Gold Award: VA San Diego Healthcare System Building 1 Seismic Correction San Diego, Calif.

Thanks to a $55 million upgrade, the Veterans Affairs San Diego Healthcare System Building 1 can now withstand a 7.2 magnitude earthquake. The 920-day project concentrated on installing new foundations and exterior stair towers with integrated braced framing. Additional work focused on utility upgrades, core strengthening of the penthouse structure to the surrounding building, and beefing up particularly vulnerable areas, such as interior bridges, roof corners, and balconies.
     
Three decades after its original construction in the early 1970s, the Veterans Affairs San Diego Healthcare System Building 1 fell far short of current seismic codes. This not only put the building and its occupants—patients, doctors, nurses, visitors, and administrative staff—at risk in the event of a major earthquake, it violated a California state mandate requiring all hospitals to either retrofit or rebuild. In 2005, VA administrators opted to retrofit the six-story, 855,000-sf hospital—and remain open throughout the course of construction.

 
The building’s eight exterior stair towers were completely demolished, but in phases, to keep the hospital operational. Replacement stair towers were built atop new, deep foundations and connected to one another by a braced-frame structural steel system.
         
The Building Team, including general contractor Clark Construction Group, architect Leo A Daly, and structural engineer Nabih Youssef & Associates, worked out a five-phase plan for the $55 million project that would keep the hospital functioning throughout the scheduled 920-day project. Upon completion, the facility would be able to withstand a 7.2 magnitude earthquake.

Most of the work concentrated on installing new foundations and exterior stair towers with integrated braced framing. Additional work focused on utility upgrades, core strengthening of the penthouse structure to the surrounding building, and beefing up particularly vulnerable areas, such as interior bridges, roof corners, and balconies.

The building’s eight exterior stair towers were completely demolished, but in phases, to keep the hospital operational. Replacement stair towers were built atop new, deep foundations and connected to one another by a braced-frame structural steel system. The brace frames provide the hospital’s critical seismic strengthening through continuous slab edge connections. Value engineering turned the brace frame structures into architectural elements: metal cladding was originally going to be the finish material, but after that idea was abandoned, the criss-cross steel was left exposed and painted white.

It is the staircase structures as seismic solutions that really caught the judges’ attention. Summing up their thoughts is Lucien Lagrange, AIA, principal at Chicago-based Lucien Lagrange Architects, who characterized the engineering as “quite amazing.” 

Along the way, more than 1,100 tons of asbestos were removed. MRI facilities had to be relocated during construction so cranes and steel didn’t interfere with the machines’ calibrations and accuracy. Undocumented structural steel was discovered embedded in concrete, while an undocumented sewer lateral was discovered after it was hit and filled with slurry. 

Collaboration between the Building Team and the hospital staff allowed the challenging project to be finished months ahead of schedule and with minimum disruption to the hospital.











       
Project Summary

VA San Diego Healthcare System Building 1 Seismic Correction
La Jolla, Calif.

Building Team
Submitting firm:
Clark Construction Group (GC)
Architect: Leo A Daly
Structural engineer: Nabih Youssef & Associates
M/E engineer: S&K Engineers
Geotechnical consultant: Ninyo & Moore

General Information

Area: 855,000 sf
Construction cost: $55 million
Construction time: November 2005 to April 2008










         
Building owners must plan ahead for roof replacement to avoid emergency leak rem
Building owners must plan ahead for roof replacement to avoid emergency leak rem
No building owner wants to be caught unprepared by catastrophic roof failure. Emergency roof replacements tend to be more expensive than planned ones, and damage to interiors may mean unrecovered costs and detrimental...
AIA: New Developments in Concrete Construction
AIA: New Developments in Concrete Construction
Concrete has long been a reliable building material for commercial and institutional projects. Yet recent trends, including the growth in hospitality and urban rental project starts, as well as mixed-use towers and transit-...
AIA Rainscreens BD+C DEcember 2011
AIA Rainscreens BD+C DEcember 2011
Until recently, it has been lighting, mechanical, and control system upgrades which have received the most attention in the green building movement. At long last, the industry is now recognizing building enclosures as a long...
Brick and stone masonry have served as reliable and valuable elements of commercial building projects for centuries, gracing urban and rural landscapes since time immemorial. Building Teams have trusted clay brick to bring...
Buildings Teams have long sought to keep water out of buildings, to prevent corrosion, rot, and other damage and to keep building occupants comfortable and dry. Yet only recently has air infiltration also been seen as a...
Learning Objectives After completing this course, you will be able to:
Ambient noise levels in some facility types are trending up and becoming a barrier to clear communication between building occupants. A 2005 study conducted by Ilene Busch-Vishniac, PhD, a dean and professor of mechanical...
Download Complete White Paper Download Introduction Download Chapters 1-4Defining Net-Zero Energy Buildings
Our seventh White Paper on Green Buildings focuses on the role of water in sustainable design and construction. The editors conclude with a set of 21 detailed recommendations for the consideration of the Building Teams, home...
Click here to read BD+C's 2008 White Paper: Green Buildings + Climate Change
Click here to read BD+C's 2007 Green Buildings Research White Paper: Where Building Owners, End Users and AEC Professionals Stand on Sustainability and Green Building
Click here to read BD+C White Paper 2006: Green Buildings and the Bottom Line The ‘New Reality’ of Green Building From Environmental Cause to Financial Opportunity
Click here to read BD+C's Life Cycle Assessment and Sustainability White Paper 2005
It’s time to raise the performance of our existing commercial buildings. To reduce energy consumption. To increase durability. To lessen environmental impact and lifecycle cost. The 4.8 million existing commercial buildings...
Wired glass was the only fire rated glass (FRG) product available for over 100 years. In traditional wired glass, the embedded wires hold annealed glass in place during the fire test to achieve a fire rating. While the wires...
Building project teams involved in design- build and other forms of integrated project delivery (IPD) face new and fast-moving chal- lenges in project team organization, software and hardware, networking, file sharing and...
To benefit from new building design and construction technologies as well as novel project management approaches, leading AEC organizations of all sizes and scales are deploying building information modeling (BIM). While the...

Top Rated Articles

AWARDS

Award Winners
View BD+C’s award-winning projects and people, including our ‘40 Under 40’ superstars, top projects from our Building Team Awards and Reconstruction Awards programs, and the Best AEC Firms to Work For.