Construction nears completion on $1B Grand Egyptian Museum in Cairo

Projects

Construction nears completion on $1B Grand Egyptian Museum in Cairo

Set to open in late 2022, the museum will be the largest museum in the world dedicated to one civilization.


By Novid Parsi, Contributing Editor | March 2, 2022
Grand Egyptian Museum
The Grand Egyptian Museum is set to open in late 2022. Photo courtesy Hill International

At an estimated budget of $1 billion, the Grand Egyptian Museum (GEM) is considered the largest museum in the world dedicated to one civilization. The superlatives don’t end there: It’s also the largest museum in Egypt, the largest Pharaonic museum in the world, and one of the world’s leading scientific, historical, and archeological study centers. 

Aerial View
Aerial view of the Grand Egyptian Museum in Cairo. Photo courtesy Hill International

Designed by Irish architects Henghan Peng, the museum sits on the edge of the Giza Plateau, between the pyramids and Cairo. Visitors move through a massive forecourt before ascending to the plateau level, where the galleries are located. There, visitors to the futuristic glass-and-concrete structure can glimpse the ancient pyramids 2 kilometers away.

Owned by the Ministry of Tourism & Antiquities, Engineering Authority of the Egyptian Armed Forces, the 168,000-square-meter structure includes 24,000 square meters of permanent exhibition space covering 3,500 years of ancient Egyptian history. It houses 100,000 artifacts, about 20,000 of them on display for the first time. The precious objects include a 30-foot-tall, 3,200-year-old statue of Ramses the Great, a 140-foot solar boat found buried beside the Great Pyramid, and the Tutankhamun collection. The project also includes a children’s museum and extensive gardens. In all, GEM will accommodate 4.8 million visitors a year.

Entrance Courtyard
The entrance courtyard of the Grand Egyptian Museum, as of August 2018. Photo courtesy Hill International

Construction unfolded over three phases. The first involved clearing the site; the second entailed constructing a fire station, energy supply center, and conservation center. The final phase saw the construction of the main building as well as landscaping. 

Construction is now 99% complete, with the remaining 1% representing the final touches and logistics for the official opening, planned for November 2022. It will mark the end of a long journey for the project, which got its start in the early 1990s when a decree from Egypt’s president allocated nearly 50 hectares of land at Giza.

Corner Temple
The corner temple of the Grand Egyptian Museum as of December 2020. Photo courtesy Hill International

The architect of record is Raafat Miller Consulting. Other team members include structural engineer OVE Arup & Partners, MEP engineer Buro Happold, and general contractors BESIX and Arab Contractors Joint Venture. The project manager is a joint venture between Hill International and EHAF Consulting Engineers.

Related Stories

Affordable Housing | Feb 15, 2023

2023 affordable housing roundup: 20+ multifamily projects

In our latest call for entries, Building Design+Construction collected over 20 multifamily projects with a focus on affordable housing. Here is a comprehensive list of all projects in alphabetical order.

Sponsored | Projects | Feb 6, 2023

How Suffolk Construction leverages Procore data in real-time with Toric

Read how Suffolk Construction enables project stakeholders to make better-informed project decisions faster by feeding data from sources like Procore and Oracle P6 as actionable insights.

Augmented Reality | Jan 27, 2023

Enhancing our M.O.O.D. through augmented reality therapy rooms

Perkins Eastman’s M.O.O.D. Space aims to make mental healthcare more accessible—and mental health more achievable.

Senior Living Design | Jan 10, 2023

8 senior living communities that provide residents with memory care

Here are eight senior living communities that offer their residents memory care, an important service for residents who need this specialized care.

Adaptive Reuse | Dec 21, 2022

University of Pittsburgh reinvents century-old Model-T building as a life sciences research facility

After opening earlier this year, The Assembly recently achieved LEED Gold certification, aligning with the school’s and community’s larger sustainability efforts.

K-12 Schools | Dec 20, 2022

Designing an inspiring, net zero early childhood learning center

LPA's design for a new learning center in San Bernardino provides a model for a facility that prepares children for learning and supports the community.

Student Housing | Dec 7, 2022

9 exemplary student housing projects in 2022

Production continued apace this year and last, as colleges and universities, for-profit developers, and their AEC teams scrambled to get college residences open before the start of classes.

Building Materials | Aug 3, 2022

Shawmut CEO Les Hiscoe on coping with a shaky supply chain in construction

BD+C's John Caulfield interviews Les Hiscoe, CEO of Shawmut Design and Construction, about how his firm keeps projects on schedule and budget in the face of shortages, delays, and price volatility.

Office Buildings | Apr 11, 2022

SOM-designed office tower aims to promote health and wellness

Skidmore, Owings & Merrill (SOM) recently completed work on 800 Fulton Market, a new mixed-use office building in Chicago’s historic Fulton Market/West Loop neighborhood.

Government Buildings | Apr 11, 2022

Milan’s new US Consulate celebrates Italian design

In Milan, Italy, the new U.S. Consulate General broke ground on April 6. Managed by Overseas Buildings Operations (OBO), a U.S. government agency that directs overseas builds, the 10-acre campus will feature a new Consulate building, as well as the restoration of the site’s historic Liberty Building and reconstruction of a pavilion on the 80,000-square-foot parade ground.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021