Force Majeure and COVID-19 in construction contracts - What you need to know

Coronavirus

Force Majeure and COVID-19 in construction contracts - What you need to know

With the onset of the COVID-19 pandemic, we are all taking a closer look at many portions of our contracts.


By Gordon Rees Scully Mansukhani | March 19, 2020

Courtesy Pixabay

“Force Majeure” – While most construction contracts contain these provisions, they are often not understood  in relation to the implications they may have on construction projects. With the onset of the COVID-19 pandemic, we are all taking a closer look at many portions of our contracts. The following is a brief primer on how to understand your construction contract and its potential implications on your business in this season of change.

 

What is a Force Majeure?

Construction contracts usually take into consideration that the parties want to agree at the outset on who bears the risk of unforeseen incidents that may affect the project’s progression. These issues are generally handled in a “force majeure” clause. Force majeure, according to Mariam Webster’s Dictionary is a “superior or irresistible force; or an event or effect that cannot be reasonably anticipated or controlled.” To be deemed a force majeure, generally the circumstances must be outside of a party’s control which makes performance impossible, inadvisable, commercially impractical, or illegal. In addition to being unforeseeable, the circumstances must have external causation, and be unavoidable. However, the key to understanding if COVID-19 will be deemed a condition that will excuse a contractor’s performance is the specific language in the provision.

Generally force majeure events are unavoidable events such as “acts of God,” most notably weather conditions including hurricanes, tornadoes, floods, earthquakes, landslides, and wildfires, as well as certain man-made events like riots, wars, terrorism, explosions, labor strikes, and scarcity of energy supplies. However, there is not much case law or specifics on conditions similar to COVID-19.

 

What are the Key Aspects of a Force Majeure Clause?

While force majeure is a recognized concept in most legal systems, it usually does not have a precise legal definition. As a result, parties must generally look to the specific language used in the contract. Most contracts include a definition of force majeure and often include a non-exhaustive list of both illustrative force majeure events and events that do not constitute force majeure. The contract interpretation will often turn on how the event of force majeure is characterized.

First, to be classified as a force majeure event, the event must be beyond the control of the contracting parties, it cannot be anticipated, foreseeable, or expected, and the event must be unavoidable. The circumstances must also be found to be externally caused, unforeseeable, and unavoidable. The specifics that you are looking to call the force majeure are important — what is the claimed impediment to performance? Is the circumstance the outbreak of the disease, an order by the government trying to contain the spread of the disease, or lack of materials or manpower. Once the event is determined and the specific force majeure is clarified, there must be found to be a sufficient causal link between the alleged force majeure and the claiming party’s non-performance. Finally, even if the declaration of force majeure is validly given, the amount of time that performance should be excused and the time at which the force majeure has ceased to exist will need to be addressed.

 

Can I trigger my Force Majeure Clause due to impacts from COVID-19?

The most secure means of ensuring that you can trigger your force majeure clause to excuse performance, or extend time for performance, is if your provision specifically calls out a pandemic or other similar serious disease, epidemic, or public health issue. However, most contract provisions do not contain that level of specificity. The next step would be to see if the terms in your contract include sufficient examples that can be found to be analogous to a public health crisis such as we are currently experiencing. In many instances, the risk will rest on the contractor and not the owner for increased costs for material shortages and/or price increases unless another provision (such as price escalation clauses) apply.

The best course of action is to ensure that you negotiate as specific and clear language as possible to define the scope and effect of a force majeure clause to protect against unexpected liabilities. The following elements should be addressed in a force majeure clause:

  • What events are considered force majeure?
  • Who is responsible for suspending performance?
  • Who is allowed to invoke the clause?
  • Which contractual obligations are covered by the clause?
  • How should the parties determine whether the event creates an inability to perform?
  • What happens if the force majeure event continues for more than a specified period of time?

If you already have force majeure clauses in your standard contracts, we recommend a review of those provisions to ensure the terms provide clear, comprehensive, and adequate protections for the company and consider whether terms such as “widespread epidemic,” “pandemic,” and/or “public health emergency” should be added. We have seen courts loathe to extend the interpretation of force majeure clauses beyond what is specifically listed in the contract. While the impact of the COVID-19 pandemic is likely to be found to be unforeseen and externally caused, the key issue will likely be whether the impact was unavoidable.

You also should review the terms of your existing force majeure clauses in preparation for potentially needing to invoke them for COVID-19-related issues. In the event you are unable to assert a force majeure clause when faced with such events, the doctrine of impossibility and impracticability may be your next best bets. The common law doctrine of impossibility "allows a party to suspend or avoid performance when a supervening event beyond its control makes performance of the contract no longer capable of being performed.” (17A Am. Jur. 2d Contracts § 655 (2010).) For example, where unforeseeable severe material shortages or an embargo render the materials necessary to complete a construction contract completely unavailable, impossibility is probably a viable defense. However, the more likely effect of an embargo or a material shortage is that it will significantly increase the cost of completing a contract, but not render it impossible. In such a scenario, a party's best defense may be the doctrine of commercial impracticability. However, the terms of the contract must be carefully consulted to determine whether any waiver or assumption of these risks were included.

Many courts have moved beyond the requirement of “absolute impossibility" and recognize the doctrine of commercial impracticability, which allows a party to be excused from performance where, although performance of the party's contractual obligations is technically possible, changed circumstances have rendered performance commercially unreasonable. The doctrine of commercial impracticability is codified in the Uniform Commercial Code § 2-615 "Excuse by Failure of Presupposed Conditions" (however, the U.C.C. only applies to commercial goods). When deciding U.C.C. cases involving commercial impracticability, in addition to U.C.C. § 2-615, courts often also expressly discuss the Restatement of Contracts (Second) § 261, which sets forth the common law application of the doctrine of commercial impracticability. Thus, the holdings of these U.C.C. cases should be generally applicable to non-U.C.C. construction contracts involving the provision of services.  (15 J.L. & Com. 213, 214-15 (1995).) 

Generally, in order to prevail on a defense of commercial impracticability, a party must show the following: "(i) a supervening event, either an 'act of God' or an act of a third party, made performance impracticable, (ii) the non-occurrence of the event was a basic assumption upon which the contract was based; (iii) the occurrence of the event was not the party's fault; and (iv) the party did not assume the risk of the event's occurrence.” (L.W. Matteson, Inc. v. U.S., 61 Fed. Cl. 296, 320 (2004).) Whether non-occurrence of a particular event "was a basic assumption" generally depends upon the foreseeability of the event. (15 J.L. & Com. 213, 214-15 (1995).) "If a disruptive event was foreseeable and the promisor failed to protect himself by means of an express provision in the contract (a force majeure clause), then the promisor will be deemed to have assumed the risk of the disruptive event." (Id.)

However, "a severe shortage of raw materials or of supplies due to a contingency such as a war, embargo, local crop failure, unforeseen shutdown of major sources of supply or the like, which either causes a marked increase in cost" or prevents performance altogether is likely sufficient for an impracticability defense under the U.C.C. (See U.C.C. § 2-615.) The Restatement's comments echo those of the U.C.C. and provide that such circumstances would also probably be sufficient for an impracticability defense in a contract for services. (See RESTATEMENT (SECOND) OF CONTRACTS § 261 (1981).) Accordingly, it appears that the doctrine of impracticability can relieve a party from its contractual duties when faced with price increases caused by severe material shortages or an embargo, or even arguably when faced with a health pandemic affecting global commerce.

In conclusion, there may be steps you can take now to protect yourself and to negotiate an agreement with your contracting partners as to how to weather this storm as well as to ensure that you comply with any notice requirements or mitigation efforts required. At a minimum, consult with an experienced construction lawyer to evaluate your risk and determine what risk management and mitigation steps you should be taking while this situation unfolds.

Visit our COVID-19 Hub for ongoing updates.

Related Stories

Coronavirus | Mar 19, 2020

Positive vibes: Let's take a look at the brighter side of these crazy times

Perhaps now is a good time to take a page from Monty Python's book and look on the bright side of life. So let's push aside the doom and gloom for a bit and bring a little positivity to these strange times we all currently find ourselves in.

Coronavirus | Mar 19, 2020

Technology crucial during COVID-19 social distancing

Technology can help bridge the gap during the Coronavirus pandemic as higher education institutes and corporations are moving to a remote work model.

Coronavirus | Mar 18, 2020

Coronavirus latest: Short-term pain but strong rebound likely, says Oxford Economics

Once the disruption and uncertainty fade, the rebound in global economic activity will be strong. It’s important for firms to position themselves for such a recovery.

Coronavirus | Mar 18, 2020

We are in the midst of a paradigm shift for higher education

The question for higher education is, what will the university of the future look like?

Coronavirus | Mar 17, 2020

AIA: Design services saw increase in February, but economic footings are rapidly shifting

"The rapid pull-back in activity throughout the economy will obviously be felt in the design and construction sector, and architecture firms will be one of the first to see how these events play out,” said AIA Chief Economist, Kermit Baker, Hon. AIA, PhD.

Coronavirus | Mar 17, 2020

AGC to government officials: Shutting down construction projects is an unnecessary step

Construction firms are already taking steps to protect employees, most of whom already wear protective equipment, while halting work will undermine efforts to add hospital capacity.

Coronavirus | Mar 16, 2020

Boston mayor orders shut down of construction sites due to coronavirus

Boston Mayor Martin Walsh has ordered that all construction projects in the city be suspended in response to the spread of the coronavirus.

Coronavirus | Mar 16, 2020

Effective remote workforce: Key steps and strategies for success

As the potential scope of the COVID-19 outbreak has become more clear in the United States and Canada, public and private organizations from all industries, sectors and geographies are encouraging their teams to work remotely to reduce the spread of the virus.

Coronavirus | Mar 16, 2020

Coronavirus and the water cycle—here is what treatment professionals need to know

As the global health community tracks the spread of this virus, it’s important for water and wastewater professionals to keep updated on potential impacts.

Coronavirus | Mar 15, 2020

Designing office building lobbies to respond to the coronavirus

Touch-free design solutions and air purifiers can enhance workplace wellness.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021