More than half (53%) of multifamily developer respondents reported construction delays in the jurisdictions where they operate, according to the third edition of the National Multifamily Housing Council (NMHC) COVID-19 Construction Survey. Of this group, 85% reported delays in permitting due to COVID-19, up from 77% in round two (conducted April 9-14) and 76% in the initial survey (conducted March 27-April 1).
Getting permits is a major problem for multifamily developers and construction firms, says the NMHC in its latest survey.
Survey respondents reporting construction delays also indicated a significant pause in starts, with 78% reporting delays, up 8 percentage points from the end of last month, and 19 percentage points from the first round.
More than three-quarters of multifamily developers said continue to face delays in starts, says the latest NMHC survey.
The NMHC Construction Survey is intended to gauge the magnitude of the disruption caused by the COVID-19 outbreak on multifamily construction. Additional findings include:
• 53% of developers reported a delay in construction. Of those developers, the percentage experiencing a delay in construction because of construction moratorium dropped from 62% in round one to 37% in round three, indicating that construction activity is resuming as states relax pandemic-related restrictions.
• Only 29% of respondents reported being impacted by a lack of materials, but the percentage of respondents experiencing price increases in materials jumped to 17%, from 5% in round one and 4% in round two. Despite this jump, 78% still report no price impact, and 24% of those implementing new strategies report they are sourcing alternative building materials, up 8 percentage points from the first survey.
Labor availability seems to be less of a problem for multifamily construction firms, says the NMHC survey.
• Labor availability has also improved over the course of the three surveys. Seventy percent of respondents said they were not impacted by labor shortages, up from 54% in round one and 57% in round two. This may be due in part to the fact that 24% of those implementing new strategies said they were offering workforce incentives or other benefits, up from 16% in round two.
Firms continue to innovate in the face of challenges posed by the outbreak. Fifty-nine percent of respondents indicated they have implemented new strategies to deal with the hurdles established by the virus’s continued presence. This is down from 75% in the last round and 73% in the first round. Many firms said they have implemented more than one strategy.
View the full survey results here and a comprehensive overview of the results here.
Additional resources, data, and materials from NMHC can be found here.
Related Stories
Coronavirus | Apr 1, 2020
Green cleaning and the coronavirus
If your cleaning teams use bleach to disinfect buildings from Coronavirus, will you put your LEED certification at risk?
Coronavirus | Mar 31, 2020
As cities scramble for hospital beds to treat COVID-19 patients, Leo A Daly offers a hotel-to-hospital solution
The firm has devised three conversion models, for different levels of healthcare required.
Coronavirus | Mar 30, 2020
Your turn: Has COVID-19 spelled the death knell for open-plan offices?
COVID-19 has designers worrying if open-plan offices are safe for workers.
Coronavirus | Mar 30, 2020
Learning from covid-19: Campuses are poised to help students be happier
Overcoming isolation isn’t just about the technological face to face, it is about finding meaningful connection and “togetherness”.
Coronavirus | Mar 30, 2020
COVID-19 innovation: Setting parameters for hotel-to-hospital conversions
tvsdesign breaks down different room types and how they might help free up hospital beds for coronavirus patients.
Coronavirus | Mar 30, 2020
New Department of Homeland Security guidance clarifies construction's role in supporting essential critical infrastructure
Construction officials say new federal guidance should signal to state and local officials the need to allow construction activity to continue, or resume, during coronavirus-related work stoppages.
Coronavirus | Mar 27, 2020
Sharp jump in owners cancelling or delaying construction projects across the country, new survey finds
After 42 states added jobs in February, coronavirus is taking a swift and severe toll on the industry, prompting association officials to call for additional measures to help workers and firms recover.
Coronavirus | Mar 27, 2020
Covid-19 stalls demand for design services
Two thirds of architecture firms report slowing or stoppage of projects due to COVID-19.
Coronavirus | Mar 26, 2020
It’s not if, but when: Designing healthcare spaces that support pandemic response
What can we learn from Singapore’s response to COVID-19? How does it impact the next generation of hospitals?
Coronavirus | Mar 26, 2020
AIA praises Congress for advancing desperately needed COVID-19 relief
Approval for the latest relief legislation advances a number of AIA-supported measures to help meet the needs of firms and members.