Originally completed in 1925, Chicago’s Union Station was designated a landmark in 2002 and listed by AIA Illinois as one of the 200 Illinois Great Places. The restoration of the station’s Great Hall sought to maximize the reuse of existing materials and infrastructure, preserve the historic integrity of prior generations, and significantly reduce its energy use.
The project team, led by local architecture firm Goettsch Partners, was brought in to investigate and assess the existing conditions of the 219-foot-long vaulted skylight, and to design and construct a new watertight skylight over the original system, while fully restoring the deteriorative finishes. Previous patch repairs to the leaking skylight altered its appearance and decreased the amount of natural light in the space.
The new, energy-efficient skylight, built five feet above the original cast-iron skylight, is comprised of 858 panes of clear, high-efficiency glass that protects the building while brightening the Great Hall interiors with 50% more daylight than before. Another 2,052 pieces of glass in the existing skylight were replaced.
An energy analysis conducted before work began evaluated the potential impact of the new skylight in conjunction with the existing skylight by creating a 3D model of the existing Great Hall conditions to use as a baseline for simulating different design scenarios. Critical variables were investigated: the annual heating energy, the temperature of the volume of space between the existing and new skylights, the solar heat gain into the Great Hall, and the heat conduction of the new skylight.
Annual heating energy results showed a 13% savings through the combination of replacing the existing monolithic skylight with double glazing, cutting solar heat gain by up to 29% annually, and a 67% savings in heat conduction due to improvements in thermal resistance and the reduction of outdoor air infiltration.
Historic lighting fixtures were restored, rewired, and upgraded to dimmable LED. Surface-mounted cornice lights were replaced with asymmetrical reflector LED fixtures. A control system was then connected to a dimming day/night scene selection with daylight sensor controls to reduce lighting intensity when necessary. This resulted in a 60% reduction in wattage from 1.9 watts/sf to 0.76 watts/sf.
Union Station is the third-busiest metropolitan transportation station in the country, hosting 35 million Metra passengers annually, so it was imperative for the building to remain open with minimal disruptions during the restorative work. A unique 24,000-sf work deck was created and hung from the skylight girders, eliminating scaffolding that would have taken up valuable space on the floor. From this work deck, installation of the new skylight, restoration of the historic skylight, and restoration of the ornamental plaster and historic lighting were completed, all while 130,000 daily commuters passed by directly below.
SILVER AWARD WINNER
BUILDING TEAM Goettsch Partners (submitting firm, architect) Amtrak (owner) Klein & Hoffman (SE) ESD (MEP) Berglund Construction (GC) DETAILS 600,000 sf Total cost $22 million Construction time August 2015 to January 2019 Delivery method Design-bid-build
Related Stories
Reconstruction Awards | Nov 27, 2017
The birthplace of General Motors
The automotive giant salvages the place from which it sprang, 131 years ago.
Reconstruction Awards | Nov 21, 2017
Mama mia! What a pizzeria!: It started as a bank nearly a century ago, now it’s a pizza parlor with plenty of pizzazz
The first floor features a zinc bar and an authentic Neapolitan pizza oven.
Reconstruction Awards | Nov 21, 2017
Honor Guard: San Francisco’s historic Veterans Building pays homage to those who served in World War I and other foreign wars
The Veterans Building houses the War Memorial staff, the city’s Arts Commission, the Opera’s learning center and practice/performance node, the Green Room reception venue, and the 916-seat Herbst Theatre.
Reconstruction Awards | Nov 20, 2017
Eyes wide open: Students can see their new home’s building elements
The two-phase project revamped an opaque, horseshoe-shaped labyrinth of seven buildings from the ’60s and ’70s.
Reconstruction Awards | Nov 17, 2017
Gray lady no more: A facelift erases a landmark’s wrinkles, but not her heritage
The Building Team restored the granite and terra cotta façade and reclaimed more than 500 double-hung windows.
Reconstruction Awards | Nov 17, 2017
Elegance personified: New life for a neglected but still imposing retail/office space
The building was in such disrepair that much of the reconstruction budget had to go toward structural, mechanical, and electrical infrastructure improvements.
Reconstruction Awards | Nov 16, 2017
Back to the '20s: Coney Island gets a new eatery reminiscent of the past
This project included the restoration of the landmark Childs Restaurant.
Reconstruction Awards | Nov 15, 2017
Foyer fantastique: Faded images provide the key to a historic theater's lobby restoration
The restoration relied heavily on historic photos and drawings.
Reconstruction Awards | Nov 14, 2017
Hallowed ground: A Mormon temple rises from the ashes of a fire-ravaged historic tabernacle
Parts of the tabernacle’s exterior shell were the only things that survived the blaze.
Reconstruction Awards | Nov 13, 2017
Harlem Renaissance: A vacant school provides much-needed housing and a clubhouse for children
Word that PS 186 might be demolished brought out the preservationists, whose letter-writing campaign gained the support of the New York Landmarks Conservancy.