Integrated Design Group completes UCSB data center

Integrated Design Group completes UCSB data center

Firm uses European standard of power at USCB North Hall Research Data Center.


By Posted by Tim Gregorski, Senior Editor | July 9, 2012
By utilizing the 415/240 V AC power distribution system, which is standard in mo
By utilizing the 415/240 V AC power distribution system, which is standard in most European and Asian countries, ID was able to

Integrated Design Group(ID) completed construction at the North Hall Data Center located at the University of California at Santa Barbara (UCSB). Integral to the university’s computing operations, the data center, which contained enterprise computing capabilities and all campus network connections, was fully operational during the project, allowing the university community to access the servers normally and not cause disruption to the institution’s computing.

A major client goal was for the new research data center to become flexible and scalable in order to provide the opportunity for future expansion as needed. Although the existing facility posed significant limitations on interior clearances, restricting both the depth of the raised floor and the overall height within the computer room, ID was able to nearly double the raised floor space by using innovative cooling technology. With updated mechanical and electrical systems, the research data center is now able to support the latest in high performance computing.

By utilizing the 415/240 V AC power distribution system, which is standard in most European and Asian countries, ID was able to implement efficiency gains within  the data center, and provide monetary savings for the university. This application offers a significant amount of energy improvement over North America’s standard of 208/120 V. Delivering  power to IT loads at 415/240 V instead of 208/120 V eliminates power distribution unit (PDU) transformers. This elimination not only offers energy efficiency gain, but also reduces copper costs and floor loading while freeing up additional space within the data center. +

Related Stories

Industrial Facilities | Apr 9, 2024

Confessions of a cold storage architect

Designing energy-efficient cold storage facilities that keep food safe and look beautiful takes special knowledge.

Cultural Facilities | Apr 8, 2024

Multipurpose sports facility will be first completed building at Obama Presidential Center

When it opens in late 2025, the Home Court will be the first completed space on the Obama Presidential Center campus in Chicago. Located on the southwest corner of the 19.3-acre Obama Presidential Center in Jackson Park, the Home Court will be the largest gathering space on the campus. Renderings recently have been released of the 45,000-sf multipurpose sports facility and events space designed by Moody Nolan.

Green | Apr 8, 2024

LEED v5 released for public comment

The U.S. Green Building Council (USGBC) has opened the first public comment period for the first draft of LEED v5. The new version of the LEED green building rating system will drive deep decarbonization, quality of life improvements, and ecological conservation and restoration, USGBC says. 

Codes and Standards | Apr 8, 2024

Boston’s plans to hold back rising seawater stall amid real estate slowdown

Boston has placed significant aspects of its plan to protect the city from rising sea levels on the actions of private developers. Amid a post-Covid commercial development slump, though, efforts to build protective infrastructure have stalled.

Sustainability | Apr 8, 2024

3 sustainable design decisions to make early

In her experience as an architect, Megan Valentine AIA, LEED AP, NCARB, WELL AP, Fitwel, Director of Sustainability, KTGY has found three impactful sustainable design decisions: site selection, massing and orientation, and proper window-to-wall ratios.

Brick and Masonry | Apr 4, 2024

Best in brick buildings: 9 projects take top honors in the Brick in Architecture Awards

The Ace Hotel Toronto, designed by Shim-Sutcliffe Architects, and the TCU Music Center by Bora Architecture & Interiors are among nine "Best in Class" winners and 44 overall winners in the Brick Industry Association's 2023 Brick in Architecture Awards.

Retail Centers | Apr 4, 2024

Retail design trends: Consumers are looking for wellness in where they shop

Consumers are making lifestyle choices with wellness in mind, which ignites in them a feeling of purpose and a sense of motivation. That’s the conclusion that the architecture and design firm MG2 draws from a survey of 1,182 U.S. adult consumers the firm conducted last December about retail design and what consumers want in healthier shopping experiences.

Healthcare Facilities | Apr 3, 2024

Foster + Partners, CannonDesign unveil design for Mayo Clinic campus expansion

A redesign of the Mayo Clinic’s downtown campus in Rochester, Minn., centers around two new clinical high-rise buildings. The two nine-story structures will reach a height of 221 feet, with the potential to expand to 420 feet.

Sports and Recreational Facilities | Apr 2, 2024

How university rec centers are evolving to support wellbeing

In a LinkedIn Live, Recreation & Wellbeing’s Sadat Khan and Abby Diehl joined HOK architect Emily Ostertag to discuss the growing trend to design and program rec centers to support mental wellbeing and holistic health.

Architects | Apr 2, 2024

AE Works announces strategic acquisition of WTW Architects

AE Works, an award-winning building design and consulting firm is excited to announce that WTW Architects, a national leader in higher education design, has joined the firm.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021