flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Data center construction facing record-breaking inflation, delays

Data Centers

Data center construction facing record-breaking inflation, delays

Average cost to build has increased by 15%.


By Peter Fabris, Contributing Editor | October 31, 2022
Data Center Construction
Courtesy Pexels.

Data center construction projects face record-breaking inflation amid delays to materials deliveries and competition for skilled labor, according to research from global professional services company Turner & Townsend.

Average costs on data center projects rose 15% in 2022 compared to last year, with escalating prices for energy and key materials squeezing margins. Intense competition for labor from life sciences, gigafactories, and other large-scale advanced manufacturing facilities in North America is driving up labor costs. Some 92% of respondents reported that they are struggling to meet construction demand due to a shortfall of experienced site teams.

Supply chain woes resulting in extended equipment and material lead times are jeopardizing program completion dates, with delays of more than 12 weeks for some components. Of the 45 key markets covered in the survey, North America has five of the top ten most expensive world markets. This is prompting clients to re-evaluate their development strategies to consider building in less costly new or emerging regional markets such as Columbus and Canada.

Despite these challenges, optimism remains high in the sector with 71% of respondents seeing the sector as less susceptible to recessionary pressures than other industries.

Related Stories

Giants 400 | Aug 28, 2019

Top 50 Data Center Engineering Firms for 2019

Vanderweil, ESD, kW Mission Critical, Jacobs, and EXP head the rankings of the nation's largest data center sector engineering and engineering architecture (EA) firms, as reported in Building Design+Construction's 2019 Giants 300 Report.

Giants 400 | Aug 28, 2019

Top 35 Data Center Architecture Firms for 2019

Corgan, HDR, Gensler, AECOM, and Page top the rankings of the nation's largest data center sector architecture and architecture engineering (AE) firms, as reported in Building Design+Construction's 2019 Giants 300 Report.

Data Centers | Aug 9, 2019

This will be Central Florida’s largest data center

Baker Barrios Architects is designing the project.

Data Centers | Jul 25, 2018

Data centers keep cool while staying hot-hot-hot

Cooling mission critical facilities efficiently is critical to their operations and profitability.

Data Centers | Jun 22, 2018

Can this new data center concept combat climate change?

The concept has been dubbed The Spark.

Data Centers | Feb 22, 2018

Demand for ‘hyperscale’ data centers continues to grow; U.S. leads the way

The number of so-called “hyperscale” data centers worldwide surpassed 390 at the end of 2017, with 69 more facilities in the works, according to Synergy Research Group.

Giants 400 | Oct 16, 2017

Data center market forecast: Clearly cloudy

Look for mission-critical construction to double in the next few years.

Data Centers | Oct 13, 2017

Top 35 data center construction firms

Turner Construction Co., Holder Construction, and DPR Constrcution top BD+C’s ranking of the nation’s largest data center sector contractors and construction management firms, as reported in the 2017 Giants 300 Report.

Giants 400 | Oct 12, 2017

Top 30 data center engineering firms

Syska Hennessy Group, AECOM, and Morrison Hershfield top BD+C’s ranking of the nation’s largest data center sector engineering and EA firms, as reported in the 2017 Giants 300 Report.

Giants 400 | Oct 11, 2017

Top 25 data center architecture firms

Jacobs, Corgan, and Gensler top BD+C’s ranking of the nation’s largest data center sector architecture and AE firms, as reported in the 2017 Giants 300 Report.

boombox1 - default
boombox2 -
native1 -

More In Category

Data Centers

What’s next for data center design in 2024

Nuclear power, direct-to-chip liquid cooling, and data centers as learning destinations are among the emerging design trends in the data center sector, according to Scott Hays, Sector Leader, Sustainable Design, with HED. 




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021