Streamline Design-build with BIM

How construction manager Barton Malow utilized BIM and design-build to deliver a quick turnaround for Georgia Tech’s new practice facility.

The John and Mary Brock Football Facility at Georgia Tech in Atlanta was designed and constructed in just 40 weeks using a combination of 3D design and BIM-enabled fabrication techniques.

Last fall, the design-build team for Georgia Tech’s new indoor football practice facility was given just 40 weeks to design and construct the John and Mary Brock Football Facility in Atlanta. The design-build team led by project management firm Barton Malow won the job on October 15, 2010, and the 88,000-sf facility had to be ready by August 1, 2011 in time for the new season of Yellow Jackets’ Football. The $9.75 million new practice facility would also have to be accessible to Georgia Tech officials, boosters, and recruits considering committing to the program the summer before it opened.

“Our sole focus was minimizing risk to deliver the project on schedule,” said Jason McFadden, project manager for Barton Malow. “We weren’t using BIM to show clash detection or make a pretty model.”

At the kickoff meeting last October, Barton Malow and other members of the Building Team—architect Knight Architects of Atlanta, structural engineer Walter P Moore, and owner representatives from Georgia Tech and construction partner May Moeller Purcell—signed memos that committed each discipline to specific completion dates for the various phases of the project. They also set up a workflow where the entire team had to go through the BIM model together on a weekly basis. Most important, the team agreed on a set of tools to model in, collaborate, and deliver closeout documents—a combination of Tekla Engineer and Detailing packages and Tekla for Construction Management to manage and track project status, including submittals, RFIs, and scheduling. Subsequently, TeklaBIMsight for collaboration was added.

At that initial meeting, the Building Team decided that designing a building that was mostly structural steel (rather than a prefabricated metal building) would be the only way to deliver on the tight schedule. Shortly thereafter, Barton Malow published an RFP for steel fabricators challenging them to explain how their system would most benefit the project. The Atlanta office of SteelFab won the project and committed to using Tekla for direct design-to-fabrication as outlined in the RFP.

Walter P Moore started development of the steel model in Tekla Structures in early December. By December 8, 2010, the first model was out to the Steelfab team. The process ran smoothly from that initial model exchange, since both the engineer and fabricator were using native Tekla Structures files. The final, fully detailed design model was approved by Walter P Moore on January 8, 2011. Only 12 weeks separated the start of steel design to the start of steel erection.

Truss sections were determined by what could be shipped and built on the tight site on Georgia Tech’s campus. Each 228-foot truss was divided into six equal sections, which were delivered and bolted together on the ground at the site. The stair tower and camera platform, including rails, were all fully modeled in Tekla.

“The key was continuous back-and-forth information exchange,” McFadden said. Steelfab suggested several fabrication techniques that really allowed us to achieve our schedule goals.

The Tekla Model Reviewer was used early in the steel design, but once TeklaBIMSight was released last February, the Building Team quickly adopted it as its collaboration tool. Ambassador Steel of Waukesha, Wis., was chosen as the concrete rebar fabricator; however, the concrete foundation design was delayed because a geotechnical report was not delivered until December 7. That cut the team’s schedule to three weeks for completion of concrete design and one week to complete the reinforcing bar detail shop drawings.

“We gambled a little bit with publishing approved rebar shop drawings prior to the concrete subcontract award,” McFadden said. “That’s not yet very common in the eastern part of the country but Ambassador Steel really came through.”

Ambassador and Walter P Moore delivered a full rebar model for the foundation by December 30. It took only eight days from the time the concrete subcontract was awarded to get rebar on site. The structural engineer modeled all concrete reinforcement and shared it with Ambassador Steel in Tekla to streamline the rebar detailing process. Ambassador also produced reinforcing bend diagrams directly from the model. The concrete model was integrated with the steel and electrical model by late January. By that time TeklaBIMsight was being used as the collaboration tool and model viewer of choice. Tekla BIMsight was also taken out into the field in tablet computers to match up the model to work in the field. With both rebar and steel design, the model exported directly to the fabricator’s production equipment.

The integrated models were used for scheduling and erection planning sequencing with Tekla’s Construction Management solution, which also provided a tool to evaluate erection plan and sequence.

CREATING A VISUAL REPRESENTATION
To coordinate the schedule, the Barton Malow team used model-based color-coded timelines for scheduling and just-in-time delivery. The Suretrak schedule was integrated with the Tekla task manager to provide a visual representation of all completed and upcoming construction tasks. Custom reports were created using the BIM model to streamline a two-week look-ahead for installation of each component of the building. No paper approval documents were used on the project until file record copies were needed. 

The Tekla Model Reviewer and BIMsight from tablets and computers in the field were used to document and discuss all construction problems in the field. Thanks to the weekly meetings and detailed project memos from design to construction there were no clashes at any point in construction. Last August 1, the new practice facility opened on time and on budget.

“We’re not necessarily trying to have every project engineer or project manager or superintendent having to learn a particular BIM software, but for every project team to be using BIM technology in the way that’s right for their job,” said Phil Kirby, Barton Malow’s senior vice president. “We don’t have a one-size-fits-all solution because every job is different. What we have found is that prefabrication can be applied to most jobs, and choosing the right tool to enable that is what worked at Georgia Tech.” BD+C
--

Contributing Editor Jeff “BIMBoy” Yoders blogs on BIM and related IT topics at www.BDCnetwork.com.

         
 

Comments on: "Streamline Design-build with BIM"

The colorful ribboned flooring at Toronto’s Corus Quay mimics the iconic corkscr
The colorful ribboned flooring at Toronto’s Corus Quay mimics the iconic corkscr
Discussions of commercial flooring tend to focus on the floor covering or finish material. This is hardly surprising, since the covering is the part of the floor that stakeholders see, interact with, and care about most. The...
The use of light load-bearing glass to create transparent stairs, floors, and ot
The use of light load-bearing glass to create transparent stairs, floors, and ot
Glass has taken on new life in recent building years. Long valued for its transparency and lightness, glass is now also being considered for its structural and protective capabilities. Beyond the technique known as...
Building owners must plan ahead for roof replacement to avoid emergency leak rem
Building owners must plan ahead for roof replacement to avoid emergency leak rem
No building owner wants to be caught unprepared by catastrophic roof failure. Emergency roof replacements tend to be more expensive than planned ones, and damage to interiors may mean unrecovered costs and detrimental...
AIA: New Developments in Concrete Construction
AIA: New Developments in Concrete Construction
Concrete has long been a reliable building material for commercial and institutional projects. Yet recent trends, including the growth in hospitality and urban rental project starts, as well as mixed-use towers and transit-...
AIA Rainscreens BD+C DEcember 2011
AIA Rainscreens BD+C DEcember 2011
Until recently, it has been lighting, mechanical, and control system upgrades which have received the most attention in the green building movement. At long last, the industry is now recognizing building enclosures as a long...
Brick and stone masonry have served as reliable and valuable elements of commercial building projects for centuries, gracing urban and rural landscapes since time immemorial. Building Teams have trusted clay brick to bring...
Making the Most of the Reconstruction Boom Reconstruction in its many forms—tenant improvements, retail fitouts, adaptive reuse, historic preservation, gut rehab, and so on—is keeping many design and construction firms...
The topic of water shortages is nothing new, as cities around the globe struggle with drought, water quality, supply constraints, and failing infrastructures. However, the idea of new plumbing codes and design standards...
Guard booths, stations and shelters are defense strategy linchpins, becoming increasingly integral to perimeter defense planning. Before evaluating the efficacy of different guard booth configurations, and before selecting a...
From the company that brought you Construction Computing Magazine’s 2011 BIM Product of the Year ArchiCAD 15, the “Get There Faster with ArchiCAD” whitepaper examines five critical areas to explore before making your final...
Download Complete White Paper Download Introduction Download Chapters 1-4Defining Net-Zero Energy Buildings
Our seventh White Paper on Green Buildings focuses on the role of water in sustainable design and construction. The editors conclude with a set of 21 detailed recommendations for the consideration of the Building Teams, home...