Operations and maintenance: The missing link in BIM/VDC coordination

May 02, 2013 |
David Barista

For as much progress as Building Teams have made over the past decade with regard to 3D BIM/VDC coordination on building projects, even the most ardent BIM adopters have neglected what is perhaps the most vital component of any project—operations and maintenance processes and procedures.

Don’t get me wrong: Any building owner or developer would gladly welcome the upfront savings in cost and schedule—along with a higher-quality built environment—that BIM/VDC coordination typically delivers. But the scope of any immediate savings gained by using BIM/VDC pales in comparison to the ongoing efficiencies and cost avoidances that can be achieved by producing a building that is markedly easier and safer to service over its life. And the gains are even greater for owners of legacy buildings—hospitals, schools, government facilities—where 100-year life spans are the norm. Something as minor as a hard-to-access ventilation fan or a poorly specified flooring system can result in decades of added costs for the owner.

Of course, BIM/VDC is not a silver bullet for solving all O&M issues. It’s a communication tool—a database with a nifty graphics interface—that can foster a deeper level of collaboration between members of the Building Team. The real advancement will come in the form of BIM/VDC/IPD project contracts that mandate O&M coordination from the earliest stages of planning.

Progressive Building Teams are beginning to explore the possibilities of O&M BIM/VDC coordination. The team for the Ann & Robert H. Lurie Children’s Hospital of Chicago, for instance, incorporated a number of O&M processes in the design scheme. However, as some of the stakeholders on the project admit, the Building Team only scratched the surface. 

“Looking back, there’s so much more we could have done,” Eric Hoffman, Administrator of Facility Services at Lurie Children’s, told me during a recent tour. He identified several areas where BIM/VDC coordination can result in a meaningful impact to O&M efforts:

  • Lean operations. It’s hard to find a healthcare organization that is not implementing some type of Lean operations program. BIM coordination can be a powerful tool for eliminating waste in process and product. Think of the thousands of health/safety inspections and preventive maintenance exercises that an O&M team must execute in a given year. By reducing the time it takes to complete these tasks (for example, by optimizing the path for inspecting fire/life safety systems), building owners can save hundreds—if not thousands—of man-hours each year.
  • FM system integration. Turning a building over to the owner is a messy process, and one of the more tedious tasks is integrating the building’s as-built data into the facility management system. Are there ways to automate this process using the data in the BIM model? That’s the million-dollar question BIM experts are trying to answer.
  • Space management. Having an accurate as-built model can be helpful not only for reconstruction planning, but also for financial analysis of the space (e.g., amount of revenue being generated in a given space, ROI for renovations, best use of a particular space, etc.).

On future projects, expect your client’s O&M team—from the facilities director down to “Bob the boiler expert”—to have a seat at the design table. It’s just good business sense for any owner, especially those who are in it for the long haul.

David Barista | Building Team Blog
Building Design+Construction
Editorial Director

David Barista is Editorial Director of Building Design+Construction and BDCnetwork.com, properties that combined reach more than 100,000 commercial building professionals, including architects, engineers, contractors, and building owners. David has covered the U.S. construction industry for more than a decade, previously serving as Editor-in-Chief of BD+C, Professional Builder, Custom Builder, and HousingZone.com. He has won numerous editorial awards, including six Jesse H. Neal Awards and multiple honors from the Construction Writers Association and the American Society of Business Publication Editors.

Email: [email protected]

Related Blogs

Benjamin Kasdan, AIA, LEED AP, NCARB, Design Director/Senior Designer with KTGY Architecture + Planning, Irvine, Calif. (Class of 2015 40 Under 40 winner)

October 26, 2015 | Building Team Blog

Are you an AEC superstar? The 2016 "40 Under 40" competition is now open for entries. Here are some helpful...

Competency-based learning: A glimpse into the future of higher education?

Photo: Xbxg32000 via Wikimedia Commons

October 16, 2015 | University Buildings | Building Team Blog

For better or worse, the higher education experience for many young Millennials and Gen Zers will not resem...

From Gehry to the High Line: What makes a project a game-changer?

El Peix sculpture in Barcelona, by Frank Gehry. Photo: Till Niermann via Wikimedia Commons

September 24, 2015 | Architects | Building Team Blog

Each year, there are a handful of projects that significantly advance the AEC industry or a particular buil...

Why AEC firms should be cultivating 'visible experts'

Photo: Cydcor via flickr creative commons

July 07, 2015 | Architects | Building Team Blog

A new study pinpoints the true dollar value of having knowledge leaders and market shapers on your team....

Tactical urbanism: Why bigger isn’t always better in urban revitalization

Each September, as part of Park(ing) Day, citizens, artists, and activists in more than 160 cities collaborate to temporarily transform metered parking spaces into micro parks, gardens, and art exhibits. Photo: my.parkingday.org

May 27, 2015 | Smart and Resilient Cities | Building Team Blog

A budding urban planning movement that is sprouting in cities across the globe proves that low-cost, small-...

Hackathons and RFCs: Why one developer killed the RFP

Image depicts design concepts from the hackathon winner, Pickard Chilton of New Haven, Conn. Photo courtesy Skanska

May 06, 2015 | Building Owner | Building Team Blog

In lieu of an RFP process, Skanska Commercial Development hosted a three-week "hackathon" to find an archit...

Chance encounters and the ‘action’ office: Do collisions spark innovation?

Google is among a handful of tech giants to unveil plans for “action” offices. Rendering courtesy Google, BIG, Thomas Heatherwick

March 29, 2015 | Office Building Design | Building Team Blog

Google, Facebook, Samsung, and Tencent have all unveiled plans for “action” offices designed to get their p...

The High Line effect: Placemaking as an economic development engine

Eight years into the transformation of an elevated section of New York Central Railroad’s West Side Line into a public park, the $273 million project is being hailed as a resounding win for the city. Photo: Beyond My Ken via Wikimedia Commons

March 02, 2015 | Cultural Facilities | Building Team Blog

As big money and eager tourists flock to Chelsea, cities across the globe are starting to take notice. Chic...

Photo: Infrogmation via Wikimedia Commons

The National Institute of Building Sciences estimates the retrofit market for small commercial buildings at $35.6 billion. Photo: Infrogmation via Wikimedia Commons

January 28, 2015 | Office Building Design | Building Team Blog

The real opportunity for shrinking the nation’s energy footprint lies in the mundane world of small commerc...

Add new comment

Your Information
Your Comment

Filtered HTML

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <blockquote> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.
Refresh Type the characters you see in this picture. Type the characters you see in the picture; if you can't read them, submit the form and a new image will be generated. Not case sensitive.  Switch to audio verification.
Overlay Init