Originally completed in 1925, Chicago’s Union Station was designated a landmark in 2002 and listed by AIA Illinois as one of the 200 Illinois Great Places. The restoration of the station’s Great Hall sought to maximize the reuse of existing materials and infrastructure, preserve the historic integrity of prior generations, and significantly reduce its energy use.
The project team, led by local architecture firm Goettsch Partners, was brought in to investigate and assess the existing conditions of the 219-foot-long vaulted skylight, and to design and construct a new watertight skylight over the original system, while fully restoring the deteriorative finishes. Previous patch repairs to the leaking skylight altered its appearance and decreased the amount of natural light in the space.
The new, energy-efficient skylight, built five feet above the original cast-iron skylight, is comprised of 858 panes of clear, high-efficiency glass that protects the building while brightening the Great Hall interiors with 50% more daylight than before. Another 2,052 pieces of glass in the existing skylight were replaced.
An energy analysis conducted before work began evaluated the potential impact of the new skylight in conjunction with the existing skylight by creating a 3D model of the existing Great Hall conditions to use as a baseline for simulating different design scenarios. Critical variables were investigated: the annual heating energy, the temperature of the volume of space between the existing and new skylights, the solar heat gain into the Great Hall, and the heat conduction of the new skylight.
Annual heating energy results showed a 13% savings through the combination of replacing the existing monolithic skylight with double glazing, cutting solar heat gain by up to 29% annually, and a 67% savings in heat conduction due to improvements in thermal resistance and the reduction of outdoor air infiltration.
Historic lighting fixtures were restored, rewired, and upgraded to dimmable LED. Surface-mounted cornice lights were replaced with asymmetrical reflector LED fixtures. A control system was then connected to a dimming day/night scene selection with daylight sensor controls to reduce lighting intensity when necessary. This resulted in a 60% reduction in wattage from 1.9 watts/sf to 0.76 watts/sf.
Union Station is the third-busiest metropolitan transportation station in the country, hosting 35 million Metra passengers annually, so it was imperative for the building to remain open with minimal disruptions during the restorative work. A unique 24,000-sf work deck was created and hung from the skylight girders, eliminating scaffolding that would have taken up valuable space on the floor. From this work deck, installation of the new skylight, restoration of the historic skylight, and restoration of the ornamental plaster and historic lighting were completed, all while 130,000 daily commuters passed by directly below.
SILVER AWARD WINNER
BUILDING TEAM Goettsch Partners (submitting firm, architect) Amtrak (owner) Klein & Hoffman (SE) ESD (MEP) Berglund Construction (GC) DETAILS 600,000 sf Total cost $22 million Construction time August 2015 to January 2019 Delivery method Design-bid-build
Related Stories
Reconstruction Awards | Dec 1, 2017
Rescue mission: Historic movie palace is now the centerpiece of Baltimore’s burgeoning arts hub
In restoring the theater, the design team employed what it calls a “rescued ruin” preservation approach.
Reconstruction Awards | Dec 1, 2017
Gothic revival: The nation’s first residential college is meticulously restored
This project involved the renovation and restoration of the 57,000-sf hall, and the construction of a 4,200-sf addition.
Reconstruction Awards | Dec 1, 2017
Rockefeller remake: Iconic New York tower is modernized for its next life
To make way for new ground-floor retail and a more dramatic entrance and lobby, the team removed four columns at the ground floor.
Reconstruction Awards | Nov 30, 2017
BD+C's 2017 Reconstruction Award Winners
Provo City Center Temple, the Union Trust Building, and the General Motors Factory One are just a few of the projects recognized as 2017 Reconstruction Award winners.
Reconstruction Awards | Nov 29, 2017
College credit: Historic rehab saves 50% on energy costs
The project team conducted surveys of students, faculty, and staff to get their input.
Reconstruction Awards | Nov 29, 2017
Amazing grace: Renovation turns a church into elegant condos
The windows became The Sanctuary’s chief sales edge.
Reconstruction Awards | Nov 28, 2017
Broadway melody: Glass walls set just the right tone for a historic lobby in Lower Manhattan
The adaptation of the 45,000-sf neoclassical lobby at 195 Broadway created three retail spaces and a public walkway.
Reconstruction Awards | Nov 27, 2017
Higher education: The rebirth of a Washington, D.C., high school
The project team, led by architect Perkins Eastman, restored the original cupola.
Reconstruction Awards | Nov 27, 2017
Bank statement: A project team saves a historic bank, yielding 100% leaseup for the developer
The project team had to fix poor renovations made in the ’50s.
Reconstruction Awards | Nov 27, 2017
Patient friendly: The University of Chicago Medicine Center for Care and Discovery adds 203 new beds
Strict infection control and life safety measures were implemented to protect patients on other floors as work proceeded.