original vault door in place.)
To retain the existing substrate of the exterior while blending it with adjacent surfaces, the team came up with a unique approach. Instead of removing patched areas, they used in-painting with a mineral silicate paint to match the appropriate color and texture of the surface. Conservators then toned the patches, using numerous colors to blend with the variable shades of the surrounding limestone.
In the end, Aker’s recruitment strategy worked. Linode has experienced a 100% growth in its workforce since relocating from the suburbs.
GOLD AWARD WINNER
BUILDING TEAM Ballinger (submitting firm, architect/SE) Atlantis Investments LLC (owner) HPE Group (MEP) Materials Conservation Collaborative (conservator) The Lighting Practice (lighting design) C. Erickson and Sons (GC) DETAILS 22,300 sf Total cost $10 million Construction time December 2016 to February 2018 Delivery method CM at risk
Related Stories
Reconstruction Awards | Nov 16, 2015
Lumberyard turned into Chicago charter school
While the existing structures were in poor condition, the Building Team preserved and restored 75% of the spaces and incorporated historic elements in the final design of the Intrinsic School on Chicago's Northwest side.
Reconstruction Awards | Nov 12, 2015
Columbia Grammar and Preparatory School grows with the times
The 251-year-old NYC school was a design-build project that overcame issues like tight space and zoning appeals during its redevelopment.
Reconstruction Awards | Nov 10, 2015
Restoration of the Whitney Building provides hope for Detroit
Four years ago, Whitney Partners purchased the 253,000-sf Whitney for $3.3 million. Their mission was to turn the 19-story structure into a mixed-use hotel, rental apartment, and retail center that would serve as a reminder of more prosperous times in Detroit’s past.
Reconstruction Awards | Nov 9, 2015
University of Chicago uses space economically with Saieh Hall
The five-story, 100,000-sf seminary was converted into a modern education facility that would be fully integrated into the university’s Hyde Park campus. The project demonstrated the university’s commitment to finding a balance between new construction and adaptive reuse of historically significant buildings.
Reconstruction Awards | Nov 9, 2015
King of kings: Classic brooklyn movie theater stages a return engagement
The theater, which withstood vacancy, neglect and vandalism, has been redeveloped with a goal: balance preservation with the creation of a modern performance space.