flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Johns Hopkins Hospital's New Clinical Building

Johns Hopkins Hospital's New Clinical Building

Johns Hopkins Hospital's new clinical building will be the centerpiece of its $1.2-billion redevelopment plan.


By By Christina Fisher | August 11, 2010

Clark/Banks, A Joint Venture (CBJV), which is composed of Clark Construction Group, LLC, of Bethesda, Maryland, and Banks Contracting Company, Inc., of Baltimore, is in Phase 1 of a $573-million project to construct Johns Hopkins Hospital's (JHH) new clinical building in Baltimore. The design team is led by Perkins+Will of Los Angeles. Bard, Rao + Athanas Consulting Engineers, LLC, of Boston is the mechanical and electrical consultant, and Thornton Tomasetti of Washington, D.C., is the structural consultant. The 1.5-million-square-foot medical building will feature two connected towers — one for adult cardiovascular and critical care and the other for children's care. It is currently the largest health care project under construction in the nation.

The project is the new main entrance and centerpiece of a $1.2-billion JHH redevelopment plan to increase research and clinical space and replace outdated hospital buildings with advanced facilities. There is a two-level below-grade basement of cast-in-place concrete, and the above-ground structure is structural steel. The skin will be curtain wall and precast with a cast-in-place brick veneer.

When CBJV arrived on-site in November 2006, other buildings on-site had been partially demolished by other contractors. Berg Demolition continued with the demolition of the Jefferson Building, the only remaining building on the project site. Complicating this process, however, was the fact that the Jefferson Building was adjacent to the Nelson/Harvey Building, which would remain in place.

"We actually had to physically separate the Jefferson Building from the existing Nelson/Harvey Building on the north side," says John Barotti, senior vice president with Clark Construction. "We cut the slab and disconnected the structure so the vibration would not (affect) the other building. We had to use selective demolition and soft strip operations."

After removing the ceilings, duct work, conduit, and other interior items, Berg Demolition used remote-controlled Brokk hydraulic hammers and Bobcat skid-steer loaders to selectively demolish the concrete shell and remove the debris. Barotti explains that there was extensive coordination with the hospital during the demolition process due to the close proximity to patients and hospital operations.

"For awhile we were only working from 6 a.m. to 8 a.m.," says Barotti. "We were shut down until 4 p.m., and then we could work at night. In some cases we couldn't (work) at all until later in the evening or on weekends. However, we were able to achieve significant noise and vibration reduction by severing building connection points, adding noise abatement materials and modifying equipment."

CBJV is nearing completion of the excavation process of Phase 1. There have been two bulk excavations of the job, with the lowest building elevation reaching 28 feet below grade. At this level, CBJV had to connect to a tow line tunnel, which serves a major role in the new hospital's operations.

"An interesting fact about this hospital is that there is no loading dock and there is no commercial kitchen or cafeteria," says Barotti. "All supplies, even food, come from across the street and through this underground tunnel below the parking garage and Orleans Street."

This level of the project also includes excavation for all of the storage areas, the elevator pits and the central sterilization area, which is a recent addition to the hospital's plans. These types of design changes and enhancements are something the project team has come to expect on hospital projects.

"A hospital is a complex facility, so it's been under design for a long time. It's an evolution and it's continuously changing," says Barotti. There are two primary reasons for this. Because the hospital wants to have the latest technology when it opens its doors in 2011, high-tech equipment will not be ordered until the last minute. For this reason, 25 areas in the hospital towers will only be shelled during construction, and they won't be completed until the specific equipment has been ordered.

In anticipation of this, the MEP design has to be flexible. "What they typically do is over-design the area," explains Barotti. "They'll give it a little extra power, a little extra air conditioning, extra floor loading, and extra ceiling loading in case we have to hang anything off the ceiling. It's kind of like a belt and suspenders approach." Therefore, when the final specs do arrive these spaces can be customized for each piece of state-of-the-art equipment.

Furthermore, Johns Hopkins Hospital has continued its fundraising efforts since the project has been in the design phase. Therefore, as more money becomes available, enhancements can be added to the project.

"Originally the hospital was going to rely on an adjacent building to do all of the sterilization for it. They came to realize that it was an operational need to have it in the hospital building itself, and they realized they had the budget to do it," says Barotti. "So, we were at the point where we were excavating walls for this area where (central sterilization) would be going in. Now we're out there making the changes to work the new plan."

The floor plan of the lower level is very "process oriented and functional," but much smaller than the actual floor plan of the towers, explains Barotti. "When you go down to the B2 level, which is all the way down, you're at deep elevation 72. Because the floor plan gets larger as you go up, there are some floor elevations that don't start until elevation 99. That's slab-on-grade elevation."

To support the foundations, there are a total of 275 caissons ranging in size from 3 feet to 11 feet. The caissons at elevation 72, the deepest elevation, go down over 30 feet, and the caissons for elevation 99, which are at the slab-on-grade level, go down approximately 40 feet. Because this is a caisson pile and steel job, the caps are not significantly larger than the caisson foundations. Instead, the new facility is a "brace-framed" job.

"There's heavy structural steel that gets encapsulated in concrete at the lower levels," says Barotti. "We'll come in around the elevators basically, and we'll set some large steel. Then we'll come in and cast them in place, too. They are the brace frames for the whole project. They keep the towers stable."

Because the footprint for the underground floors is smaller, these perimeter walls are on the interior. CBJV has been able to open cut and lay the dirt back for many of these walls. Once they are constructed, the exterior will be backfilled. The perimeter walls for the upper levels are just minor foundation walls to support one level of precast or window system, and then the next level continues with structural steel.

Phase 1 also includes the utility work. The project ties into Baltimore city power, sewer, water, and storm systems. The hospital does have its own central plant, so the project will link to the hospital's plant systems.

When the excavation and foundation work are complete, the project will move into Phase 2, which is the vertical construction. Although designed as one building with an expansion joint between them, the towers are being constructed as two different structures. CBJV had access to the children's tower site first, so vertical construction will be about three months ahead of the adult tower. The new towers will tie into existing buildings along certain corridors, and two bridges will connect the towers to existing parking garages.

When it is completely finished, the new clinical facility will be 15 stories high, with 12 active hospital floors. At an anticipated final cost of over $600 million, the entire 1.5-million-square-foot project is scheduled for substantial completion by December 23, 2010.

 

MEP coordination on a hospital project is more critical and complex than any other project. CBJV is using Building Information Modeling (BIM) to coordinate the different systems and ensure they don't collide. In order to accomplish this, CBJV takes the two-dimensional project drawings and converts them to a 3-D model. BIM combines the structure's plans with the utility drawings. Before the MEP systems are built in the field, they are virtually built to check for collisions between systems — down to a quarter-inch.

"It takes the guess work out," says John Barotti, Clark Construction senior vice president. "It doesn't eliminate all errors, but you take them down from a 6-percent probability to a 0.4-percent probability. It saves a lot of field re-fabrication time.

"There are always changes in hospitals. You expect it. You know it's going to happen. To have BIM available to us as a tool when these changes occur (allows us) to put the change right into the program. We can do artificial mockups to see how things will fit together."

Alex Zolotov, Clark Construction's on-site BIM coordinator, adds that CBJV is also using BIM for schedule coordination. "There are separate programs for scheduling (Primavera P5) and 3-D modeling (AutoCAD by Autodesk). Then there's another program to merge them (NavisWorks by Autodesk). Whenever there's a change to the schedule, you can just hit the synchronize button and it will re-link. You don't have to modify."

Barotti states that Clark Construction is a firm believer in BIM and will continue using it on the project. "When 3-D scenarios are done and problems are corrected, then the 2-D drawings can be changed accordingly and everyone knows that they have a coordinated set of documents. We hope that in 10 years everybody is doing 3-D modeling and we can synch them all with the schedule. Our coordination capabilities will be a lot better than they are today."

Just how complicated is the MEP coordination on the project? Poole and Kent Corporation is responsible for the mechanical systems — plumbing, HVAC, sheet metal, MEP insulation, controls, and test and balance — on the project. Just the installation of the piping, which is only a portion of their entire scope of work, includes the following:
25,000-plus linear feet of steam and condensate piping 22,000-plus linear feet of chilled water piping 155,000-plus linear feet of hot water piping 234,000-plus linear feet of domestic water piping 222,000-plus linear feet of lab/medical gas piping 176,000-plus linear feet of waste and vent piping
Add to that 7,284,000 linear feet or 1,379 miles of copper wire being installed by M.C. Dean, which is enough to stretch between New York City and Miami, Florida, and 1,703,364 linear feet or 322 miles of conduit, which would take you round trip from Baltimore to Ocean City.
boombox1 - default
boombox2 -
native1 -
halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021