Cost of HVAC equipment to remain flat in 2009, says Turner

Cost of HVAC equipment to remain flat in 2009, says Turner


August 11, 2010
This article first appeared in the 200906 issue of BD+C.

While some manufacturers have announced slight increases in facilities equipment pricing for 2009, the average cost of equipment is expected to remain flat in 2009, according to the 2009 Turner Logistics Equipment Cost Index. However, equipment pricing could face increased pressure if there is a further decline in market demand.

Published by Turner Logistics, the facility equipment solutions arm of Turner Construction, the report tracks the average cost and lead time for common facilities equipment, including chillers, generators, cooling towers, and air-handling units.

Turner anticipates that lead times will continue to improve. Signs of production consolidation have been noted as manufacturers adjust workforce and production capacity.

 
Estimated lead times for HVAC equipment in 2009
(varies due to equipment sizing)
Cooling towers: 6–10 weeks Chillers: 12–20 weeks Air-handling units: 10–18 weeks Generators: 8–30 weeks Medium voltage switchgear: 12–18 weeks Uninterruptible power supply: 18–22 weeks

Related Stories

Building Technology | Mar 26, 2019

Chain of command: Blockchain for AEC

Blockchain isn’t just about exchanging Bitcoin. It could emerge as the next construction management and lifecycle assessment tool.

Building Technology | Mar 25, 2019

Blockchain: A primer

The simplest explanation of this technology is that blockchain is a digital distributed ledger of transactions or records that exists across multiple participants and computers in a peer-to-peer network.

Industrial Facilities | Mar 10, 2019

The burgeoning Port San Antonio lays out growth plans

Expansions would accommodate cybersecurity, aerospace, and defense tenants, and help commercialize technologies.

Building Technology | Mar 8, 2019

What is your firm's innovation 'hit rate'?

As firms begin to adopt the practices and mindset of Silicon Valley tech and advanced manufacturing, it’s fair to ask: Are all of these innovation projects and initiatives working?

Building Technology | Mar 6, 2019

Australia’s prefab construction sector is trying to break out from its 'getting there' stage

A paper by Deloitte looks back at an origin case study. But the country has yet to develop a fully formed industry.

Building Technology | Feb 21, 2019

Smart buildings take hold: 8 ways smart tech is transforming commercial buildings

The next generation of intelligent buildings offers promise for unseen levels of energy efficiency, optimization, and occupant health and productivity.

Building Technology | Dec 20, 2018

Autodesk is spending $1.15 billion to acquire two construction tech providers

PlanGrid and BuildingConnected are the latest pieces in the company’s quest to digitize the construction industry.

Building Technology | Dec 18, 2018

Data and analytics are becoming essential for EC firms competing to rebuild America’s infrastructure

A new paper from Deloitte Consulting advises companies to revise their strategies with an eye toward leveraging advanced technologies.

3D Printing | Dec 7, 2018

Additive manufacturing heads to the jobsite

Prototype mobile 3D printing shop aims to identify additive manufacturing applications for construction jobsites.

Energy Efficiency | Dec 5, 2018

Harvard debuts HouseZero as a possible response to making existing buildings more efficient

Hundreds of embedded sensors will inform energy use reduction research.

boombox1
boombox2
native1

More In Category

Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021