It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

Hotel Facilities

It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

PPVC techniques allowed the project to save time and manpower.


By David Malone, Associate Editor | July 5, 2017

Photo: Patrick Bingham-Hall

The Singapore Changi Airport is, according to the most recent numbers from the Airports Council International, the 17th busiest airport in the world by passenger traffic. With so many people passing through on a daily basis, it was important for the new addition to the Crowne Plaza Changi Airport hotel to be built in as little time as possible.

The new building was Singapore’s first private sector commercial project to use pre-fabricated, pre-finished volumetric construction (PPVC), which led to the addition being built in just 26 days. WOHA designed the original 320-room hotel as well as the 243-room, 103,495-sf addition.

 

Photo: Patrick Bingham-Hall.

 

The use of the PPVC method slashed manpower requirements on site by as much as 45%, reduced overall construction time by 17%, and accomplished both of these with about 40% in manpower savings.

 

Photo: Patrick Bingham-Hall.

 

“The Crowne Plaza Changi Airport hotel extension (CPEX) demonstrates that it is possible to significantly reduce the number of workers required, shorten construction time, improve building quality and even overcome site constraints by changing the way we build,” says Singapore’s Building and Construction Authority CEO John Keung in a release.

 

Photo: Patrick Bingham-Hall.

Related Stories

Architects | Sep 13, 2017

Leo A Daly hires hospitality-design veteran to lead its Dallas office

Ken Martin views this sector as an incubator of innovation.

Hotel Facilities | Sep 6, 2017

Marriott has the largest construction pipeline of any franchise company in the U.S.

Marriott has the most rooms currently under construction with 482 Projects/67,434 Rooms.

Hotel Facilities | Aug 25, 2017

Hotels savor demand in northern California's wine country

New entrant, Hotel Trio, will play up location and affordability.

Hotel Facilities | Aug 17, 2017

Seattle hotel will be the largest in the Pacific Northwest

The 45-story, 500-foot-tall tower is composed of two primary volumes.

Hotel Facilities | Aug 14, 2017

New W hotel takes a leap in its interior design

The brand’s focus will incorporate aspects of its properties’ surrounding communities.

Mixed-Use | Aug 9, 2017

Mixed-use development will act as a gateway to Orange County’s ‘Little Saigon’

The development will include apartments, ground-floor retail, and a five-story hotel.

Lighting | Aug 2, 2017

Dynamic white lighting mimics daylighting

By varying an LED luminaire’s color temperature, it is possible to mimic daylighting, to some extent, and the natural circadian rhythms that accompany it, writes DLR Group’s Sean Avery. 

Hotel Facilities | Jul 28, 2017

Achieve hospitality architecture that impresses – Multigenerational appeal, local connections

Did guests get the experience that they paid for? This question has long haunted hotel operators.

Hotel Facilities | Jul 27, 2017

Hilton’s ‘Five Feet to Fitness’ suites turn hotel rooms into gyms

Over 11 different fitness equipment and accessory options are available in each suite.

Hotel Facilities | Jul 17, 2017

This space hotel design from MIT won NASA’s graduate design competition

The project team consisted of MIT graduate students across five departments.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021