Reconstruction Awards: Reinvesting in a neighborhood’s future

Reconstruction Awards: Reinvesting in a neighborhood’s future

The reconstruction of a near-century-old derelict public works facility in Minneapolis earns LEED Platinum—and the hearts and minds of the neighboring community.


By By Leslie Streicher, Associate Editor | March 1, 2012
The buildings rugged history of service is captured in the reused building mate
The buildings rugged history of service is captured in the reused building materials from the original structure. Bricks, timbe
This article first appeared in the March 2012 issue of BD+C.

Noise, odor, and visual pollution don’t usually come to mind when picturing a pleasant residential neighborhood in the Land of 10,000 Lakes. But for a tight-knit community in Minneapolis that has abutted the city’s Hiawatha Maintenance Facility for nearly a century, pollution in many forms was a daily reality.

The public works site was “a real eyesore,” said Marc Partridge, AIA, CID, LEED AP, a senior associate at local design firm RSP Architects. According to Steve Maurelli, a project manager at RSP, the buildings on the 10-acre site were sorely in need of repair and maintenance. The sense of irony—that a facility devoted to maintenance could itself be so ill-kempt—added to the long-simmering tension between the city and the residents of the adjacent neighborhood, who for decades felt that the city was exploiting them by allowing this blot on their visual landscape.

PROJECT SUMMARY
Hiawatha Maintenance Facility, Minneapolis, Minn.
Building Team

  • Owner/developer: City of Minneapolis
  • Architect: RSP Architects (submitting firm)
  • Structural engineer: Palanisami and Associates
  • MEP engineer: Paulson & Clarke Engineering Inc.
  • General contractor: Knutson Construction

General Information

  • Size: 33,0000-sf office space; 28,000-sf maintenance bay, 20,500-sf storage area
  • Construction cost: $10.8 million
  • Completion date: June 2010
  • Delivery method: Design-bid-build

Built in 1914 as a single brick warehouse and garage, the original building served as a horse infirmary for the local fire department. Population growth spurred the city to erect 18 more facilities, and for more than 90 years the Hiawatha facility has been home to the city’s streets and sewers department.

Tearing down the buildings and starting anew would have been a swift, albeit expensive solution, but the city wanted to preserve the rich history of the facility while also paying respect to the sensitivities of its neighbors.

“When we started this project, one of the goals was to recycle and reuse as much as we could,” said Greg Goeke, director of property services for the city of Minneapolis. The city’s Public Works Department has a “rich tradition” of public service, and repurposing the existing facilities was part of preserving that tradition. The result: about 98% of construction demolition waste from the project was reused.

Click here to view profiles of other reconstruction projects that have been recognized as part of BD+C's 28th Annual Reconstruction Awards.

New construction added space where needed without inflating the mass of the original structures. The original brick building was renovated to complement the surrounding community, while industrial materials were stored on the side of the building facing the highway, out of view of the neighbors.

A new circulating glass curtain wall brought light deep into the facility and made the exteriors more aesthetically pleasing. Recycled materials—metal beams, concrete slabs forming an exterior patio, and wood and bricks salvaged from the original blacksmith shop—lent an elegant but still understated feel to the façade.

According to RSP’s Partridge, an important goal of the renovation was to keep the building functional, not precious. “Public works is raw stuff, and we wanted the building to reflect that,” he said. “In terms of maintainability and the honesty of the materials, everything had a purpose. We wanted to make sure the palette was true to the work being done there.”

Effecting cultural change through design

Before the reconstruction began, city workers were isolated in their respective departments in various parts of the building, each group with its own lunchroom, kitchen, and equipment collection—a layout that lent itself to communication breakdowns and resulting inefficiencies.

2011 RECONSTRUCTION AWARD PRODUCT LIST
Hiawatha Maintenance Facility, Minneapolis, Minn.

Structural Steel: MacSteel
Overhead Door Aluminum: Haas
Structural Deck: Vulcraft-Nucor
Corrugated Metal: CMI Inc.
Lockers: The Locker Guy
Precast Concrete: FabCon
Aluminum Storefront Curtainwall: Old Castle
Ready-mix: Cemstone
Hollow Core Planks: Molin
Remix P/6473 Carpet: Milliken
Windows DH: Pella
Aluminum Storefront Entrances and Doors: Old Castle
Light Gauge Metal Items: Clarkwestern
Louvera: Nystrom
Linoleum: Forbo
Metal Stairs: Lapeyer
Una-Clad: C Firestone
VCT Tile: Daltile
Thermal Batt Insulation: Owens Corning
Insulation: Johns Manville
Gypcrete Green 2000: Maxxom
Alucobond: Alcan
Modular Carpet: Lee's Carpet
Gypsum Board: National Gypsum
Flagpoles: Poletech
Vinyle Tile: Daltile
Gymspum Board: USG
Vinyl Tile: Daltile
Tread Riser: Nora
Rubber Base: Roppe
Rubber Tiles: Nora
Translucent Panel: Kalwall
Misc. Metal Shapes: Nucor
Structural Steel Joists: Vulcraft-Nucor
Overhead Steel Doors: DoorLink

The Building Team—which, in addition to RSP Architects, included Palanisami and Associates (structural engineer), Paulson & Clark Engineering (MEP engineer), and Knutson Construction (GC)—set to work with the municipal administration to find ways to maximize workflow by opening up the floor plan. “We did a lot of programming to see what resources and tasks could be shared between groups, and then designed the space so that the groups were thrown together in shared experiences,” said Partridge. 

Today, the Hiawatha facility takes in 33,000 sf of office space over two floors, a 28,000-sf maintenance bay, and 20,500 sf of storage. It is home to five public works departments whose workforce has experienced something of a collective cultural change as a result of the new space adjacencies. “Making the building more open brought everyone together,” said RSP’s Partridge. Daily task work has improved, response times have quickened, and overall functionality has been streamlined.

“They now realize how much more collaborative their work really is,” he said.

A tough building complex that reflects the hardy work being performed inside—this is what the Building Team envisioned. And it works. “On a day-to-day basis, our employees have an environment that works much better for them without compromising [individual departmental] goals,” said the city’s Greg Goeke—and a great justification for the project to earn Gold honors from BD+C’s Reconstruction Awards jury.

EXCEEDING EXPECTATIONS a commitment to the community

During the planning of the Hiawatha Maintenance Facility, a directive from the city of Minneapolis required the Building Team—RSP Architects, Palanisami and Associates (SE), Paulson & Clark Engineering (MEP), and Knutson Construction (GC)—to achieve LEED Gold certification. But with the high level of reused materials—nearly 98%—the team was able to reach even higher.

“Not only does a public works facility need to protect the city, it also needs to protect the environment,” said Greg Goeke, the city’s director of property services. “We have high recycled content that made achieving environmental goals fairly easy.”

Old timber repurposed for millwork, recycled switchboards and crane rails, and salvaged metal beams supporting the site’s fueling station helped earn the project LEED Platinum for new construction, the city’s first municipal building to earn this rating. An old open-grate bridge that used to cross the Mississippi River was converted into a perimeter fence.

Artifacts of the building’s past are now displayed along the walls, paying homage to the building’s nearly century-long history. Old photographs, remnants of an old asphalt plant, and materials from the infirmary were reincorporated into the building construct.

The project’s high level of sustainability demonstrated the city’s commitment to the local community’s welfare, said Goeke. By the end of the process, residents who had started out mistrusting the project became its strongest advocates. “People now see that something built nearly a century ago still has value today,” he said. +

Related Stories

| Aug 11, 2010

Colonnade fixes setback problem in Brooklyn condo project

The New York firm Scarano Architects was brought in by the developers of Olive Park condominiums in the Williamsburg section of Brooklyn to bring the facility up to code after frame out was completed. The architects designed colonnades along the building's perimeter to create the 15-foot setback required by the New York City Planning Commission.

| Aug 11, 2010

Wisconsin becomes the first state to require BIM on public projects

As of July 1, the Wisconsin Division of State Facilities will require all state projects with a total budget of $5 million or more and all new construction with a budget of $2.5 million or more to have their designs begin with a Building Information Model. The new guidelines and standards require A/E services in a design-bid-build project delivery format to use BIM and 3D software from initial ...

| Aug 11, 2010

Opening night close for Kent State performing arts center

The curtain opens on the Tuscarawas Performing Arts Center at Kent State University in early 2010, giving the New Philadelphia, Ohio, school a 1,100-seat multipurpose theater. The team of Legat & Kingscott of Columbus, Ohio, and Schorr Architects of Dublin, Ohio, designed the 50,000-sf facility with a curving metal and glass façade to create a sense of movement and activity.

| Aug 11, 2010

Residence hall designed specifically for freshman

Hardin Construction Company's Austin, Texas, office is serving as GC for the $50 million freshman housing complex at the University of Houston. Designed by HADP Architecture, Austin, the seven-story, 300,000-sf facility will be located on the university's central campus and have 1,172 beds, residential advisor offices, a social lounge, a computer lab, multipurpose rooms, a fitness center, and a...

| Aug 11, 2010

News Briefs: GBCI begins testing for new LEED professional credentials... Architects rank durability over 'green' in product attributes... ABI falls slightly in April, but shows market improvement

News Briefs: GBCI begins testing for new LEED professional credentials... Architects rank durability over 'green' in product attributes... ABI falls slightly in April, but shows market improvement

| Aug 11, 2010

Luxury Hotel required faceted design

Goettsch Partners, Chicago, designed a new five-star, 214-room hotel for the King Abdullah Financial District (KAFD) in Riyadh, Saudi Arabia. The design-build project, with Saudi Oger Ltd. as contractor and Rayadah Investment Co. as developer, has a three-story podium supporting a 17-story glass tower with a nine-story opening that allows light to penetrate the mass of the building.

| Aug 11, 2010

Three Schools checking into L.A.'s Ambassador Hotel site

Pasadena-based Gonzalez Goodale Architects is designing three new schools for Los Angeles Unified School District's Central Wilshire District. The $400 million campus, located on the site of the former Ambassador Hotel, will house a K-5 elementary school, a middle school, a high school, a shared recreation facility (including soccer field, 25-meter swimming pool, two gymnasiums), and a new publ...

| Aug 11, 2010

New Jersey's high-tech landscaping facility

Designed to enhance the use of science and technology in Bergen County Special Services' landscaping programs, the new single-story facility at the technical school's Paramus campus will have 7,950 sf of classroom space, a 1,000-sf greenhouse (able to replicate different environments, such as rainforest, desert, forest, and tundra), and 5,000 sf of outside landscaping and gardening space.

boombox1 - default
boombox2 -
native1 -

More In Category


AEC Tech

Lack of organizational readiness is biggest hurdle to artificial intelligence adoption

Managers of companies in the industrial sector, including construction, have bought the hype of artificial intelligence (AI) as a transformative technology, but their organizations are not ready to realize its promise, according to research from IFS, a global cloud enterprise software company. An IFS survey of 1,700 senior decision-makers found that 84% of executives anticipate massive organizational benefits from AI. 


Codes and Standards

Updated document details methods of testing fenestration for exterior walls

The Fenestration and Glazing Industry Alliance (FGIA) updated a document serving a recommended practice for determining test methodology for laboratory and field testing of exterior wall systems. The document pertains to products covered by an AAMA standard such as curtain walls, storefronts, window walls, and sloped glazing. AAMA 501-24, Methods of Test for Exterior Walls was last updated in 2015. 


MFPRO+ News

World’s largest 3D printer could create entire neighborhoods

The University of Maine recently unveiled the world’s largest 3D printer said to be able to create entire neighborhoods. The machine is four times larger than a preceding model that was first tested in 2019. The older model was used to create a 600 sf single-family home made of recyclable wood fiber and bio-resin materials.

halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021