flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Modular fire station allows for possible future reconfigurations

Modular Building

Modular fire station allows for possible future reconfigurations

Rancho Mission Viejo’s Fire Station 67 deployed offsite fabrication and rapid onsite assembly, resulting in a construction timeline of six months.


By Novid Parsi, Contributing Editor | February 6, 2024
Modular fire station, Rancho Mission Viejo’s Fire Station 67
Fire Station 67, Rancho Mission Viejo, Calif. Photo © Nic Lehoux, courtesy Wittman Estes

In Southern California’s Rancho Mission Viejo (RMV), Fire Station 67 has been designed and constructed as a prefab, modular build—enabling faster completion and future reconfiguration.

Designed by Seattle-based Wittman Estes, the 4,667-sf station was prefabricated offsite as 10 modules that were then assembled onsite. The offsite fabrication and rapid assembly led to a streamlined design, documentation, and permitting process. This approach allowed for parallel site development work in California and factory construction in Nevada, resulting in a construction timeline of six months. 

Fire Station 67: Modular System

The modular system also allows for relocation and reconfiguration. The sturdy, durable steel modules can be easily transported and rearranged for possible future uses, such as an environmental learning center for RMV.

Modular fire station, Rancho Mission Viejo’s Fire Station 67
Fire Station 67. Photo © Nic Lehoux, courtesy Wittman Estes

Fire Station 67 includes a vehicle bay for two fire trucks, six sleeping rooms, a day room, kitchen/dining room, dispatch/workspace, and a captain’s office. The 12-foot modules were assembled around a shaded, semi-protected central courtyard.

Construction Strategy

The building configuration enables the firefighters to serve the public quickly while also feeling calm and privacy. The north-facing public entry, captain’s office, and dispatch room face the neighborhood. The more active areas, including break room, kitchen, and fitness rooms, face east toward the firetrucks. And the sleeping rooms and bathrooms are located in a quiet zone in the west. The firetruck bay is painted bright red, while the interior spaces have a neutral, tranquil palette.

Modular construction plan of fire department

In response to climate change and the rising risk of wildfires, the prefab structure is clad in fireproof, corrugated steel siding. To improve indoor air quality, Wittman Estes designed an open-air apparatus bay to bring in fresh outside air and eliminate the need for large exhaust machines.

On the Building Team:
Clients: Orange County Fire Authority and Rancho Mission Viejo
Architect: Wittman Estes
Interior designer: Birsel+Seck
Structural engineer: DCI Engineers
Landscape architect: Land Concern
Civil engineer: Fuscoe Engineering
GC: Xtreme Cubes 

Modular fire station, Rancho Mission Viejo’s Fire Station 67
Photo © Nic Lehoux, courtesy Wittman Estes
Rancho Mission Viejo’s Fire Station 67
Photo © Nic Lehoux, courtesy Wittman Estes

Related Stories

Modular Building | Jul 22, 2016

PNC Bank’s 'Tiny Branch' opens on West Virginia University campus

The new branch doesn’t need much space for its ATM and new accounts and personal loans services.

Transit Facilities | Jun 12, 2016

Philippines’ oldest city getting its first public bus system

New York-based CAZA designed the modular bus stops with the city’s extreme weather conditions in mind.

Modular Building | May 17, 2016

Oklahoma’s first modular hotel will begin construction next month

Guerdon Modular Buildings will produce 81 modules for this project. 

Modular Building | Feb 26, 2016

CHPS releases new program, first model for prefab modular classrooms

Provides standards for indoor air quality, energy efficiency, materials, and waste management.

Game Changers | Feb 5, 2016

Asia’s modular miracle

A prefab construction company in China built a 57-story tower in 19 days. Here’s how they did it.  

Game Changers | Feb 4, 2016

GAME CHANGERS: 6 projects that rewrite the rules of commercial design and construction

BD+C’s inaugural Game Changers report highlights today’s pacesetting projects, from a prefab high-rise in China to a breakthrough research lab in the Midwest.

Modular Building | Feb 1, 2016

Hotel developers turn to modular construction to meet demand

A $90 million rebuilding project in Yellowstone National Park exemplifies this trend.

| Jan 14, 2016

How to succeed with EIFS: exterior insulation and finish systems

This AIA CES Discovery course discusses the six elements of an EIFS wall assembly; common EIFS failures and how to prevent them; and EIFS and sustainability.

Modular Building | Dec 13, 2015

Undaunted, Forest City pushes ahead on modular construction

The president of its FC Modular division says new projects are under consideration, even as competitors falter or fall by the wayside. 

Greenbuild Report | Dec 1, 2015

Data centers turn to alternative power sources, new heat controls and UPS systems

Data centers account for 2% of the nation’s electricity consumption and about 30% of the power used annually by the economy’s information and communications technology sector, according to the National Renewable Energy Laboratory.

boombox1 - default
boombox2 -
native1 -

More In Category



Modular Building

Building with shipping containers not as eco-friendly as it seems

With millions of shipping containers lying empty at ports around the world, it may seem like repurposing them to construct buildings would be a clear environmental winner. The reality of building with shipping containers is complicated, though, and in many cases isn’t a net-positive for the environment, critics charge, according to a report by NPR's Chloe Veltman.


halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021