PROJECT SUMMARY

Aug. 11, 2010

Adam Joseph Lewis Center at Oberlin College

Oberlin, Ohio

Building team

Owner: Oberlin College

Architect: William McDonough + Partners

General contractor: Mosser Construction

Structural and mechanical/electrical engineer: Lev Zetlin Associates

Energy consultant: Steven Winter Associates

General information

Area: 13,600 gross square feet

Number of floors: 2

Construction time: September 1998 to January 2000

Construction cost: $6.61 million

Delivery method: Design/bid/build

Project suppliers

Photovoltaic panels: BP Solarex

Access flooring: Interface

Wastewater treatment: Living Technologies Inc.

Sustainable wood: Collins Cos., Kane Hardwood, Columbia Forest Products