Google to convert an Alabama coal-burning plant to a data center running on clean energy

Industrial Facilities

Google to convert an Alabama coal-burning plant to a data center running on clean energy

This would be the tech giant’s seventh data center in the U.S.


By John Caulfield, Senior Editor | June 26, 2015
Google to convert an Alabama coal-burning plant to a data center running on clean energy

This October, Tennessee Valley Authority will close its outdated Widows Creek coal plant in Stevenson, Ala., which had been providing energy to the region since the 1960s. Photo: TVA Web Team via Wikimedia Commons

The coal-producing industry has taken its lumps of late, a victim of natural gas fracking and restrictions on air pollution. This October, Tennessee Valley Authority (TVA) will finally close its outdated Widows Creek coal plant in Stevenson, Ala., which had been providing energy to the region since the 1960s, rather than knock heads with the EPA over tighter financial and environmental regulations.

That plant, located on 350 acres about 60 miles northeast of Huntsville, will be retrofitted into a data center that runs on renewable energy. Google has agreed to build this $600 million project, which would be its 14th data center globally, but the first it has committed to in eight years, according to the San Antonio Express-News.

Google’s data centers in Iowa and Oklahoma run on wind power, and the Alabama facility will operate solely on renewable energy, possibly a combination of wind and solar.

The company states on its website that it has recently expanded its data centers in the states of Georgia and Iowa, as well as in Singapore and Belgium. Construction on the Alabama plant is scheduled to begin early next year and to bring between 75 and 100 jobs to Jackson County.

Google’s data centers in Iowa and Oklahoma run on wind power, and the Alabama facility will operate solely on renewable energy, possibly a combination of wind and solar, the company states. The data center will be hooked up to TVA’s electrical transmission lines, and Google will work with the Authority to run renewable energy through the latter’s electrical grid.

Alabama Gov. Robert Bentley called this project “the start of a long-lasting, productive relationship with Google.” He credited the TVA’s chairman Joe Ritch for securing the project. Google will benefit from two state tax-abatement packages that stem from the passage, three years ago, of the Alabama Data Processing Center Incentive Enhancement Act, according to AL.com.

Gary Demasi, Google’s director of Global Infrastructure, said in a prepared statement that Google sees “a lot of potential in redeveloping large industrial sites like former coal plants, and we’re excited to bring a data center to Alabama.” Urs Hölzle, Google’s SVP for technical infrastructure, told the New York Times that the company would be evaluating “plausible projects” over the next 12 months.

The data center is expected to incorporate Google’s latest technology efficiencies, which allow it to get 3.5 times the computing power out of the same amount of energy, compared to five years ago.

Related Stories

Resiliency | Apr 22, 2024

Controversy erupts in Florida over how homes are being rebuilt after Hurricane Ian

The Federal Emergency Management Agency recently sent a letter to officials in Lee County, Florida alleging that hundreds of homes were rebuilt in violation of the agency’s rules following Hurricane Ian. The letter provoked a sharp backlash as homeowners struggle to rebuild following the devastating 2022 storm that destroyed a large swath of the county.

Mass Timber | Apr 22, 2024

British Columbia changing building code to allow mass timber structures of up to 18 stories

The Canadian Province of British Columbia is updating its building code to expand the use of mass timber in building construction. The code will allow for encapsulated mass-timber construction (EMTC) buildings as tall as 18 stories for residential and office buildings, an increase from the previous 12-story limit. 

Standards | Apr 22, 2024

Design guide offers details on rain loads and ponding on roofs

The American Institute of Steel Construction and the Steel Joist Institute recently released a comprehensive roof design guide addressing rain loads and ponding. Design Guide 40, Rain Loads and Ponding provides guidance for designing roof systems to avoid or resist water accumulation and any resulting instability.

Building Materials | Apr 22, 2024

Tacoma, Wash., investigating policy to reuse and recycle building materials

Tacoma, Wash., recently initiated a study to find ways to increase building material reuse through deconstruction and salvage. The city council unanimously voted to direct the city manager to investigate deconstruction options and estimate costs. 

Student Housing | Apr 19, 2024

$115 million Cal State Long Beach student housing project will add 424 beds

A new $115 million project recently broke ground at California State University, Long Beach (CSULB) that will add housing for 424 students at below-market rates. The 108,000 sf La Playa Residence Hall, funded by the State of California’s Higher Education Student Housing Grant Program, will consist of three five-story structures connected by bridges.

MFPRO+ News | Apr 18, 2024

Marquette Companies forms alliance with Orion Residential Advisors

Marquette Companies, a national leader in multifamily development, investment, and management, announces its strategic alliance with Deerfield, Ill.-based Orion Residential Advisors, an integrated multifamily investment and operating firm active in multiple markets nationwide.

Construction Costs | Apr 18, 2024

New download: BD+C's April 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.

Construction Costs | Apr 16, 2024

How the new prevailing wage calculation will impact construction labor costs

Looking ahead to 2024 and beyond, two pivotal changes in federal construction labor dynamics are likely to exacerbate increasing construction labor costs, according to Gordian's Samuel Giffin.

Healthcare Facilities | Apr 16, 2024

Mexico’s ‘premier private academic health center’ under design

The design and construction contract for what is envisioned to be “the premier private academic health center in Mexico and Latin America” was recently awarded to The Beck Group. The TecSalud Health Sciences Campus will be located at Tec De Monterrey’s flagship healthcare facility, Zambrano Hellion Hospital, in Monterrey, Mexico.

Market Data | Apr 16, 2024

The average U.S. contractor has 8.2 months worth of construction work in the pipeline, as of March 2024

Associated Builders and Contractors reported today that its Construction Backlog Indicator increased to 8.2 months in March from 8.1 months in February, according to an ABC member survey conducted March 20 to April 3. The reading is down 0.5 months from March 2023.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021