TSX Broadway is a 550,000-sf 46-story mixed-use tower that’s been under construction in New York City’s Times Square since 2019. This $2.5 billion project—whose development partners include L&L Holding, Maefield Development, Fortress Investment, and The Nederlander Organization—has retained 25 percent of site’s existing structure that included 16 stories of what had been a DoubleTree hotel, and the iconic Palace Theater, which on January 7 began its journey from the ground floor of this site to being lifted and repositioned 30 ft above grade to make way for 75,000 sf of street-level retail.
The lift of the 7,000-plus-ton, 27,000-sf theater with landmark status was expected to take six to eight weeks, at which point the Palace Theater will undergo a $50 million renovation that includes a new entrance on 47th Street with an 80-ft marquee, the addition of 10,000 sf of front-of-house space with a new lobby, a new orchestra pit for the 1,700-seat theater, and more back-of-house space.
Last week, the project’s Building Team poured the 43rd floor of TSX Broadway, which along with the theater is scheduled for completion in the fourth quarter of 2022, according to Robert Israel, Executive Vice President of L&L Holding and the firm’s project manager, with whom BD+C spoke earlier this week.
Also see: An animation of the demolition, excavation, and theater lift
HEAVY LIFTING
This project, he said, required a new permanent foundation, a new subcellar level, and a lifting foundation. The lift itself is utilizing a mechanism, devised by Urban Foundation Engineering, that combines 34 structural lifting posts and 136 hydraulic jacks. Israel said that the developers hired the structural engineering consultant Howard Shapiro & Associates to ensure the security and stability of the structure and theater, which was originally built in 1913 and remodeled in 1988.
The 580-ft-tall tower, when completed, will also feature a 669-key hotel (Israel said the developers were close to signing a branding and property management deal, but could not disclose the hotelier).
RISING ABOVE THE NOISE
The building will also have several signage and lighting systems, all designed for marketing purposes: the exterior of floors three through nine will be distinguished by an 18,000-sf LED podium sign into which is integrated an indoor-outdoor stage with a 30x30-ft opening and a 35-ft depth that extends 10 ft outside beyond the LED lights. Israel suggested that this space could be used for New Year’s Eve events, and all manner of performances and broadcasts.
There will also be crown signage at the top of the building, and a full-tower lighting system, dubbed The Beacon, that will be able to project programmed messages and images.
Also see: How TSX Broadway will become the world’s largest billboard
TSX Broadway’s Building Team includes Mancini Duffy (AOR core and shell and hotel), PBDW Architects (AOR theater design and historic preservation), Jablonski Building Conservation (historic preservation consultant), Wise Janney Elsner Engineers & Architects (plaster structural support consultant), Cosentini (MEP), Langan (SOE/foundation engineering consultant), Severud (SE), and Perkins Eastman (lead design of building envelope).
Related Stories
Resiliency | Aug 19, 2021
White paper outlines cost-effective flood protection approaches for building owners
A new white paper from Walter P Moore offers an in-depth review of the flood protection process and proven approaches.
Cultural Facilities | Aug 2, 2021
A new venue for the San Diego Symphony’s outdoor performances opens this week
Rady Shell at Jacobs Park was funded almost entirely by private donors.
Cultural Facilities | Jun 28, 2021
Maine’s Children’s Museum & Theatre moves into new location that doubles its size
Interactive exhibits are among its features.
Resiliency | Jun 24, 2021
Oceanographer John Englander talks resiliency and buildings [new on HorizonTV]
New on HorizonTV, oceanographer John Englander discusses his latest book, which warns that, regardless of resilience efforts, sea levels will rise by meters in the coming decades. Adaptation, he says, is the key to future building design and construction.
Multifamily Housing | Jun 3, 2021
Student Housing Trends 2021-2022
In this exclusive video interview for HorizonTV, Fred Pierce, CEO of Pierce Education Properties, developer and manager of off-campus student residences, chats with Rob Cassidy, Editor, MULTIFAMILY Design + Construction about student housing during the pandemic and what to expect for on-campus and off-campus housing in Fall 2021 and into 2022.
Digital Twin | May 24, 2021
Digital twin’s value propositions for the built environment, explained
Ernst & Young’s white paper makes its cases for the technology’s myriad benefits.
Wood | May 14, 2021
What's next for mass timber design?
An architect who has worked on some of the nation's largest and most significant mass timber construction projects shares his thoughts on the latest design trends and innovations in mass timber.
Cultural Facilities | Apr 1, 2021
A Connecticut firm deploys design to assist underserved people and communities
Hartford, Conn.-based JCJ Architecture traces its roots to 1936, when the U.S. was just coming out of an economic depression and its unemployment rate was still 14%. In 2021, with the country trying to recover economically from the impact of the coronavirus, and with questions about social inequity entering the public debate as rarely before, JCJ has focused its design work on projects and clients that are committed to social responsibility and advocacy, particularly for underserved or marginalized communities.
Cultural Facilities | Mar 1, 2021
Moise Safra Center completes in New York City
The project will act as a second home for the Jewish community it serves.
Market Data | Feb 24, 2021
2021 won’t be a growth year for construction spending, says latest JLL forecast
Predicts second-half improvement toward normalization next year.