Digital tools accelerated the design and renovation of one contractor’s new office building

BIM and Information Technology

Digital tools accelerated the design and renovation of one contractor’s new office building

One shortcut: sending shop drawings created from laser scans directly to a wood panel fabricator.


By John Caulfied, Senior Editor | March 28, 2017

Photo courtesy of Heywood Chan Photography

Portland, Ore.-based Hoffman Construction is a national contractor that prides itself on using digital tools to complete its projects.

So, in mid 2015, when it was planning to renovate a 10,000-sf office space in Seattle, Hoffman challenged its interior designer, Gensler, to take a similar approach that would highlight Hoffman’s digital integration and technical delivery techniques.

With the help of a host of digital products—including SketchUp, Revit, Faro, Navisworks, Cyclone, AutoCAD and CNC—the Building Team designed the space in just four weeks and helped the client build it in seven.

“Hoffman is always looking to do the impossible in a possible amount of time. Gensler saw us as innovators showcasing our talents with this project,” says Kevin Ryan, operations manager and GM for Hoffman Construction in Seattle.

The focal point was the Think Tank, a 2,000-sf space that would serve as the office’s central hub. That space, according to Jeroen Teeuw, Senior Associate at Gensler who was Lead Designer on this design-build project, is clad in over 100 unique panels that were fabricated from shop drawings produced by digital scans. Fuller Cabinets in Eugene, Ore., supplied the panels, which were fabricated by Straight-Up Carpentry in Oregon.

 

Photo courtesy of Heywood Chan Photography.

 

Teeuw says that, before this job, Gensler had only rarely employed digital scanning for interior projects. The scans, he says, were accurate to the point where no tweaks to the design were necessary. “Hoffman had a lot of trust in us,” he says.

Demolition started on Sept. 1, 2015, and included four weeks of asbestos mitigation. Building started the first week October. Hoffman wanted to occupy the building by Christmas, “so we had to identified what absolutely needed to be done in order to satisfy the fire marshals and inspectors,” recalls Ryan. The Building Team stripped the floors, knocked down walls, and installed new T-bar ceilings.

For the renovation, the Building Team broke up the shop drawings into several packages, which Ryan says all but eliminated material waste.

Hoffman achieved its goal, even though the office wasn’t fully completed until April 2016. The space includes conference rooms and private offices, a central teaming area, pantry/lounge/kitchen, open workspace, facilities space, and a reception area.

Related Stories

BIM and Information Technology | Oct 12, 2015

NIBS launches effort to develop BIM guideline for owners

Aim is to provide uniformity in the delivery of BIM projects.

BIM and Information Technology | Oct 11, 2015

VR for all: How AEC teams are benefiting from the commercialization of virtual reality tools

AEC teams are using gaming engines to not just showcase their projects, but to immerse their clients, end users, and Building Team members in highly detailed, fully lit environments that simulate the final structure. 

BIM and Information Technology | Oct 9, 2015

Facebook’s data center complex has become economic engine for one North Carolina town

Cities are now vying for these facilities with sizable tax incentives.

BIM and Information Technology | Oct 7, 2015

Skanska and University of Washington offer new BIM program

The 11-week course is available for students and professionals and teaches BIM software skills, virtual design, and construction processes.

Sponsored | BIM and Information Technology | Oct 7, 2015

Microsoft’s Surface Pro 3 – designed with the AEC industry in mind

Sasha Reed sits down with Microsoft’s Senior Director of Programs, Pete Kyriacou to discuss the unique challenges AEC professionals face and why the  Surface Pro 3 was designed to help them be more productive.

Sponsored | BIM and Information Technology | Oct 1, 2015

How can owners make better decisions with the help of analytics?

Sasha Reed sits down with David Fano, Chief Technology Officer for WeWork  (formerly with CASE), at BIMForum to discuss how owners make better decisions with the help of analytics.

Modular Building | Sep 23, 2015

SOM and DOE unveil 3D-printed, off-the-grid building

The Additive Manufacturing Integrated Energy (AMIE) building features a high-performance shell with a photovoltaic roof and built-in natural gas generator.

BIM and Information Technology | Sep 16, 2015

Norman Foster proposes 'drone ports' as a way to ship goods across Africa

The structures would store cargo-shipping drones and serve as community centers.

BIM and Information Technology | Sep 16, 2015

VIDEO: See how Wiss, Janney, Elstner engineers use drones to perform building inspections

"We believe that drone usage will enable building owners to assess problems quicker and with less risk to the general public and workers,” said WJE Principal Michael Petermann.

BIM and Information Technology | Sep 14, 2015

Is Apple's new iPad Pro a game changer for architects?

A stylus, split screen, and improved graphics make designing on the tablet easier.

boombox1 - default
boombox2 -
native1 -

More In Category

AEC Tech

Lack of organizational readiness is biggest hurdle to artificial intelligence adoption

Managers of companies in the industrial sector, including construction, have bought the hype of artificial intelligence (AI) as a transformative technology, but their organizations are not ready to realize its promise, according to research from IFS, a global cloud enterprise software company. An IFS survey of 1,700 senior decision-makers found that 84% of executives anticipate massive organizational benefits from AI. 




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021