flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

How to comply with NYC Local Law 126 parking garage inspection rules

Transportation & Parking Facilities

How to comply with NYC Local Law 126 parking garage inspection rules

Effective January 1, 2022, New York City requires garage owners to retain a specially designated professional engineer to conduct an assessment and file a report at least once every six years.


By HOFFMANN ARCHITECTS + ENGINEERS | October 20, 2022
How to Comply with NYC Local Law 126 Parking Garage Inspection Rules-4376923_1920
Photo: Pixabay

Effective January 1, 2022, New York City requires garage owners to retain a specially designated professional engineer to conduct an assessment and file a report at least once every six years. Here are tips and best practices on how to comply with NYC Local Law 126 parking garage inspection rules. (Download a PDF version of this guide from Hoffmann Architects + Engineers.)

Why is New York City requiring parking garage inspections?

In 2018, New York State enacted a rule requiring periodic condition assessments, performed by a professional engineer, of all parking structures state-wide – except in New York City. Exempt from the state code, NYC developed its own rules for keeping garages and their appurtenances safe and well-maintained. With the passage of Local Law 126 of 2021 and RCNY §103-13, NYC has codified the requirements of this ambitious safety initiative.

Who must perform the parking garage inspection?

A Qualified Parking Structure Inspector (QPSI) has to evaluate the garage and file the report. A licensed engineer with at least three years of parking structure experience, a QPSI earns certification from NYC Department of Buildings (DOB) Parking Structure Unit.

What is required?

Any space for parking/storing motor vehicles, other than an unenclosed outdoor lot, 1- or 2-car garage, or auto service station or showroom, must undergo an assessment by a certified QPSI. 

  1. Document review. The QPSI reviews previous reports, structural designs, repair drawings, violations, and other records. 
  2. Condition assessment. The QPSI designs an assessment program specific to the parking structure, based on type of construction, age, exposure, and other features, as well as history of maintenance and repairs. Physical examination may include sounding, load tests, non-invasive scanning, and/or core extraction, in addition to visual inspection. In evaluating structural components, waterproofing, fireproofing, and wearing surfaces, the QPSI may need to order additional inspections, probes, or tests to identify the probable causes of observed defects. 
  3. Immediate response to Unsafe conditions. Upon identifying an Unsafe condition, the QPSI promptly notifies the owner and the DOB and advises on appropriate protective measures.
  4. Documentation of deficiencies. Photos, sketches, or other means are used to identify the location and extent of defects.
  5. Annual observation checklist. During the condition assessment, the QPSI creates a checklist with elements to be inspected on an annual basis, customized to that specific garage.
  6. Final inspection. In a full walkthrough of each parking level, the QPSI verifies that reported findings reflect actual conditions.
  7. Report filing. Following a prescribed format, the QPSI prepares a Compliance Report with findings and recommendations, classifying the garage as Safe, Unsafe, or “Safe with Repairs and/or Engineering Monitoring” (SREM). The report is filed with the DOB.


What must be included in the report?

Per the code, the report must contain:

  • A summary of findings and recommendations.
  • Classification as Safe, SREM, or Unsafe.
  • Building address, Block and Lot number, Building Identification Number (BIN), landmark status, and owner contact info.
  • Building description, including size, dimensions, usage, age, type of construction, materials, and structural systems.
  • Description of any distress, repairs, or modifications.
  • Procedures used in assessing conditions.
  • Extent and location of physical examinations, contractor contact info, a location diagram, and date of the assessment.
  • Description, classification, and mapping of every significant condition, classifying each as Safe, SREM, or Unsafe. 
  • Recommendations for public protection (Unsafe conditions).
  • Photographs of SREM and Unsafe conditions, keyed to locator drawings, plus photos of each elevation and parking level.
  • Evaluation of guards and railings for positive securement.
  • Analysis of causes of observed SREM and Unsafe conditions.
  • Maintenance work to-date and a maintenance plan.
  • An annual observation checklist.
  • Proposed monitoring program for SREM parking structures.
  • Recommendations for repairs or maintenance.
  • Timeframe by which repairs must be performed.
  • Work permits that may be required.
  • Seal and signature of supervising QPSI.

Reports cannot be filed describing the same condition at the same location as SREM for two consecutive filing cycles. If a previous SREM condition remains uncorrected, the QPSI must classify the parking structure as Unsafe.

What happens if there is an Unsafe condition?

As soon as the QPSI reports an Unsafe condition, the owner must take steps to protect public safety. This might include cordoning off dangerous areas, erecting sidewalk sheds and fences, installing safety netting, and starting repair and reinforcement work.

Unsafe conditions must be corrected within 90 days, unless the QPSI determines that it is not possible to do so and indicates a different timeframe in the report. Deviation from this timeframe requires supporting documents justifying the change.

Within two weeks after repairs are complete, the QPSI must inspect the garage and file an amended report. Protective measures must remain in place until the report is accepted or the QPSI certifies that conditions were corrected and requests removal.

What about SREM conditions?

Any conditions described in the report as SREM must be corrected within the timeframe recommended by the QPSI. Requests for additional time must include supporting documents from the QPSI justifying the new timeframe.

Within three years of the initial filing, a QPSI must undertake another condition assessment and file an amended report, indicating the scope of ongoing monitoring, the status of conditions identified in the initial report as SREM, and classification of any new conditions. Before the next filing cycle, all SREM conditions must be repaired, as they must be reported as Unsafe if not corrected.

NYC Parking Garage Inspection Map v2

NYC Parking Garage Map Key

When do reports need to be completed and filed?

Owners are required to file a report at least once every six years, within the staggered filing windows in the diagram. Reports must be filed within 60 days of the condition assessment.

If the garage is located within a building subject to the Facade Inspection Safety Program (FISP), the owner may opt to change the parking structure filing window so it aligns with the FISP filing window. To do so, the owner must notify the DOB at least 180 days before the end of the assigned parking structure sub-cycle.

Owners of new garages must retain a QPSI to file a report six years from the first Certificate of Occupancy or, if that falls outside the applicable filing window, then within the window for the next cycle.

In addition to required repairs, what do owners need to do between filing cycles?

Each year, parking garages must undergo an “annual observation,” based on the checklist prepared by the QPSI in the inspection report. The person performing the annual observation is obligated to notify the owner and the DOB of any potentially hazardous conditions. Completed annual observation checklists must be kept on file and made available to the DOB if requested.

What are the penalties for failing to comply?

Filing late incurs a hefty penalty of $1,000 per month. Failing to file at all racks up an extra $5,000 per year, in addition to the $1,000 per month late filing penalty. Unsafe conditions not corrected within 90 days bring a penalty of $1,000 per month until the condition is fixed and an amended report is filed (unless an extension has been granted). If an owner allows a SREM condition to languish and become Unsafe in the next cycle, they’ll face a $2,000 penalty, plus risk more penalties if the condition continues to go unaddressed.

Waivers may be requested when change in ownership, a state of emergency, bankruptcy, or demolition preclude compliance.

What’s the main takeaway?

If you own a parking structure west or south of Central Park in Manhattan, you need to take immediate action. Owners of garages in these districts only have until December 2023 to retain one of the small number of professional engineers currently certified by NYC Department of Buildings as QPSIs, then to schedule the inspection and allow time for the QPSI to file a Compliance Report. 

Owners of garages in upper Manhattan and Brooklyn don’t have much time to waste, either, with the filing period for those districts opening in 2024. For all parking structure owners in the City, it doesn’t hurt to plan ahead, as demand for limited QPSI resources and looming deadlines will likely lead to a last-minute scramble to meet inspection and filing requirements.

Resources
NYC Buildings Parking Structures Resource Page
Local Law 126 of 2021 – see Article 323, p. 229-232
RCNY §103-13: Periodic Inspection of Parking Structures

Hoffmann Architects + Engineers was among the first to have a certified QPSI. We are one of a select few currently authorized to carry out NYC Local Law 126 parking garage inspections. Reach out to us at (212) 789-9915 or hoffarch.com/contact-us

Material provided is for informational purposes. Before taking action, consult a design professional.

Related Stories

Transportation & Parking Facilities | May 20, 2015

Federal Highway Administration releases guide for protected bike lanes

The guide consolidates lessons learned from practitioners designing and implementing separated bike lanes across the U.S.

High-rise Construction | May 6, 2015

Parks in the sky? Subterranean bike paths? Meet the livable city, designed in 3D

Today’s great cities must be resilient—and open—to many things, including the influx of humanity, writes Gensler co-CEO Andy Cohen. 

Building Team Awards | Apr 10, 2015

14 projects that push AEC teaming to the limits

From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.

Building Team Awards | Apr 10, 2015

Anaheim’s soaring intermodal hub

Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.

Building Team Awards | Apr 9, 2015

Nation's first LEED-certified bus depot

A bus garage in Harlem shows that even the most mundane of facilities can strut its environmentally sensitive stuff.

Structural Materials | Mar 30, 2015

12 projects earn structural steel industry's top building award

Calatrava's soaring Innovation Science and Technology Building at Florida Polytechnic University is among the 12 projects honored by the American Institute of Steel Construction in the 2015 IDEAS² awards competition. 

Transit Facilities | Mar 4, 2015

5+design looks to mountains for Chinese transport hub design

The complex, Diamond Hill, will feature sloping rooflines and a mountain-like silhouette inspired by traditional Chinese landscape paintings.

Sponsored | | Mar 3, 2015

New York’s Fulton Center relies on TGP for light-flooded, underground transit hub

Fire-rated curtain wall systems filled this subterranean hub with natural light.

Transit Facilities | Feb 12, 2015

Gensler proposes network of cycle highways in London’s unused underground

Unused tube lines would host pedestrian paths, cycle routes, cultural spaces, and retail outlets.

boombox1 - default
boombox2 -
native1 -

More In Category

Giants 400

Top 45 Parking Structure Engineering Firms for 2023

Walker Consultants, Kimley-Horn, Wiss, Janney, Elstner Associates, KPFF Consulting Engineers, and Walter P Moore head BD+C's ranking of the nation's largest parking structure engineering and engineering/architecture (EA) firms for 2023, as reported in the 2023 Giants 400 Report.  


Giants 400

Top 55 Parking Structure Construction Firms for 2023

PCL Construction Enterprises, Swinerton, Bomel Construction, McCarthy Holdings, and Alberici-Flintco top BD+C's ranking of the nation's largest parking structure general contractors and construction management (CM) firms for 2023, as reported in the 2023 Giants 400 Report.


Giants 400

Top 60 Parking Structure Architecture Firms for 2023

Choate Parking Consultants, Page Southerland Page, Gensler, AO, and Elkus Manfredi Architects top BD+C's ranking of the nation's largest parking structure architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report.


halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021